Description Unit Data<br />
WIND GENERATION<br />
Location<br />
Erris, Mayo<br />
Capacity zoned within 25km MW 3000MW approx.<br />
Predicted wind at 100m+ height m/s 10<br />
Capacity factor expected % 52<br />
Required optimum capacity MW 1850<br />
Number of turbines if 3MW rated - 615<br />
class 1, 1A Type<br />
Hub Height m 130+<br />
Turbine separation 360 degrees m 500<br />
Connection to Glinsk kV 110/220 AC XLPE<br />
underground or similar<br />
Projected annual power production TWhr 8.3<br />
ENERGY STORAGE HUB<br />
Operating head m 295.5<br />
Reservoir volume m3 8,900,000<br />
Energy storage capacity<br />
MWhr 6,000/cycle<br />
Minimum drawdown, fill rate hours 6,7<br />
Rated capacity MW 960<br />
Projected annual power storage TWhr 3.25<br />
HVDC TRANSMISSION<br />
Cable Type - Bipole, buried<br />
From location (1,2) - Glinsk, Mayo<br />
To location (1) - AC system Woodland<br />
To location (2) - DC interconnector, Woodland<br />
Cable length km 270 approx<br />
Commutation - Voltage Sourced<br />
Maximum cable power (certified) MW 550<br />
Maximum output combined cables MW 1100<br />
Projected average power MW 1000 for 7400 hours/year<br />
<strong>Organic</strong> <strong>Power</strong> Ltd<br />
Issued September 2011<br />
FBD House, Mardyke Street, Skibbereen,<br />
County Cork, Ireland<br />
Tel: +353 (0)28 51951<br />
E-mail: info@organicpower.ie<br />
Web : www.organicpower.ie