12.05.2015 Views

Monographies - Concrete Layer Innovations

Monographies - Concrete Layer Innovations

Monographies - Concrete Layer Innovations

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

LIMASSOL MARINA<br />

Country<br />

Cyprus<br />

Owner<br />

Lemesos Marina Ltd<br />

Contractor<br />

J&P Athena-Cybarco Marina Lemsou JV<br />

Designer<br />

SOGREAH Consultant<br />

Construction period<br />

2011-2013<br />

CLI’s involvement<br />

Sublicense granted to the Contractor and<br />

technical assistance provided during the<br />

construction<br />

Background<br />

Lemesos Marina Ltd has been granted<br />

permission by the Government of the<br />

Republic of Cyprus for a development<br />

of a Marina resort in Limassol.<br />

The Limassol Marina is an integrated<br />

project including unique residential<br />

island properties.<br />

The luxurious Marina combines the<br />

yachting facilities with residential and<br />

commercial development with<br />

beautiful Mediterranean views for an<br />

exclusive lifestyle.<br />

The Marina Lemesou Joint Venture<br />

between the companies J&P, Cybarco<br />

and Athena has been awarded a<br />

contract for development of the new<br />

Limassol Marina in the south of<br />

Cyprus Island. The main breakwater<br />

which protects the marina is covered<br />

by a revetment<br />

made of ACCROPODE units.<br />

Hydraulic conditions<br />

Length of ACC structure: 1500m<br />

Max. water depth (toe): -11m<br />

Top of the crest: +20m<br />

Design wave Hs: 2.7 m<br />

Wave period Tp: 9 s<br />

ACCROPODE storing yard<br />

3D model test: ARTELIA laboratory in 2010<br />

ACCROPODE Construction aspects<br />

ACCROPODE units produced onsite<br />

Up to 19 line on the slope<br />

10 399 No ACCROPODE units<br />

ACCROPODE placing trial<br />

Placement carried out in 14 months<br />

ACCROPODE sizes:<br />

• 2m 3<br />

• 4m 3<br />

• 5m 3<br />

<strong>Concrete</strong> quantity: 37 697 m 3<br />

ACCROPODE placement


KATTUPALLI L&T SHIPYARD PORT<br />

0 Country<br />

INDIA<br />

Owner<br />

Larsen & Toubro limited<br />

Contractor<br />

ECC division of L&T Limited<br />

Designer<br />

M/s L&T Ramboll Consulting Engineer<br />

Limited<br />

Construction period<br />

2010 - 2012<br />

CLI’s involvement<br />

Sublicense granted to the Contractor and<br />

technical assistance provided during the<br />

construction<br />

Background<br />

The Kattupalli Shipyard Captive Port<br />

Complex is a large shipyard project at<br />

Kattupalli village ( Near Ennore port,<br />

North of Chennai ) being built by L&T<br />

Shipbuilding Ltd. It is being set up<br />

jointly by TIDCO and Larsen & Toubro<br />

(L&T) in two phases.<br />

In terms of cargo generation, the<br />

terminal is located close to the majority<br />

of Container Freight stations in Chennai.<br />

The Kattupalli development also<br />

includes a shipyard being developed by<br />

L&T, a private sector–backed<br />

development.<br />

The ACCROPODE unit first and second<br />

generation were produced onsite. The<br />

core, the underlayer and the units<br />

placement were carried out in two<br />

phases. A transition between<br />

ACCROPODE first and second<br />

generation was also applied on this<br />

project.<br />

Hydraulic conditions<br />

Length of South Bw: 1665m<br />

Length of North Bw: 1775m<br />

Max. water depth (toe): -12m<br />

Top of the crest: +6.5m<br />

Design wave Hs: 5.2 m<br />

Wave period Tp: 17s<br />

Underlayer profiling<br />

3D model test<br />

Cyclone area<br />

ACCROPODE & ACCROPODE II<br />

Construction aspects<br />

ACCROPODE & ACCROPODE II units<br />

produced on site<br />

17 423 No ACCROPODE units<br />

1204 No ACCROPODE II units<br />

ACCROPODE placing<br />

Breakwater built in two phases<br />

from bottom to +3m and from +3m to the top<br />

ACCROPODE sizes:<br />

2.5m 3<br />

4m3<br />

6.3m 3<br />

ACCROPODE II sizes:<br />

4m 3<br />

6m 3<br />

Training in ACCROPODE II<br />

<strong>Concrete</strong> quantity: 72 571 m 3 placing


KHALIF<br />

FA PORT - UAE<br />

Country<br />

UAE<br />

Owner O<br />

Abu Dhabi Port Company (UAE)<br />

Contractor<br />

Archirodon Overseas<br />

Designer D<br />

Halcrow/Han Padron<br />

Construction period<br />

2008 - 2010<br />

CLI’s involvement<br />

ACCROPODE<br />

sublicense,<br />

technical<br />

assistance for testing and technical<br />

assistance during the construction<br />

Typical section of the Main Breakwater<br />

Typical sectionn of the Environmental Breakwater<br />

Background<br />

A consortium led by Archirodon, which<br />

includes<br />

Boskalis<br />

Westminster<br />

and<br />

Hyundai E&C, has been awarded by<br />

Abu Dhabi Port Company the $1500<br />

million turnkey marine works contract<br />

for<br />

the phase 1 of Khalifa Port in Abu<br />

Dhabi.<br />

The multi-purpose maritime facility is<br />

located 5 kms offshore of the<br />

Taweelah<br />

area. The outer works contract involves<br />

the<br />

constructionn of 7.3 kilometres of<br />

breakwaters<br />

and revetments.<br />

Consultants<br />

Han Padron<br />

Associates/Halcrow of New<br />

York<br />

prepared the detailed engineering. The<br />

loading<br />

facilities have to be fully<br />

protected against the waves generated<br />

by<br />

cyclones even with important surge.<br />

An<br />

environmental breakwater protects<br />

the<br />

coral reefs<br />

against possible<br />

accidentally polluted water current.<br />

Archirodon Overseas being in<br />

charge of<br />

the<br />

construction of the breakwaters<br />

and shore protection works has signed<br />

with CLI an ACCROPODE<br />

licence<br />

contract including technical assistance<br />

on<br />

site.<br />

Hydraulic conditions<br />

♦ Total length of ACCROPODE<br />

<br />

structure: 10 000 m<br />

♦ Max. water depth (toe):<br />

- 7.60 m<br />

♦ Top of thee crest: + 5.000 m<br />

ACCROPOD<br />

DE Construction aspects<br />

♦ All ACCROPODE units produced on site<br />

♦ ACCROPODE units placed by standard cranes<br />

♦ Up to 21 lines in the slope<br />

♦ Placementt carried out in<br />

19 months<br />

♦ ACCROPODE sizes :<br />

0,8m3 62000 units<br />

1,5m3 64500 units<br />

2,2m3 20100 units<br />

♦ <strong>Concrete</strong> quantity: 135<br />

000m3<br />

Highlights<br />

armour<br />

♦ Very narrow crested Environmental<br />

Breakwater<br />

tested in Stellenbosh (RSA)<br />

♦ All milestones reached ahead of time<br />

♦ High placement rate with enhanced safety<br />

training for underwaterr placement*<br />

♦ Enhanced quality control with underwater video<br />

records off placement*<br />

* by specially trained diving<br />

company<br />

