Earned Schedule Analysis, A Better Set of Schedule Metrics

Earned Schedule Analysis, A Better Set of Schedule Metrics

Earned Schedule Analysis, A Better Set of Schedule Metrics

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

IPPM<br />

SPI at the End <strong>of</strong> the Project<br />

NOTIONAL DATA<br />

1.2<br />

1.1<br />

Project status:<br />

Project finished 3 months late<br />

Final SPI = 1.00<br />

Final SV$ = 0<br />

There’s got to<br />

be a better<br />

metric!<br />

3 months<br />

1.0<br />

.9<br />

TIME<br />

SPI<br />

.8<br />

Original<br />

Project<br />

Finish<br />

Actual<br />

Project<br />

Finish<br />

6