1.21. Labour, Property and Equipment Compensation<br />
1.21.1. CPC is not responsible for labour compensation on any damage. CPC is<br />
expecting from each supplier, all the labours to be insured and Workman<br />
compensation policy document which is issued by government recognized<br />
insurances firm to be submitted before awarding the contract.<br />
1.21.2. The successful bidder will have to pay CPC, as liquidated damages, for<br />
failure to comply with contractor’s obligation to provide the service in the<br />
time guaranteed and amount for each calendar day at the rate of 1% per day<br />
for total payment due. However the maximum liability of the contractor will<br />
not exceed 10% of the total payment.<br />
1.21.3. Additional services that have not been covered in this invitation to bid shall<br />
be clearly stated for CPC’s consideration.<br />
1.22. Defaulted Contractors<br />
1.22.1. Bid offers will not be entertained from firm or persons who have been placed<br />
on the list of defaulted contractors of the CPC.<br />
2. CONDITIONS OF CONTRACT (COC)<br />
2.1. Performance Guarantee<br />
2.1.1. The successful Bidder, on being notified by CPC of the acceptance of his Bid,<br />
shall furnish at his own expense a Performance Guarantee, within (07days)<br />
of such notification through/ confirmed by a recognized Bank in Sri Lanka,<br />
in a sum equivalent to 10% of the accepted Bid. The Performance Guarantee<br />
shall be substantially in the format given in Appendix III<br />
2.1.2. If the successful bidder, fails to furnish the Performance Guarantee as<br />
aforesaid, his name will be placed in the list of defaulting Contractors. CPC<br />
shall therefore, be entitled in its absolute discretion to make suitable<br />
arrangements required for the performance of such Bid, as the case may be,<br />
at the risk and expense of the successful bidder.<br />
2.1.3. The successful bidder, in the event of his failure to furnish the Performance<br />
Guarantee as required, shall be liable for any losses, cost, expenses and<br />
damages, which the CPC may sustain in consequence of such failure, and<br />
the Bid Security Guarantee shall be forfeited.<br />
2.1.4. The Performance Guarantee shall be in favor of the CPC, and shall be valid<br />
for a period not less than 42 days from the works order Issued<br />
2.2. Mode of payment<br />
2.2.1. No advance payment will be made on this contract<br />
2.2.2. Progress/part payments will be paid on the basis of 75% of the value of work<br />
completed. The balance 25% will be retained until the successful<br />
completion of the work.<br />
2.2.3. Part Payment will be made only after finishing first half of the job and<br />
after finishing the second half.<br />