Placement at sea level<br />

Narrow<br />

crested<br />

Environmental Breakwater<br />

Underwaterr view with fish<br />

colonization


FORT JALALI REVETMENT<br />

Contractor<br />

Country<br />

OMAN<br />

Owner<br />

The Royal Court<br />

Contractor<br />

Sarroj Construction Company LLC<br />

Designer<br />

WS Atkins (Muscat)<br />

Construction period<br />

2008 - 2009<br />

CLI’s involvement<br />

Sublicense granted to the Contractor<br />

and technical assistance provided<br />

during the construction<br />

Background<br />

Further to GONU cyclone the original<br />

SHED revetment had been totally<br />

destroyed. The Royal Court decided to<br />

repair the protection in order to<br />

withstand to exceptional cyclonic<br />

conditions.<br />

After a study performed in in<br />

Wallingford, the ACCROPODE unit<br />

was selected for its intrinsic robustness<br />

and its capacity to resist to the highest<br />

waves conditions, for the construction<br />

of the new revetment.<br />

Before and during the construction,<br />

special advises were given by CLI for<br />

the toe design that is essential for the<br />

stability of the whole armouring.<br />

The CLI commitment consisted in<br />

providing both, technological solution<br />

and a specific technical support to the<br />

Contractor by sending a specialist on<br />

site during the construction period.<br />

Hydraulic conditions<br />

♦<br />

♦<br />

♦<br />

♦<br />

♦<br />

♦<br />

♦<br />

Length of breakwater: 300 m<br />

Sea bed level: -7.5m CD<br />

Top of the crest: +12.4 m<br />

Design wave Hs: 8.4 m (Gonu conditions)<br />

Wave period Tp: 18 s<br />

MHHW +2.6 m<br />

HAT: +3.3m<br />

ACCROPODE Construction aspects<br />

♦ ACCROPODE units selected<br />

♦ Up to 12 lines in the slope<br />

♦ Placing by land base crane<br />

♦ Specific reinforced toe using the old big crest<br />

concrete blocks reinforced with rocks<br />

♦ ACCROPODE size:<br />

16.0m3: 901 units<br />

<strong>Concrete</strong> quantity: 14 416m3<br />

ACCROPODE unit placement<br />

ACCROPODE revetment<br />

Old crest wall blocs that had<br />

been placed as toe blocs on the<br />

new structure


RAS LAFFAN PORT EXPANSION<br />

Contractor<br />

Country<br />

Qatar<br />

Owner<br />

Qatar Petroleum<br />

Contractor<br />

Jan De Nul Dredging Ltd. – Boskalis<br />

Westminster Middle East Ltd. J.V.<br />

Designer<br />

Sogreah Consultant<br />

Construction period<br />

2007 - 2008<br />

CLI’s involvement<br />

Sublicense granted to the Contractor<br />

and technical assistance provided<br />

during the construction<br />

Background<br />

The project is located at the North east<br />

of Qatar, in the RAS LAFFAN Industrial<br />

city. The project consisted in the<br />

construction of two new breakwaters<br />

for the LNG PORT breakwaters in order<br />

to shelter the future LNG facilities.<br />

These breakwaters are protected with<br />

artificial armour units such as cubes<br />

and ACCROPODE units. The<br />

ACCROPODE technology was selected<br />

to be placed at the most exposed areas<br />

of the two structures (north and south<br />

breakwaters).<br />

The ACCROPODE placing had to be<br />

carried out in a very tight schedule.<br />

Several positioning systems were used<br />

in order to save time and increase the<br />

placing rate:<br />

• POSIBLOC system<br />

• ECHOSCOPE sonar<br />

• Video cameras<br />

Hydraulic excavators were also used in<br />

order to increase the placing rate.<br />

All of the units were fabricated in<br />

Ajman (U.A.E) and shipped over during<br />

the construction.<br />

Hydraulic conditions<br />

♦ Length of ACCROPODE protection: 4400m<br />

♦ Max. water depth (toe):-13m<br />

♦ Top of the crest: +8.9m<br />

♦ Design wave Hs: 4.6 m<br />

♦ Wave period Tp: 11 s<br />

♦ HAT +1.86m<br />

♦ 3D model tests: in Sogreah and DHI<br />

ACCROPODE Construction aspects<br />

♦ 70 000 ACCROPODE units fabricated<br />

♦ Fabrication abroad<br />

♦ Transport of the units by barges.<br />

♦ Up to 24 lines in the slope (+4 on crest)<br />

♦ Placement carried out in 9 months<br />

♦ ACCROPODE sizes:<br />

3m3<br />

4m3<br />

5m3<br />

♦ <strong>Concrete</strong> quantity: 250 000m 3<br />

POSIBLOC<br />

positioning system<br />

Placing with ECHOSCOPE<br />

Layout of the project


GANGAVARAM PORT<br />

Contractor<br />

Country<br />

INDIA<br />

Owner<br />

Port of Gangavaram<br />

Contractor<br />

Larsen & Toubro<br />

Designer<br />

Larsen & Toubro - Ramboll<br />

Construction period<br />

2007 - 2009<br />

CLI’s involvement<br />

Sublicense granted to the Contractor<br />

and technical assistance provided<br />

during the construction<br />

Background<br />

The two breakwaters have been<br />

constructed in difficult sea conditions<br />

(important wave agitation and poor<br />

visibility below water).<br />

The use of permanent divers was<br />

decided in order to allow the proper<br />

positioning of the units even with poor<br />

visibility condition.<br />

CLI provided GPS referenced placing<br />

drawings to be used directly with the<br />

crane DGPS system.<br />

CLI has provided technical assistance<br />

on site by sending a specialist to advise<br />

on fabrication and placement of the<br />

ACCROPODE units.<br />

Hydraulic conditions<br />

♦ Length of NBW (ACCROPODE): 810 m<br />

♦ Length of SBW (ACCROPODE): 1740 m<br />

♦ Max. water depth (toe): -14 m<br />

♦ Top of the crest: +8.7 m<br />

♦ Design wave Hs: 7.6m<br />

♦ Wave period Tp: 10 s<br />

♦ HWL +1.80 m<br />

♦ Cyclone possible<br />

ACCROPODE Construction aspects<br />

♦ 11698 ACCROPODE units<br />

♦ Up to 16 lines in the slope<br />

♦ Placing with DGPS system<br />

♦ Placement rate by crane: units/day<br />

♦ ACCROPODE sizes:<br />

2.5m 3 : 1879 units<br />

4m 3 : 1890 units<br />

6.3m 3 : 4335 units<br />

9m 3 : 2439 units<br />

12m 3 : 1155 units<br />

♦ <strong>Concrete</strong> quantity: 76720m3<br />

ACCROPODE casting yard<br />

ACCROPODE storing yard<br />

ACCROPODE placing


SINT-MARTEEN PORT EXPANSION<br />

Country<br />

Sint-Marteen, Netherlands Antilles<br />

Owner<br />

The Sint-Marteen Harbour Holding<br />

Company N.V<br />

Contractor<br />

BNPA Joint Venture (Ballast Nedam<br />

V.O.F. & per Aarsleff A/S)<br />

Construction period<br />

2007- 2009<br />

CLI’s involvement<br />

Sublicense granted to the<br />

Contractor and technical assistance<br />

provided during the construction<br />

Breakwater layout 3D artistic rendering Cross-section<br />

Background<br />

The expansion at the harbour entailed<br />

mainly an extension of the berthing<br />

facility, deepening of the waterfront<br />

area by the cargo pier, a new cruise<br />

