eceive all directions and instructions from the CPC Engineer, on behalf of<br />
the Contractor.<br />
3.2.7. The Contractor shall supply crane operators, riggers & helpers with the<br />
crane.<br />
3.2.8. Cables, wire slings, I bolts, D - shackles will be supplied by CPC and those<br />
have to be returned before leaving the Refinery premises. Any shortages will<br />
be deducted from the final bill.<br />
3.2.9. Fuel (Diesel) may be supplied to the contractor if requested at the market<br />
price prevailing at the date of filling and total cost of such supplies will be<br />
deducted from the progress payment and final bill. See appendix IV<br />
3.2.10. Selected contractor shall not employ CPC permanent or casual (labor) for<br />
any work included in this tender<br />
3.3. Time schedule and service cost<br />
3.3.1. Shut down is scheduled to be started tentatively in the first half of the July<br />
2012 and the durations will be 33 days; the service will be required only for<br />
10days. However the shutdown time will be change due to unavoidable<br />
circumstance.<br />
3.3.2. Working time during shutdown<br />
Sunday, Monday, Tuesday, Wednesday<br />
Thursday<br />
Friday<br />
0730- 1930 hrs<br />
0730-1630 hrs<br />
3.3.3. Other holidays such as Poya days, mercantile holidays and Public holidays<br />
are considered to be working days during the shutdown period.<br />
3.3.4. Normally Saturdays are holidays. However the selected contractor may have<br />
to work even on Saturdays and long working hours depending on the<br />
criticalness of the Job. No payment will be entitled on Saturdays for<br />
being idling.<br />
3.3.5. The contract shall be carried out on daily & hourly basis for the specified<br />
period as in table-1 all hiring charges shall cover the salaries and other<br />
expenses of operators, supervisor and helpers. Mobilization and<br />
demobilization charges shall include all transport and setting up charges.<br />
Finally the tender shall cover the cost of all the work contributions<br />
stipulated in this document, taxes if applicable, Bidders are strictly advised<br />
to follow the given price schedules. Offers which are not in compliance with<br />
the price schedule will not be considered for evaluation and will be rejected<br />
and if taxes are not mentioned separately, such taxes will be considered as<br />
not relevant for the bid.<br />
3.3.6. All offered rates in the SCHEDULE OF PRICES will not be allowed to change<br />
within the bid validity period due to any change of the prices of fuel and<br />
other consumables in the market.<br />
3.4. Sanitation Facilities<br />
3.4.1. Toilets<br />
Contractor and his employees shall use the toilets and washing facilities<br />
reserved for contractors. No other facilities shall be used by his personnel.<br />