Earned Schedule Analysis, A Better Set of Schedule Metrics
Earned Schedule Analysis, A Better Set of Schedule Metrics
Earned Schedule Analysis, A Better Set of Schedule Metrics
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
IPPM<br />
SPI at the End <strong>of</strong> the Project<br />
NOTIONAL DATA<br />
1.2<br />
1.1<br />
Project status:<br />
Project finished 3 months late<br />
Final SPI = 1.00<br />
Final SV$ = 0<br />
There’s got to<br />
be a better<br />
metric!<br />
3 months<br />
1.0<br />
.9<br />
TIME<br />
SPI<br />
.8<br />
Original<br />
Project<br />
Finish<br />
Actual<br />
Project<br />
Finish<br />
6