jetty and the deepening of the cargo<br />

basin.<br />

The new reclamation of the cargo<br />

expansion area is protected by a<br />

breakwater covered with a single layer<br />

of ACCROPODE amour units.<br />

Two ACCROPODE sizes are used to<br />

protect this structure: 12m 3 and 16m 3<br />

The Cruise area consists in building a<br />

new reclaimed zone. The new jetty is<br />

able to receive two more cruise liners.<br />

The polder located root of jetty is<br />

protected by single layer armouring of<br />

6.3m3 ACCROPODE units.<br />

The breakwaters are protected with<br />

ACCROPODE. About 956 units<br />

representing 9895m3 of armour<br />

concrete.<br />

Hydraulic conditions<br />

♦ Max. waterdepth : 14.50m<br />

♦ Design wave Hs: 6.7 m<br />

♦ Wave period Tp: 13 s<br />

Construction aspects<br />

♦ 6 ACCROPODE moulds of<br />

6.3m 3<br />

♦ 4 ACCROPODE moulds of<br />

12m3<br />

♦ 2 ACCROPODE moulds of<br />

16m3<br />

♦ 7 site visits by CLI at the<br />

important stages of the armour<br />

construction<br />

ACCROPODE casting yard<br />

During placement<br />

Underwater ACCROPODE inspection


SALALAH CONTAINER PORT EXPANSION<br />

Contractor<br />

Country<br />

OMAN<br />

Owner<br />

Ministry of Transport and<br />

Communication<br />

Contractor<br />

ARCHIRODON Construction (overseas)<br />

Designer<br />

Consulting Engineering Services LLC<br />

Construction period<br />

2006 - 2009<br />

CLI’s involvement<br />

Sublicense granted to the Contractor<br />

and technical assistance provided<br />

during the construction<br />

Background<br />

Hydraulic conditions<br />

The OMANIES Port Authorities have<br />

decided to expand the SALALAH port in<br />

order to increase the container traffic.<br />

Salalah is located on a strategic route<br />

linking the middle east to the far est.<br />

This new breakwater protects the new<br />

facilities of the Salalah port.<br />

♦<br />

♦<br />

♦<br />

♦<br />

♦<br />

♦<br />

Length of breakwater: 2 825 m<br />

Sea bed level: -13m to -20m CD<br />

Top of the crest: +12.7 m<br />

Design wave Hs: 7 m<br />

Wave period Tp: 8.9 s<br />

MHHW +1.68 m<br />

Crown wall<br />

The breakwater was built in difficult sea<br />

conditions (important wave agitation<br />

especially during monsoon period).<br />

Most of the work was performed by<br />

marine equipment due to the<br />

configuration of the breakwater.<br />

The checking of the proper<br />

ACCROPODE units positioning under<br />

the sea level was performed thanks to<br />

divers.<br />

The CLI commitment consisted in<br />

providing the technological solution and<br />

support to the Contractor by handing<br />

over the documentation and sending a<br />

specialist.<br />

ACCROPODE Construction aspects<br />

♦ 15 045 ACCROPODE units<br />

♦ Up to 15 lines in the slope<br />

♦ Placing by barge and land base crane<br />

♦ ACCROPODE size:<br />

12.0m3: 15 045 units<br />

<strong>Concrete</strong> quantity: 180 540m3<br />

Casting yard<br />

Placing trial


ORTONA PORT EXPANSION<br />

Country<br />

Italy<br />

Owner O<br />

City of Ortonaa<br />

Contractor<br />

SVILUPO Ortona Porto (Sidra/Nicolaj)<br />

Designer D<br />

Modimar<br />

Construction period<br />

October 2007 – September 2009<br />

CLI’s involvement<br />

Sublicense granted to the Contractor<br />

and technical assistance provided<br />

during the construction<br />

O<br />

4<br />

3<br />

+3.75<br />

4<br />

3<br />

ACCROPODE TM 12<br />

0.00 l.m.m.<br />

ACCROPODE TM 4 m³<br />

12 m³<br />

0.00 l.m.m.<br />

3<br />

2<br />

-9.85<br />

-9.70<br />

var. -9.05/-9.30<br />

var. -10.10/-10.35<br />

3<br />

2<br />

Background<br />

This part of the breakwater was<br />

constructed right after the completion<br />

of the first phase. The city of Ortona<br />

has decided to lengthen the main<br />

breakwater by 450m and increase the<br />

altitude of the top crest.<br />

This phase has been tested in<br />

Laquila<br />

at the Universtity laboratory (LIAM) in<br />

October 2007.<br />

The Contractor also checked the<br />

damage that could happen on<br />

the<br />

breakwater at the construction stage.<br />

The breakwater consists in a rubble<br />

mound covered with an ACCROPODE<br />

revetment.<br />

Hydraulic conditions<br />

♦ Length of f CL structure: 447m<br />

♦ Max. water depth (toe):-12m<br />

♦ Top of thee crest: +5.25m<br />

♦ Design wave Hs: 7.2 m<br />

♦ Wave period Tp: 10.9<br />

ACCROPOD<br />

DE Construction aspects<br />

♦ ACCROPODE units produced at sitee<br />

♦ 4084 ACCROPODE units with the sizes ranging<br />

from 4m33 to 12m3 for the round head.<br />

♦ Rock toe and ACCROPODE toe<br />

♦ Service quay in the armour<br />

Temporary round head of<br />

the breakwater<br />

Storing and placement on<br />

the breakwter<br />

ACCROPODE casting yard


ORTONA PORT EXPANSION<br />

Country<br />

Italy<br />

Owner O<br />

City of Ortonaa<br />

Contractor<br />

SVILUPO Ortona Porto (Sidra/Nicolaj)<br />

Designer D<br />

Modimar/Med.IF SRL/DEAM SRL<br />

Construction period<br />

2005 - 2007<br />

CLI’s involvement<br />

Sublicense granted to the Contractor<br />

and technical assistance provided<br />

during the construction<br />

+4.08<br />

4<br />

LATO MARE<br />

+1.70<br />

3<br />

ACCROPODE TM 6.3 m³<br />

+0.10<br />

ACCROPODE TM 6.3 m³<br />

0.00 l.m.m<br />

2<br />

3<br />

-7.80<br />

-7.80<br />

3<br />

2<br />

Background<br />

The city of Ortona has created a major<br />

breakwater in the view of protecting<br />

the<br />

new quays at of the extension of<br />

Ortona Port.<br />

The breakwater consists in a rubble<br />

mound covered with an ACCROPODE<br />

revetment.<br />

Hydraulic conditions<br />

♦ Length of f CL structure: 813m<br />

♦ Max. water depth (toe):-10m<br />

♦ Top of thee crest: +4.10m<br />

♦ Design wave Hs: 7.2 m<br />

♦ Wave period Tp: 10.9<br />

ACCROPOD<br />

DE Construction aspects<br />

♦ ACCROPODE units produced at sitee<br />

♦ 5800 ACCROPODE units of4m3 andd 6.3m3<br />

♦ Rock toe<br />

♦ Transitionn with Tetrapodes<br />

Temporary round head of<br />

the breakwater<br />

Storing and placement on<br />

the breakwter<br />

ACCROPODE casting yard


ONEGLIA EXPANSION PORT MAIN BREAKWATER<br />

Country<br />

Italy, Liguria<br />

Owner<br />

Imperia community<br />

Contractor<br />

IDRESIA S.R.L.<br />

Designer<br />

Dott Ing Valentino CASTELLINI<br />

Dott Ing Lorenzo GRASANNO<br />

Construction period<br />

2005 - 2006<br />

CLI’s involvement<br />

Sublicense granted to the Contractor<br />

and technical assistance provided<br />

during the construction<br />

Background<br />

The Commune di Imperia has decided to<br />

