1000 TPD CO 2 CAPTURE PLANT FEED STUDYDEVON JACKFISH 1 OILSANDS OPERATIONSFEED STUDY REPORTDEV-JA-03-001-1 (R1)5 Engineering, Fabrication & Site Installation ScheduleFigure 3 below shows the high level engineering, fabrication and site installation schedule for the CO 2Capture Unit. The expected overall project duration is 20 months after EPC contract award.Figure 3 – EPC Execution ScheduleHTC PURENERGYPage17 (19)