RANGE OF DURATION ESTIMATES<br />
36.00<br />
34.00<br />
MONTHS<br />
32.00<br />
30.00<br />
28.00<br />
26.00<br />
PD<br />
EAC(t) (contractor)<br />
Unconstrained<br />
IEAC(t) (customer)<br />
24.00<br />
22.00<br />
20.00<br />
Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03<br />
TIME<br />
<strong>Analysis</strong><br />
Even though the contractor has provided an<br />
updated schedule estimate, it appears that it<br />
is unachievable. The independent<br />
calculation by the customer results in an<br />
estimated duration <strong>of</strong> just under 34 months,<br />
compared to the contractor’s estimate <strong>of</strong> 25<br />
months.<br />
Recommend calculation <strong>of</strong> a<br />
range <strong>of</strong> durations