extend the port of Oneglia by lengthening<br />

the main breakwater of 160m and creating<br />

a secondary breakwater next to a new<br />

quay. These operations targeted to<br />

increase the length of quays available and<br />

decrease the agitation in the port. In order<br />

to carry out this project, one company was<br />

awarded for each of the two breakwaters.<br />

The Idresia company was in charge of the<br />

main breakwater and the SET company<br />

was in charge of the secondary<br />

breakwater. Both of the structures were<br />

covered by ACCROPODE units. The main<br />

breakwater was protected by 3m3 and<br />

4m3 ACCROPODE units. The fabrication<br />

yard was located a few kilometres away<br />

from the breakwaters. The units were<br />

placed by land by using a crane and<br />

excavators.<br />

Hydraulic conditions<br />

♦ Length of CL structure: 165m<br />

♦ Max. water depth (ACCROPODE toe):-5.5m<br />

♦ Max. water depth of the whole structure: -10m<br />

♦ Top of the crest: +5.5m<br />

♦ Design wave Hs: 6.2 m<br />

♦ Wave period Tp: 12s<br />

ACCROPODE units aspects<br />

♦ 2649 ACCROPODE units of 3m3<br />

♦ 416 ACCROPODE units of 5m3<br />

♦ Placement by crane and excavator<br />

Storage area<br />

Rock toe placement<br />

ACCROPODE units<br />

placement under progress


MAP TA PHUT PHASE II (Cooling water intake)<br />

Country<br />

Thailand<br />

Owner<br />

BLPC power ltd<br />

Contractor<br />

ITALTHAI<br />

Consultant<br />

MITSUBISHI Corp.<br />

Construction period<br />

April 2005 -<br />

CLI’s involvement<br />

Sublicense granted to the contractor<br />

and technical services provided during<br />

casting and placement of the<br />

Accropode armour units.<br />

Background<br />

Map Ta Phut industrial port phase<br />

II works include the construction<br />

of marine works to protect the<br />

new coal power plant located on<br />

the west side of the reclaimed<br />

outer revetment .<br />

Protection of the intake basin and<br />

entrance consists in building<br />

approx 500m long rubble mound<br />

structures.<br />

Selected Acrropode unit sizes:<br />

2.0m³ and 2.5m³ (for the 90°<br />

bends).<br />

Total volume of armour concrete<br />

placed: 6 000m³.<br />

Hydraulic conditions<br />

♦ Max water depth: -4.5m<br />

♦ Design wave Hs: 4.3m<br />

♦ Wave period: 8 sec<br />

♦ Crest level: +7.4m<br />

Construction aspects<br />

♦ 12 new moulds made locally<br />

and 12 existing ones (2m³) re –<br />

used from phase I works.<br />

♦ Land - based crawler crane<br />

Amhoist equipped with DGPS<br />

theoretical placement drawings<br />

provided by CLI.<br />

♦ 7 months precasting period.<br />

♦ 4 site visits by CLI at the<br />

important stages of the armour<br />

construction.<br />

2m³ moulds ready for casting<br />

View of the outlet area in progress


Morocco - New Tangiers Mediterranean Port<br />

ACCROPODE TM Technical Assistance<br />

Country<br />

Morocco<br />

Client<br />

Société pour la Réalisation<br />

du Port de Tanger<br />

Méditerranée (SRPTM)<br />

Date<br />

2003-2006<br />

Sogreah's services<br />

Transfer of the rights to use the<br />

ACCROPODE technique<br />

Technical assistance to the<br />

Contractor for ACCROPODE<br />

block fabrication and placing<br />

Description<br />

Main breakwater: 965 m long<br />

connected to quarterfoil<br />

caissons extending the<br />

breakwater by approx. 1100 m.<br />

The main structure is protected<br />

by ACCROPODE blocks as<br />

follows:<br />

. 4 m 3 blocks from the root over<br />

a length of approx. 200 m,<br />

. 9 m 3 blocks over 320 m,<br />

. 16 m 3 blocks over 445 m up to<br />

the junction with the caissons.<br />

The structure is built in water<br />

depths ranging from 2 to 20 m,<br />

and has a crest level at + 14.00<br />

TGZ.<br />

Secondary breakwater: 470 m<br />

long.<br />

Protected over a distance of<br />

300 m by 9 m 3 ACCROPODE<br />

blocks and over 170 m by 4 m 3<br />

ACCROPODE blocks up to the<br />

junction with the caisson.<br />

Sogreah's role<br />

After having assisted the<br />

Contractor in finalising the design<br />

through 2D and 3D testing,<br />

Sogreah provided additional<br />

technical assistance during<br />

construction in the form of:<br />

Technical specifications<br />

for ACCROPODE block<br />

fabrication and placing;<br />

Form drawings for<br />

ACCROPODE block<br />

fabrication;<br />

Placing drawings for the<br />

ACCROPODE blocks, and files<br />

of GPS coordinates indicating<br />

the centre of gravity of each<br />

ACCROPODE block, adapted<br />

to suit the placing method<br />

selected by the Contractor;<br />

Technical assistance onsite<br />

and from head office<br />

for ACCROPODE block<br />

fabrication and placing.<br />

Quantities<br />

Total concrete volume 79 900 m 3 ,<br />

of which:<br />

. 9 950 m 3 in 4 m 3 blocks;<br />

. 31 120 m 3 in 9 m 3 blocks;<br />

. 38 830 m 3 in 16 m 3 blocks.<br />

SETS/MFS/0106


Venice - Malamocco offshore breakwater<br />

Country<br />

Italy<br />

Owner<br />

Consorzio Venezia Nuova<br />

Contractor<br />

Mantovani S.PA.<br />

Design<br />

Technital<br />

Date<br />

2003-2005<br />

Sogreah's services<br />

◗ Technical assistance in the<br />

framework of a licence<br />

agreement for use of the<br />

ACCROPODE technique<br />

03/05 SETS<br />

Background<br />

In the framework of the MOSE<br />

project, aimed at protecting<br />

Venice from high tides, a series of<br />

works have been carried out in<br />

the lagoon and its three inlets. The<br />

specific purpose of these works is<br />

to create mobile barriers at each<br />

inlet that will close off the lagoon<br />

during high tides. Since these<br />

barriers are unable to withstand<br />

very large waves, the lagoon inlets<br />

had to be protected with offshore<br />

breakwaters.<br />

The Malamocco entrance<br />

channel is the closest one to<br />

Venice and is also a point of<br />

access to the Mestre crude oil<br />

terminal.<br />

Services provided by Sogreah<br />

Throughout the works, Sogreah<br />

provided technical assistance to<br />

the contractor.<br />

This involved supplying the<br />

technical information required<br />

in order to implement the<br />

ACCROPODE technique<br />

correctly and to train the placing<br />

teams. Placing drawings were<br />

drawn up in close collaboration<br />

with the Contractor, in order to<br />

take account of the equipment<br />

being used and the anticipated<br />

placing schedule.<br />

A Sogreah expert visited the site<br />

several times in order to ensure<br />

that the ACCROPODE technique<br />

had been implemented correctly<br />

and to improve the placing rate<br />

and quality.


