The planning and Programming Process - Directrouter.com
The planning and Programming Process - Directrouter.com
The planning and Programming Process - Directrouter.com
- No tags were found...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
<strong>The</strong> Planning&<strong>Programming</strong> <strong>Process</strong>Major Pat Miller, USAF, PE1
LESSON OBJECTIVEOBJECTIVE: Comprehend Basic Planning <strong>and</strong><strong>Programming</strong> Fundamentals for Application in aContingency EnvironmentTOPICS:Key TermsPlanning<strong>Programming</strong>Project DevelopmentAFIT Graphic2
REFERENCES– AFI 32-1032, Plan/Program APF Projects– AFI 32-1021, Plan/Program MILCON Projects– AFI 65-601 V1, Budget <strong>and</strong> Guidance Procedures– HQ USCENTCOM Regulation 425-1: Construction <strong>and</strong>Base Camp Development in the USCENTCOM AOR, “<strong>The</strong>S<strong>and</strong> Book”- 15 April 2009– AR 420-1, Facilities <strong>Programming</strong>– DA PAM 420-11– DOD Financial Mgt Regs– USFOR-A Pub 1-06, MAAWS-A– AFCENT & ARCENT <strong>Programming</strong> Guidance3
SETTING THE STAGEIMPORTANT TO REMEMBER: In a contingencyenvironment: All “normal” programming rules apply– Tax payer dollars still used to fund requirementsWhat Differs, then?– Time <strong>and</strong> Resource balance is very different– Some unique funding avenues– Some different construction st<strong>and</strong>ards/practices– Some different Policies4
KEY TERMS“<strong>Programming</strong> is the process of acquiringboth the authority <strong>and</strong> the resourcesnecessary to ac<strong>com</strong>plish planned work.---AFI 32-10325
THE PROCESSPLANNINGPROGRAMMINGPROJECTDEVELOPMENTIdentifyRqmtsValidateDevelopScopeDevelopCostCLASSIFYWORKMaintRepairConstDETERMINEFUNDSOURCEAPFNAFSELECTPROGRAMAVENUEO&MMILCONP-341NAFProject RecordCoordinationFacilities BoardDocumentationApprovalE.A.MFH7
NEED TO UNDERSTANDPLANNING TOOLS<strong>The</strong>ater Posture Plan (J5 document ):• Articulates basing strategy <strong>and</strong> posture ( “Dots on the Map” )• Approved by Comm<strong>and</strong>er; adjusted during implementation• Under pins all other productsMaster Plan (J4 document ICW with J5):• Summarizes basing presence (personnel, equipment,mission…aka “Blocks on the Dots” ) <strong>and</strong> the associatedinfrastructure requirements to support presence• Primary document for driving implementation of overall TPPrequirements9
NEED TO UNDERSTANDResponsible PartyBase Operating Support Integrator (BOS-I)– Manage Base Master <strong>planning</strong> efforts for all Services/forces– Provide contingency construction project requirements onDD1391– Responsible for programming <strong>and</strong> funding projectsSenior Airfield Authority (SAA)– Prepare Airfield Master Plans– Coordinate with appropriate BOS-I– Responsible for programming <strong>and</strong> funding projectsNOTE: Lead Component BOS-I Matrix can befound on CCJ4-P’s website10
NEED TO UNDERSTANDCONSTRUCTION STANDARDSConstruction at contingency locations is typically limited to“expeditionary” or “temporary” st<strong>and</strong>ards– “<strong>The</strong> S<strong>and</strong> Book “(CENTCOM Reg 415-1) defines constructionst<strong>and</strong>ards; use in conjunction w/ AT/FP OPORDs, UFCs <strong>and</strong> FRAGOsConstruction at GDP locations can be “expeditionary,”“temporary,” or “permanent”– Surge rqmnts typically met w/ expeditionary or temporary st<strong>and</strong>ards– Steady state rqmnts are met w/ permanent construction st<strong>and</strong>ardsExpeditionary Temporary Permanent11
