ASO 11000.8<br />

13 Sep 10<br />

Upon final determination of requirements, the FDO and in<br />

conjunction with the AC/S MCCS will determine, using the Facility<br />

Planning Document (FPD) , the best means of satisfying deficiencies<br />

in terms of specific projects. These projects will then be listed<br />

on the Summary for Correction of Deficiencies (NAVFAC Form 10956)<br />

by category (i.e., club, exchange, commissary, or recreation) and<br />

fiscal year and included in the appropriate construction program<br />

submission.<br />

5. Projects Submitted for <strong>MCO</strong>N (APF). Projects proposed for<br />

MILCON funding will go through the review process as described in<br />

reference (n). The FDD will issue a call biannually requesting<br />

candidate MILCON projects four to nine fiscal years in the future.<br />

6. Projects Submitted for MCCS CCF (NAF). Projects proposed will<br />

be developed and forwarded with the required documentation as<br />

outlined in reference (n) to MCCS for inclusion of financial<br />

documentation and forwarding to HQMC (MR) , with a copy to HQMC<br />

(LFF) .<br />

7. Projects Submitted for Local Funding, APF or NAF<br />

a. APF minor construction requests will be submitted per the<br />

annual call for projects as previously described in Chapter 6.<br />

b. NAF minor construction requests will be submitted to the<br />

AC/S MCCS for evaluation and forwarding to FDD for preliminary<br />

design and cost estimating. After project documentation has been<br />

developed,_ it is returned to MCCS for approval and funding as<br />

appropriate.<br />

8. NAF Project Approval Authority<br />

a. Funding Authority<br />

(1) Projects less than $200K are normally budgeted for,<br />

approved, funded, and capitalized at the local level. (The NAF<br />

Construction Committee will consider requests for a lesser amount<br />

on a case-by-case basis depending on the financial wherewithal of<br />

the requesting command) .<br />

(2) Projects less $500K MAY be approved by the<br />

installation commander using solely local funds. If they are over<br />

$200K, they are to be transferred to CMC for depreciation.<br />

Constructions projects between $200K-$500K must be reported to<br />

Congress via OSD.<br />