Port of Rawson<br />

Country<br />

Argentina<br />

Client<br />

Dyopsa<br />

Date<br />

2001-2003<br />

Sogreah’s services<br />

◗ Technical assistance during 3D<br />

tests at the DHI<br />

◗ Granting of right to use the<br />

ACCROPODE technique<br />

◗ Technical assistance during<br />

fabrication and placing of the<br />

ACCROPODE blocks<br />

SETS 09/04<br />

Background<br />

Construction of two breakwaters<br />

265 m and 544 m long designed<br />

to facilitate entrance to the port<br />

of Rawson. The port of Rawson<br />

is situated in southern Argentina<br />

near the Valdes peninsula.<br />

The design wave is Hs = 4.2 m.<br />

The structure was protected by<br />

a single-layer armour of 1.0 m³,<br />

2.0 m³ and 3.0 m³ ACCROPODE<br />

blocks on the roundhead in water<br />

up to 2.5 m deep.<br />

Sogreah’s role<br />

During the works, Sogreah<br />

provided technical assistance in<br />

the form of:<br />

◆ Technical drawings and<br />

information required for the<br />

proper construction of the<br />

structure.<br />

◆ Drawings and printouts of polar<br />

coordinates for automatic<br />

placing of the ACCROPODE<br />

blocks.<br />

◆ Technical assistance on line and<br />

on site for the fabrication and<br />

placing of the ACCROPODE<br />

blocks. Four site visits were<br />

carried out.<br />

Key figures:<br />

Southern breakwater:<br />

◆ Unit size of blocks: 2 m³<br />

Number of blocks placed: 3122<br />

◆ Unit size of blocks: 3 m³<br />

Number of blocks placed: 660<br />

◆ Total volume: 8224 m³<br />

Northern breakwater:<br />

◆Unit size of blocks: 1 m³<br />

Number of blocks placed: 3036<br />

◆ Unit size of blocks: 2 m³<br />

Number of blocks placed: 714<br />

◆ Unit size of blocks: 3 m³<br />

Number of blocks placed: 536<br />

◆ Total volume: 6072 m³


Port 2000, the new container terminal at Le Havre<br />

Construction of protective breakwaters<br />

Country<br />

France<br />

Client<br />

DPAM2000 consortium (GTM<br />

terrassement, Campenon<br />

Bernard, Dredging<br />

International, Vinci)<br />

Owner<br />

Port of Le Havre Authority<br />

Date<br />

2002-2005<br />

© Patrice Lefebvre<br />

Sogreah's services<br />

◗ Granting of right to use the<br />

ACCROPODE technique<br />

◗ Technical assistance throughout<br />

the fabrication and placing of<br />

the ACCROPODE blocks<br />

Background<br />

The breakwaters, totalling 6000 m,<br />

are divided into three sections. The<br />

northern and western structures<br />

protect the entrance to the port<br />

and are the most exposed. The<br />

entrance channel consists of<br />

two concrete caissons against<br />

which the breakwaters abut. The<br />

southern breakwater protects the<br />

quays and reclamation areas of<br />

the terminal. The northern and<br />

western breakwaters are levelled<br />

at +13.35 m CMH and are faced<br />

with 2 and 3 m 3 ACCROPODE <br />

blocks, while the southern<br />

breakwater is levelled at +12.55 m<br />

CMH and is faced with 1.5m 3<br />

blocks.<br />

Sogreah's role<br />

After assisting the consortium that<br />

was awarded the works to finalise<br />

the design and carry out 3D scalemodel<br />

tests on the western and<br />

southern breakwaters, Sogreah<br />

provided technical assistance<br />

during the works in the form of:<br />

◆ provision of drawings and<br />

technical information needed<br />

to ensure proper construction of<br />

the breakwaters,<br />

◆ provision of the drawings<br />

and GPS files for placing<br />

the ACCROPODE blocks in<br />

accordance with the placing<br />

method chosen by the<br />

contractor,<br />

SETS 01/05<br />

◆ technical assistance on line and<br />

on site with the fabrication and<br />

placing of the ACCROPODE <br />

blocks.<br />

Key figures:<br />

◆ 1.5 m 3 ACCROPODE blocks<br />

Theoretical number of blocks:<br />

26 150<br />

◆ 2 m 3 ACCROPODE blocks<br />

Theoretical number of blocks:<br />

3730<br />

◆ 3 m 3 ACCROPODE blocks<br />

Theoretical number of blocks:<br />

2260<br />

◆ Total volume: 53 465 m 3


La Esfinge<br />

Country<br />

Spain (Canary Islands)<br />

Client<br />

FCC Construction, S.A.<br />

Date<br />

2002-2003<br />

Sogreah’s services<br />

◗ Granting of right to use the<br />

ACCROPODE technique<br />

◗ Technical assistance during tests<br />

at the CEDEX in Madrid<br />

◗ Technical assistance during<br />

fabrication and placing of the<br />

ACCROPODE blocks<br />

SETS 09/04<br />

Background<br />

Construction of the 300 m long<br />

main breakwater situated at<br />

Las Palmas in the north of Gran<br />

Canaria island, with a design<br />

wave of Hs = 7.7 m. The structure<br />

was protected by a single-layer<br />

armour of 12 m³ ACCROPODE<br />

blocks in water up to 20 m deep.<br />

Sogreah’s role<br />

After assisting the client during<br />

finalisation of the design and<br />

3D hydraulic scale-model tests<br />

in Madrid, Sogreah provided<br />

technical assistance to the<br />

contractor during the works in the<br />

form of:<br />

◆ Technical drawings and<br />

information required for the<br />

proper construction of the<br />

structure.<br />

◆ Drawings and printouts of polar<br />

coordinates for automatic<br />

placing of the ACCROPODE<br />

blocks, in accordance with the<br />

contractor’s working method.<br />

◆ Technical assistance on line and<br />

on site for the fabrication and<br />

placing of the ACCROPODE<br />

blocks. Four technical assitance<br />

visits were carried out on site.<br />

Key figures<br />

◆ Unit size of blocks: 12 m³<br />

Number of blocks placed: 1120<br />

◆ Total volume: 13 440 m³


Expansion project for the port of Bourgas<br />

Country<br />

Bulgaria<br />

Client<br />

Penta-Ocean Construction /<br />

Mitsubishi J.V.<br />

Date<br />

2001 - in progress<br />

Sogreah’s services<br />

◗ Granting of right to use the<br />