PROJECT PLANNING― ID Requirements― Verify Necessity― Is there already a project planned?― Can it be added to an existing project?― Does this already exist?― Check for Compatibility w/ Base Master Plan― Check Against Other Criteria― CENTCOM Reg 415-1, “<strong>The</strong> S<strong>and</strong> Book”― Space criteria― AT/FP― CENTAFI 32-1056 (airfield st<strong>and</strong>ards)12
PROJECT PLANNING― Cost Estimating Tools― Historical costs/contractor bids― Previous 1391s― MAAWS-A cost estimating template― DOD Pricing Guide (UFC 3-701-09)― Consider― Influencing factors (security, transportation,location, etc.)― Contingency― SIOH13
THE PROCESS: PROGRAMMINGPLANNINGPROGRAMMINGPROJECTDEVELOPMENTIdentifyRqmtsValidateDevelopScopeDevelopCostCLASSIFYWORKMaintRepairConstDETERMINEFUNDSOURCEAPFNAFSELECTPROGRAMAVENUEO&MMILCONP-341NAFProject RecordCoordinationFacilities BoardDocumentationApprovalE.A.MFH14
IMPACT OF WORK CLASS:APPROVAL LEVELS$7.5 M$5 MCongressSAF/IEIInstall/CCMAJCOMCongress$750KConstMAJCOMMaintRpr15Construction
SPECIAL CASE:MINOR CONSTRUCTION$3M$2M$750K$0K(UMC)P-341LHSMILCONP-341O&MMC-LHSO&M Minor ConstConstructionO&M FUNDS (3400)MILCON FUNDS (3300)• National DefenseAuthorization act for FY 96:– For work solely to correctdeficiencies that threatenlife, health, safety:• O&M MC thresholdincreased to $1.5 M$1.5M• P-341 (UnspecifiedMinor Construction,$750K UMC) thresholdincreased to $3 M– Authorization: SAF/IEI16
Maintenance….?Repair……?Construction…..?Minor Construction…..?Work Classificationdescribes the nature ofthe work that is to beac<strong>com</strong>plished on afacility.SOURCES:• 10 USC• AF: AFI 32-1032• Army: AR PAM 420-11& AR 420-1
WORK CLASSIFICATIONMaintenance:Work required to preserve real propertysystems or <strong>com</strong>ponents <strong>and</strong> preventpremature failure or wearing out of the same.Includes work to prevent <strong>and</strong> arrest<strong>com</strong>ponent deterioration, as well asl<strong>and</strong>scaping or planting work which is notcapitalized.18
WORK CLASSIFICATION:MAINTENANCE EXAMPLES― Protective Coatings― Painting― Cathodic Protection― Sealants― Roofs― Roads― Pothole repair19
WORK CLASSIFICATIONRepair:Work to restore real property systems or<strong>com</strong>ponents to such condition that theymay effectively be used for theirdesignated functional purposes.…Need not have failed to permit a repairproject.20
WORK CLASSIFICATION:REPAIR EXAMPLES― Repair by replacement― Remedy Code Deficiencies (NEC a big issue)― All Interior Rearrangements (including load-bearingmembers)― Utility Modifications for Current Usage― Installation of Mezzanines (
WORK CLASSIFICATIONConstruction:To build, develop, or extend realproperty systems or <strong>com</strong>ponents22
WORK CLASSIFICATION:CONSTRUCTION EXAMPLES― Creating new or enlarging (volume or footprint)― Facility Replacement/Relocation―Upgrading Surface of Unpaved Transportation Systems(gravel placement on dirt)―All Work Associated with New Construction/FacilityReplacement―Site work/L<strong>and</strong>scaping―Demolishing facilities in way of construction―Environmental remediation23
FUNDING AUTHORITIES― Host Nation― OCO MILCON― Regular MILCON― Contingency Construction Authority― Unspecified Minor Military Construction (P-341)― Troop Labor― O&M/OMA24
O&M DELEGATED APPROVAL LEVELS:EXAMPLE OF DELEGATION FOR USFOR-ADocument Approval AuthorityOrganizationARCENT/CongressHQ USFOR-A DCDR-SHQ USFOR-A CoSCSTC-A/CCRegional or USFOR-A Detachment CCTF Rushmore/CCThresholdAll construction over $750K (Exceptionfor Life Health Safety)Construction < $750K; LHS > $750K<strong>and</strong> < $1.5M; Repair < $5M; Total
