February 22, 2000 - Hunterdon County, New Jersey
February 22, 2000 - Hunterdon County, New Jersey
February 22, 2000 - Hunterdon County, New Jersey
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
done to the <strong>County</strong>=s satisfaction.<br />
Mr. Bell advised a medication hearing is scheduled for March 14, <strong>2000</strong> with Ray Angelini, Inc., general<br />
contractor for the new North Branch <strong>County</strong> Library, to discuss and resolve open Change Order issues.<br />
The main change order is for the caissons.<br />
The steel silo fabrication for the Route 12 Office Building is completed and will be shipped to the site<br />
within a week. Mechanical and electrical rough in of pipes and conduit continues. Openings are being<br />
cut into the steel deck and treated wood blocking is being installed for the trusses and miscellaneous<br />
trim work.<br />
Mr. Bell advised the insulation of gypsum board for the Warehouse/Records Retention Center is about<br />
75% complete. The ceiling grid has been installed and final inspections of the duct work are complete<br />
and the natural gas line has been installed and the heating system is being prepared to be fired up.<br />
Mr. Bell stated the electrical work for the Route 12 Water System is scheduled for completion this<br />
week. The contractor will begin flushing the 3" and 8" mains next week. The entire project should be<br />
completed by the middle of March.<br />
The underground detention system for the surface parking lot in Flemington, is complete. Cleaning and<br />
grubbing of the remaining trees and brush will start once the snow has been removed. Phase II paving<br />
will begin in the Spring.<br />
Mr. Bell reported the work on the historic Court House. The contractor has been monitoring the<br />
temperatures and feels they have risen enough to resume to strip the lead paint.<br />
The building for the Haz-Mat services, vehicles and personnel will be a prefab steel structure located at<br />
the Franklin Township site. A mechanical, structural, civil and site engineers will be hired for this<br />
project. Mr. Fuzo advised to hold off on this until after the next meeting as the resolution for funding will<br />
be presented at the March 14, <strong>2000</strong> meeting.<br />
The documents for Deer Path Park, Phase II will be completed by mid-March and bids should be<br />
received by mid-April. The Park System has requested the construction not start until the middle of<br />
August due to the scheduled activities at the Park System. The documents will be revised to reflect<br />
that in the schedule.<br />
Mr. Bell stated a meeting was held with prospective architects for the Emergency Services Addition, on<br />
<strong>February</strong> 14, <strong>2000</strong>. Due to additional requests from the architects, the receipt of the RFP will be<br />
extended.<br />
The engineer for the Fire School Propane System will have the drawings completed by March 3, <strong>2000</strong>.<br />
The specifications will be completed by March 24th and a cost estimated should be ready by March<br />
14th.<br />
Mr. Bell met with Don Einhorn, of <strong>County</strong> Counsel=s Office, regarding the South <strong>County</strong> Garage, to<br />
review the front end documents to the specifications and a number of sections need reworking and<br />
refinement. This work should be completed in a few weeks.<br />
A meeting will be held on March 3, <strong>2000</strong>, with Mr. Bell, the Library Commission and Jim Faridy of the<br />
architectural firm of Faridy, Thorne and Fraytak, to discuss the Route 12 Library Master Plan.<br />
Mr. Bell advised he will work with the <strong>County</strong> Administrator and <strong>County</strong> personnel on a <strong>County</strong>-wide<br />
Space Allocation/Utilization Survey and furniture and equipment needs, as well. There is a meeting<br />
scheduled for Friday to review the furniture needs for the Warehouse/Records Retention Center with<br />
Bob Thurgarland, Print Shop Director. There was a large furniture list prepared for the building and that<br />
will be reviewed also on Friday.<br />
Director Karrow advised that the Freeholders have decided to renovate the old Administration Building,<br />
instead of building more buildings. John Clarke of Clarke, Caton and Hintz, AIA advised he is here<br />
today to get more of a feeling of what the Board is looking to do and not do. Director Karrow advised<br />
the Freeholders are interested in finding out the costs to do the windows, HVAC, new carpeting, making<br />
things ADA compliant, putting up an elevator and how many <strong>County</strong> office will fit in the old<br />
Administration Building versus what the maximum it will provide.<br />
Director Karrow stated for Mr. Clarke that the Freeholders would prefer to be housed in the historic court<br />
house, for their offices, as well as the Freeholders= Meeting Room.<br />
Freeholder Sauerland came into the meeting at 3:45 p.m.<br />
Mr. Clarke explained an elevator system would be needed at the old Administration Building to get to all<br />
the floors. There are also building code issues that need to be address, such as the fire stairs and<br />
corridors. Also a new mechanical system would be needed.<br />
Mr. Clarke briefly described the Hall of Records, Court House, the old Administration and the additions<br />
that would be needed. He feels the basement area would only be good for support, not office space.<br />
Several years ago an analysis was done, by a consultant, on <strong>County</strong> population growth,<br />
filings, permits and a project was made on how that would relate to staff. Director Karrow informed Mr.<br />
Clarke that she would prefer the Freeholders to fit into any space for their offices, including the