ACCROPODE technique<br />

◗ Technical assistance during<br />

fabrication and placing of the<br />

ACCROPODE blocks<br />

SETS 09/04<br />

Background<br />

Construction of the main 1200 m<br />

long breakwater on the Black<br />

Sea, with a design wave of Hs =<br />

4.2 m. The structure is protected<br />

by a single-layer armour of 2 m³<br />

ACCROPODE blocks on the<br />

running section and 3 m³ blocks<br />

on the roundhead, in water up to<br />

12 m deep.<br />

Sogreah’s role<br />

During the works, Sogreah is<br />

providing technical assistance in<br />

the form of:<br />

◆ Technical drawings and<br />

information required for the<br />

proper construction of the<br />

structure.<br />

◆ Drawings and printouts of polar<br />

coordinates for automatic<br />

placing of the ACCROPODE<br />

blocks.<br />

◆ Technical assistance on line and<br />

on site for the fabrication and<br />

placing of the ACCROPODE<br />

blocks. Six site visits are planned.<br />

Key figures:<br />

◆ Unit size of blocks: 2 m³<br />

Number of blocks placed: 8500<br />

◆ Unit size of blocks: 3 m³<br />

Number of blocks placed: 1600<br />

◆ Total volume: 21 800 m³


Fregate Island<br />

Reconstruction of the harbour breakwater<br />

Country<br />

Seychelles<br />

Client<br />

Interbeton (The Netherlands)<br />

Date<br />

2000<br />

Sogreah's services<br />

◗ Licence to use the<br />

ACCROPODE ® technique<br />

◗ Technical assistance during<br />

ACCROPODE ® block casting<br />

and placing.<br />

04/01 MFN<br />

Context<br />

The project involves rebuilding<br />

the breakwater protecting the<br />

harbour on Fregate Island, which<br />

is located in the Seychelles<br />

Archipelago.<br />

The 250 m long breakwater is<br />

protected by an armour facing<br />

made of 2 m 3 ACCROPODE ®<br />

blocks.<br />

Sogreah's role<br />

Sogreah provided technical<br />

assistance to the contractor<br />

during the works, including the<br />

following:<br />

◆ Provision of technical<br />

information required for the<br />

successful completion of the<br />

structure.<br />

◆ Technical assistance on site with<br />

casting and placing the<br />

ACCROPODE ® blocks.<br />

◆ Supply of positioning drawings<br />

for the ACCROPODE ® armour.<br />

Sogreah also provided project<br />

design assistance.<br />

Key figures<br />

◆ 2 m 3 ACCROPODE ® blocks<br />

Number of units placed: 966<br />

Volume of concrete (m 3 ): 1932<br />

◆ Total<br />

Number of units placed: 966<br />

Volume of concrete 1932


Tuen Mun - Hong Kong<br />

Container terminal RTT 38<br />

Country<br />

China (Hong Kong)<br />

Client<br />

River Trade Terminal Co Ltd<br />

Contractor<br />

Scott Wilson<br />

(Hong Kong) Ltd<br />

Date<br />

1999<br />

03/01 MFN<br />

Sogreah's services<br />

◗ Licence to use the<br />

ACCROPODE ® technique<br />

◗ Technical assistance during<br />

casting and placing of<br />

ACCROPODE ® blocks<br />

Background<br />

The purpose of this container<br />

terminal, which is situated in the<br />

New Territories, is to decongest<br />

container traffic in Hong Kong<br />

itself, and at the same time<br />

reduce traffic on the roads and<br />

mitigate environmental impacts.<br />

The project involved the<br />

construction of a 65 ha landfill<br />

platform offering 3000 linear<br />

metres of berthing facilities.<br />

The landfill is protected against<br />

cyclonic waves by two<br />

breakwaters, one of which is<br />

built offshore. The breakwaters<br />

themselves are protected by a<br />

facing of 2.5 et 3 m 3<br />

ACCROPODE ® blocks.<br />

Design criteria<br />

The breakwaters were sized to<br />

withstand the following design<br />

waves:<br />

◆ Return period: 100 years<br />

◆ H s = 4.2 m<br />

◆ T p = 7 sec<br />

Sogreah's role<br />

Sogreah provided technical<br />

assistance to the contractor<br />

throughout the works, including<br />

the provision of technical<br />

information required to build the<br />

structures, on-site assistance with<br />

block casting and placing, and<br />

preparation of positioning<br />

drawings for the ACCROPODE ®<br />

blocks.<br />

Previous services provided by<br />

Sogreah<br />

Technical assistance to the<br />

designer in sizing the<br />

ACCROPODE ® armour.<br />

Key figures<br />

◆ 2.5 m 3 blocks<br />

Number of units placed: 8986<br />

Volume of concrete (m 3 ): 22 465<br />

◆ 3 m 3 blocks<br />

Number of units placed: 2425<br />

Volume of concrete (m 3 ): 7275<br />

◆ Total<br />

Number of units placed: 11 411<br />

Volume of concrete (m 3 ): 29 740


Hammamet south marina<br />

Country<br />

Tunisia<br />

Client<br />

Entreprise ETEP<br />

Date<br />

1998-2000<br />

Sogreah's services<br />

◗ Wave-flume stability study for the<br />

offshore breakwater<br />

◗ Wave-tank stability study for the<br />

southern roundhead of the<br />

offshore breakwater<br />

◗ Technical assistance during<br />

fabrication and placing of the<br />

ACCROPODE ® blocks<br />

06/01 MFN<br />

Background<br />

The Owner, SEAMHS (Société<br />

d’Etudes et d’Aménagement de<br />

la Marina de Hammamet Sud),<br />

commissioned ETEP to carry out<br />

maritime works as part of the<br />

Hammamet south marina<br />

construction project.<br />

The marina is protected by a<br />

main offshore breakwater with a<br />

facing of 2.5 m 3 , 4 m 3 and<br />

6.3 m 3 ACCROPODE ® blocks, and<br />

a so-called northern breakwater<br />

made of rockfill. An artificial<br />

beach has been created to the<br />

south by the partly submerged<br />

southern breakwater. This is also<br />

made of rockfill, and only the<br />

roundhead, which is protected<br />

by 2.5 m 3 ACCROPODE ® blocks,<br />

emerges above the water level.<br />

Sogreah's role<br />

Sogreah provided technical<br />

assistance to the contractor<br />

during the works, including:<br />