O&M DELEGATED APPROVAL LEVELS:EXAMPLE OF DELEGATION FOR USAFBase Support (APF 3400)MinorConstructionRepairMaintenanceUSAFCENT/A7 $700K $4,000K $4,000KUSAFCENT/A7-2 $700K $4,000K $4,000K332 AEW/CC (Balad) $300K $500K $500K376 AEW/CC (Manas) $300K $500K $500K379 AEW/CC (Al Udeid) $300K $500K $500K380 AEW/CC (Al Dhafra) $300K $500K $500K386 AEW/CC (Ali Al Salem) $300K $500K $500K407 AEG/CC (Ali) $300K $500K $500K447 AEG/CC (Baghdad IAP) $300K $500K $500K451 AEW/CC (K<strong>and</strong>ahar) $300K $500K $500K455 AEW/CC (Bagram) $300K $500K $500K506 AEG/CC (Kirkuk) $300K $500K $500K26
MAJOR PROGRAMMING RULES― 75% Rule for Repair Projects (50% for Army)― Complete <strong>and</strong> Useable Facility―12-month rule for New Construction―Current Repair Rule (24-month Repair Rule)― Re-<strong>Programming</strong>: exceeding threshold, exceedingPA or scope by 10% (25% for Army)― Don’t Mix O&M MC with:― P-341 MC― MILCON27
PLANNINGTHE PROCESS:PROJECT DEVELOPMENTPROGRAMMINGPROJECTDEVELOPMENTIdentifyRqmtsValidateDevelopScopeDevelopCostCLASSIFYWORKMaintRepairConstDETERMINEFUNDSOURCEAPFNAFSELECTPROGRAMAVENUEO&MMILCONP-341NAFProject RecordCoordinationFacilities BoardDocumentationApprovalE.A.MFH28
JOINT FACILITIES UTILIZATION BOARD(JFUB)― Evaluates <strong>and</strong> Reconciles Component Rqmnts― Reviews All Facility Rqmnts― Authorizes/Prioritizes (but does not fund) Projects― Members― Voting: J3, J4, J6, <strong>and</strong> J8― Non-voting: SJA, Force Protection, Contracting, <strong>and</strong>others as required29
PURPOSE OF JFUB PACKAGE― Project Documents Must Be Sufficient to Allow anIndependent Reviewer to Underst<strong>and</strong> <strong>The</strong>:― Requirement― Benefit― Classification of Work― Total Cost (Funded <strong>and</strong> Unfunded)― Impact If Not Provided― Timing of Project Requirements― Captured in a JFUB package30
JFUB PACKAGE ELEMENTS― Operational Needs Statement/Letter of Justification― Independent Gov’t Cost Estimate―Site Map/Location Map―JFUB Quad Chart― Legal Opinion― Statement from Master Planner― LOGCAP Checklist31
1391 PACKAGETypical items in 1391 Package for higher approval:DD Form 13911391c with Location & Site Plan– Include st<strong>and</strong>off from US Controlled perimeterE-mail transmittal– List of projects <strong>com</strong>pleted with that Cat Code inthe last 12 months32
SUMMARYOBJECTIVE: Comprehend Basic Planning <strong>and</strong><strong>Programming</strong> Fundamentals for Application in aContingency EnvironmentTOPICS:Key TermsPlanning<strong>Programming</strong>Project Development33
PARTING COMMENTS― <strong>Programming</strong> Rules Apply No Matter What― Fighting a War w/ CONUS Fiscal Restraints― Environment Adds Constraints (Time, Mission, etc.)― Your Job is to Keep the Boss Out of Trouble― Balance the Rules with the Mission― Underst<strong>and</strong> the Rules for the Service Employing You34
QUESTIONS35
BACK-UPSLIDES36
COSTESTIMATING37
FUNDED VS. UNFUNDED VS.EXCLUDED COSTSFunded Costs– Costs charged to thefacility projects– Count towardsstatutory approvallimits - $750KUnfunded Costs– Cost charged toother appropriationsor fund sources– Capitalized, but donot count againstapproval limitsExcluded Costs– Does not count againstapproval limits– Not capitalized38
FUNDED COSTSMaterials, Contract Labor, Non-US LaborRPIE – equipment that is integral to the facilitySite work– Utility connections– Site clearing– L<strong>and</strong>scapingTransportation <strong>and</strong> travel costs (even for RED HORSE)Supervision, Inspection, & Overhead (SIOH)Air Force Real Property Government FurnishedEquipment (GFE)SOURCE: AFI 32-1021 – Attachment 1, AFI 65-601 V1
UNFUNDED COSTS (NO-CLASS WORK)Design (except design-build)U.S. Military labor, including RED HORSEReal Property GFE from other DOD or governmentagencies– If the AF gives GFE to itself, it’s a funded costWar Reserve Materials (Tents, ECUs, generators, etc)Modular Force Protection (T-walls, barriers)Relocateable facilities (trailers, pods, CHUs, etc)SOURCE: AFI 32-1021 – