CASE STUDY<br />
<strong>Murphy</strong> <strong>Pipe</strong> <strong>and</strong> <strong>Civil</strong><br />
<strong>Constructions</strong> <strong>Pty</strong> <strong>Ltd</strong><br />
In May 2012, <strong>QGC</strong> <strong>Pty</strong> Limited, developer of the Queensl<strong>and</strong> Curtis<br />
LNG Project, awarded a construction contract to <strong>Murphy</strong> <strong>Pipe</strong> <strong>and</strong><br />
<strong>Civil</strong> <strong>Constructions</strong> <strong>Pty</strong> <strong>Ltd</strong> to install gas <strong>and</strong> water gathering pipelines<br />
throughout <strong>QGC</strong>’s gas fields in the Surat Basin.<br />
The initial phase of the contract is worth about A$250 million.<br />
Brisbane-based <strong>Murphy</strong> <strong>Pipe</strong> <strong>and</strong> <strong>Civil</strong> will install high-density<br />
polyethylene pipe to gather <strong>and</strong> transport gas <strong>and</strong> water from wells to<br />
<strong>QGC</strong>’s processing facilities.<br />
The <strong>Murphy</strong> <strong>Pipe</strong> <strong>and</strong> <strong>Civil</strong> contract, which runs for about two years,<br />
complements other work the company is doing for <strong>QGC</strong> through<br />
innovative ‘spider plough’ machinery (shown below) <strong>and</strong> fast-fusion<br />
welding technology.<br />
In 2011, <strong>QGC</strong> awarded a A$120 million contract to Iplex <strong>Pipe</strong>lines to<br />
supply the high-density polyethylene pipe for the gas fields through a<br />
new manufacturing plant at Toowoomba.<br />
The plant is scheduled to reach full production by September 2012.<br />
Quick Facts<br />
• <strong>Murphy</strong> <strong>Pipe</strong> <strong>and</strong> <strong>Civil</strong> is an<br />
Australian pipeline installation<br />
company delivering leading edge<br />
pipeline solutions to the energy,<br />
water <strong>and</strong> mining industries<br />
through a range of innovative <strong>and</strong><br />
purpose-built pipeline equipment.<br />
• The company was established in<br />
2006 <strong>and</strong> has grown rapidly to<br />
boast a skilled workforce of about<br />
450 staff.<br />
• In March 2011, the company<br />
merged with J. <strong>Murphy</strong> <strong>and</strong><br />
Sons – one of the largest civil<br />
construction firms operating in<br />
the United Kingdom.<br />
• Its primary work is installing<br />
pipelines throughout the Surat<br />
Basin in South East Queensl<strong>and</strong>,<br />
<strong>and</strong> it is also constructing largescale<br />
pipeline projects throughout<br />
North West Queensl<strong>and</strong> <strong>and</strong> in<br />
Western Australia.
About <strong>QGC</strong><br />
<strong>QGC</strong> is a leading Australian coal seam<br />
gas explorer <strong>and</strong> producer focused on<br />
developing world-class reserves for<br />
domestic <strong>and</strong> international supply.<br />
Our priority development is QCLNG<br />
– one of Australia’s biggest capital<br />
infrastructure projects <strong>and</strong> the world’s<br />
first liquefied natural gas project<br />
based on gas from coal seams.<br />
We will create an average of 5000<br />
jobs during construction of QCLNG.<br />
<strong>Murphy</strong> <strong>Pipe</strong> <strong>and</strong> <strong>Civil</strong> has indicated that a further 250 people will<br />
be employed to fulfil the contract <strong>and</strong> that it will draw heavily on<br />
its network of Western Downs’ suppliers <strong>and</strong> service providers.<br />
Company Managing Director Jim Campbell says <strong>Murphy</strong> <strong>Pipe</strong> <strong>and</strong><br />
<strong>Civil</strong> has injected more than A$8 million into the Western Downs<br />
economy over the past 12 months.<br />
“This commitment will continue <strong>and</strong> increase thanks to this new<br />
contract,” Mr Campbell said.<br />
Mr Campbell believes the company’s focus on bringing innovative<br />
pipeline solutions to the industry has been key to its success.<br />
“Traditionally, the pipeline industry was all about getting the<br />
client’s pipelines into the ground as quickly as possible, but those<br />
days are gone now,” he said.<br />
“Today, the construction industry is much more accountable<br />
<strong>and</strong> therefore is looking for total pipeline packages that deliver<br />
productivity <strong>and</strong> quality, without compromising the safety of<br />
people, the environment <strong>and</strong> local communities.<br />
“Our company always looks for continuous improvement in our<br />
operations <strong>and</strong> we believe the spider plough <strong>and</strong> fast-fusion<br />
welding technology we have introduced heralds a very positive new<br />
chapter in the history of the pipeline industry,” Mr Campbell said.<br />
QCLNG involves significantly<br />
exp<strong>and</strong>ing <strong>QGC</strong>’s operations in<br />
the Surat Basin <strong>and</strong> transporting<br />
the gas via a 540km underground<br />
pipeline network to Curtis Isl<strong>and</strong>, off<br />
Gladstone, where it will be cooled to a<br />
liquid for transport by ship.<br />
<strong>QGC</strong> also supplies about 20 per cent<br />
of Queensl<strong>and</strong>’s gas dem<strong>and</strong> through<br />
our existing domestic gas business.<br />
Our commitments<br />
We seek to minimise the effects of our<br />
operations on l<strong>and</strong>holders <strong>and</strong> make a<br />
positive contribution to the protection<br />
of the environment.<br />
We run our business in accordance<br />
with government regulations, industry<br />
st<strong>and</strong>ards <strong>and</strong> the access rules that we<br />
agree with l<strong>and</strong>holders.<br />
Our staff, contractors <strong>and</strong> consultants<br />
follow <strong>QGC</strong>’s Code of Conduct,<br />
outlined in our Information for<br />
L<strong>and</strong>holders booklet available via our<br />
website: www.qgc.com.au<br />
Contact details<br />
Please contact <strong>QGC</strong> for more information.<br />
1800 030 443 (toll-free)<br />
email: community@bg-group.com<br />
<strong>QGC</strong> <strong>Pty</strong> Limited<br />
275 George St<br />
Brisbane QLD 4000, Australia