◆ supplying the necessary<br />

technical information for<br />

building the structure,<br />

◆ site visits to provide technical<br />

assistance with fabricating and<br />

placing the ACCROPODE ®<br />

blocks,<br />

◆ preparing placing drawings for<br />

the ACCROPODE ® blocks.<br />

Key figures<br />

◆ 2.5 m 3 blocks<br />

Number of blocks placed: 2066<br />

Volume of concrete (m 3 ): 5165<br />

◆ 4 m 3 blocks<br />

Number of blocks placed: 2177<br />

Volume of concrete (m 3 ): 8708<br />

◆ 6.3 m 3 blocks<br />

Number of blocks placed: 466<br />

Volume of concrete (m 3 ): 2796<br />

◆ Total<br />

Number of blocks placed: 4709<br />

Volume of concrete (m 3 ): 16 669


La Goulette harbour<br />

Consolidation of the northern jetty<br />

Country<br />

Tunisia<br />

Owner<br />

Office National des Ports de<br />

Tunisie (O.N.P.T.)<br />

Contractor<br />

SOMATRA<br />

Date<br />

1998<br />

12/00 MFN<br />

Sogreah's services<br />

◗ Technical assistance within the<br />

context of a licence agreement<br />

for the use of the ACCROPODE ®<br />

technique<br />

Context<br />

The jetty is located at the<br />

entrance to the access channel<br />

to La Goulette harbour, on the<br />

shore of the Gulf of Tunis. It<br />

was decided to consolidate the<br />

jetty because buildings and<br />

structures situated on the<br />

adjacent landfill platforms were<br />

frequently damaged by storms.<br />

Protection of the sheet-pile<br />

structure forming the ferry loading<br />

platform at the western end of<br />

the jetty was also included in the<br />

project.<br />

The jetty was consolidated with<br />

a facing of 2.5 and 4 m 3<br />

ACCROPODE ® artificial blocks.<br />

Hydraulic conditions<br />

◆ Maximum water depth beyond<br />

jetty: 8 m<br />

◆ Significant wave height<br />

Hs = 4.7 m<br />

◆ Wave period Tp = 10 s<br />

Sogreah's role<br />

Throughout the works, which<br />

lasted 9 months, Sogreah provided<br />

technical assistance to the<br />

contractor.<br />

This involved supplying the<br />

necessary technical information<br />

for understanding and applying<br />

the ACCROPODE ® technique and<br />

preparing positioning drawings in<br />

close liaison with the contractor<br />

in order to take into account the<br />

equipment being used and the<br />

anticipated placing schedule.<br />

Sogreah's specialist made several<br />

site visits to deal with questions<br />

from the owner and contractor,<br />

and to ensure that the<br />

ACCROPODE ® technique was<br />

correctly applied.


Port of Beirut<br />

Construction of the offshore breakwater<br />

Country<br />

Lebanon<br />

Client<br />

Port of Beirut<br />

Date<br />

1998-2000<br />

Sogreah's services<br />

◗ Licence to use the<br />

ACCROPODE ® technique<br />

◗ Technical assistance during<br />

ACCROPODE ® block casting<br />

and placing.<br />

03/01 MFN<br />

Context<br />

The project involves building an<br />

offshore breakwater for the port of<br />

Beirut.<br />

The 450 m long breakwater is<br />

protected by an armour facing<br />

made of 9 m 3 ACCROPODE ®<br />

blocks with 16 m 3 blocks on the<br />

roundhead.<br />

Sogreah's role<br />

Sogreah provided technical<br />

assistance to the contractor<br />

during the works, including the<br />

following:<br />

◆ Provision of technical<br />

information required for the<br />

successful completion of the<br />

structure.<br />

◆ Technical assistance on site with<br />

casting and placing the<br />

ACCROPODE ® blocks. This<br />

involved 4 site visits.<br />

◆ Supply of positioning drawings<br />

for the ACCROPODE ® armour.<br />

Key figures<br />

◆ 9 m 3 ACCROPODE ® blocks<br />

Number of units placed: 3813<br />

Volume of concrete (m 3 ): 34 317<br />

◆ 16 m 3 blocks (d = 2.35)<br />

Number of units placed: 496<br />

Volume of concrete (m 3 ): 7936<br />

◆ 16 m 3 blocks (d = 2.55)<br />

Number of units placed: 222<br />

Volume of concrete (m 3 ): 3552<br />

◆ Total<br />

Number of units placed: 4531<br />

Volume of concrete (m 3 ): 45 805


Seafront promenade and marina<br />

in Beirut city centre<br />

Quays<br />

Reef<br />

Platform<br />

Caissons<br />

Marina<br />

breakwater<br />

Marina<br />

Reclaimed<br />

area<br />

Works-site and<br />

prefabrication<br />

area<br />

03/99 M4<br />

Country:<br />

Lebanon<br />

Date: January 1997 - April 2000<br />

Client:<br />

Owner:<br />

Engineer:<br />

Sogreah’s services:<br />

Entreprise Bouygues - Bouygues Offshore<br />

Solidere<br />

Christiani & Nielsen - Cowi<br />

• Licence to use the ACCROPODE® technique.<br />

• Technical assistance during fabrication and placing of the<br />

ACCROPODE® blocks.


Seafront promenade and marina<br />

in Beirut city centre - page 2<br />

Project features<br />

The project involves constructing a new<br />

marina and 60 ha landfill platform<br />

protected by an underwater reef and<br />

barrier of caissons, in Beirut city centre.<br />

The 450 m long breakwater and<br />

underwater reef are both protected by<br />

an ACCROPODE® facing.<br />

Sogreah’s services under the<br />

ACCROPODE® contract<br />

Sogreah provided technical assistance<br />

to the contractor throughout the period<br />

of works, including providing the<br />

information required for proper<br />

construction of the facing, assistance on<br />

site with fabricating and placing the<br />

ACCROPODE® blocks, and<br />

preparation of placing drawings.<br />

Key figures<br />

Unit volume Number of Volume of<br />

of Accropode® blocks placed concrete<br />

blocks (m 3 )<br />

4 m 3 6 262 25 048<br />

6.3 m 3 963 6 066.9<br />

14 m 3 620 8 680<br />

16 m 3 1 078 17 248<br />

Total 8 923 57 042.9<br />

Sogreah’s previous services<br />

Sogreah also prepared the initial design<br />

for the project which was partially<br />

modified by the contractor at the time of<br />

bid submission.


Ennore<br />

Construction of a new collier harbour<br />

Country<br />

India<br />

Client<br />

Chennai Port Trust (Madras)<br />

Date<br />

1997-2001<br />

Sogreah's services<br />

◗ Licence to use the<br />

ACCROPODE ® technique<br />

◗ Technical assistance during<br />

ACCROPODE ® block casting<br />

and placing<br />

03/01 MFN<br />

Context<br />

The project entails constructing a<br />

new harbour at Ennore which is<br />

located 20 km north of Chennai<br />

(Madras). The inner harbour area<br />

created covers an area of 2500 m<br />

x 1500 m dredged to a depth of<br />

-15.50 m, with a channel dredged<br />

to -18 m.<br />

The man breakwater is 3200 m long<br />

and is protected by an armour<br />

facing made of 4 m 3 , 5 m 3 and<br />

6.3 m 3 ACCROPODE ® blocks.<br />

The secondary breakwater is<br />

about 1300 m long.<br />

Sogreah's role<br />

Sogreah provided technical<br />

assistance to the contractor during<br />

the works, including the following:<br />

◆ Provision of technical information<br />

required for the successful<br />

completion of the structure.<br />

◆ Technical assistance on site with<br />

casting and placing the<br />

ACCROPODE ® blocks. This<br />

involved 8 site visits.<br />

◆ Supply of positioning drawings for<br />

the ACCROPODE ® armour.<br />

Key figures<br />

◆ 4 m 3 ACCROPODE ® blocks<br />

Number of units placed: 4360<br />

Volume of concrete (m 3 ): 17 440<br />

◆ 5 m 3 ACCROPODE ® blocks<br />

Number of units placed: 3200<br />

Volume of concrete (m 3 ): 16 000<br />

◆ 6,3 m 3 ACCROPODE ® blocks<br />

Number of units placed: 610<br />

Volume of concrete (m 3 ): 3 843<br />

◆ Total<br />

Number of units placed: 8170<br />

Volume of concrete (m 3 ): 37 283


Port of Beirut<br />

Extension of main breakwater<br />

Country<br />

Lebanon<br />

Client<br />

Port of Beirut<br />

Date<br />

1997-1999<br />

Sogreah's services<br />

◗ Licence to use the<br />

ACCROPODE ® technique<br />

◗ Technical assistance during<br />

ACCROPODE ® block casting<br />

and placing.<br />

03/01 MFN<br />

Context<br />

The project involves building an<br />

extension to the main breakwater<br />

of the port of Beirut. The<br />

breakwater was in fact extended<br />

by 280 m and protected with an<br />

armour facing made of 16 m 3<br />

ACCROPODE ® blocks and 18 m 3<br />

blocks on the roundhead.<br />

Sogreah's role<br />

Sogreah provided technical<br />

assistance to the contractor<br />

during the works, including the<br />

following:<br />

◆ Provision of technical<br />

information required for the<br />

successful completion of the<br />

structure.<br />

◆ Technical assistance on site with<br />

casting and placing the<br />

ACCROPODE ® blocks. This<br />

involved 4 site visits.<br />

◆ Supply of positioning drawings<br />

for the ACCROPODE ® armour.<br />

Sogreah had also previously<br />

carried out 3D model tests of the<br />

roundhead.<br />

Key figures<br />

◆ 16 m 3 ACCROPODE ® blocks<br />

Number of units placed: 520<br />

Volume of concrete (m 3 ): 8320<br />

◆ 18 m 3 blocks (d = 2.35)<br />

Number of units placed: 395<br />

Volume of concrete (m 3 ): 7110<br />

◆ 18 m 3 blocks (d = 2,55)<br />

Number of units placed: 88<br />

Volume of concrete (m 3 ): 1 584<br />

◆ Total<br />

Number of units placed: 1003<br />

Volume of concrete (m 3 ): 17 014


Extension of Beni Khiar<br />

fishing harbour<br />

Country<br />

Tunisia<br />

Owner<br />

Ministry of Equipment and<br />

Housing<br />

Contractor<br />

ETEP<br />

Date<br />

1997-1998<br />

Sogreah's services<br />

◗ Technical assistance within the<br />

context of a licence agreement<br />

for the use of the ACCROPODE ®<br />

technique<br />

12/00 MFN<br />

Context<br />

Beni Khiar fishing harbour, situated<br />

in the southern part of Cap Bon,<br />

is one of the busiest in Tunisia. The<br />

Ministry of Equipment and Housing<br />

decided to extend it in order to<br />

double its capacity. The existing<br />

main breakwater was lengthened<br />

by 150 m and a new 220 m<br />

long secondary breakwater was<br />

built. The extension to the main<br />

breakwater was protected with<br />

a facing of 2.5 and 4 m 3<br />

ACCROPODE ® artificial blocks and<br />

the new secondary breakwater by<br />

2.5 m 3 ACCROPODE ® blocks.<br />

Hydraulic conditions<br />

◆ Maximum water depth beyond<br />

breakwaters: 8 m<br />

◆ Significant wave height<br />

Hs = 4.7 m<br />

◆ Wave period Tp = 10 s<br />

Sogreah's role<br />

Throughout the works, which<br />

lasted 17 months, Sogreah<br />

provided technical assistance to<br />

the contractor.<br />

This involved supplying the<br />

necessary technical information<br />

for understanding and applying<br />

the ACCROPODE ® technique and<br />

preparing positioning drawings in<br />

close liaison with the contractor<br />

in order to take into account the<br />

equipment being used and the<br />

anticipated placing schedule.<br />

Sogreah's specialist made several<br />

site visits to deal with questions<br />

from the owner and contractor,<br />

and to ensure that the<br />

ACCROPODE ® technique was<br />

correctly applied


Extension of Mayotte<br />

airport runway<br />

1 1 / 9 6 M 3<br />

Country:<br />

Client:<br />

Owner:<br />

Prime contractor:<br />

France<br />

COLAS<br />

Ministère des Départements et Territoires d’Outre-Mer<br />

D.E. Mayotte<br />

Date: 1 9 9 4 / 1 9 9 5<br />

Sogreah’s services:<br />

Technical assistance as part of a contract awarding a licence<br />

to use the Accropode® technique.


Extension of Mayotte airport runway - page 2<br />

Context<br />

The Pamandzi airport runway was<br />

initially 1300 m long, and was<br />

extended to 1750 m. For the extension,<br />

a strip of land 700 m long and 150 m<br />

wide was reclaimed from the sea.<br />

Project features<br />

Extending the runway and protecting it<br />

from cyclonic waves will enable a fully<br />

laden Air Austral Boeing 737 to land<br />

daily on the Island of Mayotte in the<br />

optimum safety conditions.<br />

Typical cross-section<br />

Key figures<br />

• The works lasted 22 months.<br />

• 7200 2.5 m 3 Accropode® blocks<br />

were made using 22 moulds.<br />

• In this way, 1000 lm of reclaimed<br />

land was protected.<br />

Services provided by Sogreah<br />

• 3D scale model tests at Sogreah’s<br />

laboratory on behalf of STCPMVN.<br />

• 1992: preparation of working<br />

drawings on behalf of STCPMVN.<br />

• 1994-1995: Technical assistance<br />

during works.<br />

During the works, Sogreah provided the<br />

contractor with technical assistance,<br />

including all the technical information<br />

required to implement the Accropoderelated<br />

works, and with the layout<br />

drawings for placing the blocks.<br />

A specialist from Sogreah supervised the<br />

Accropode® application, and carried<br />

out several site assignments in order to<br />

assist and advise the contractor in the<br />

field in fabricating and laying the<br />

Accropode® blocks.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!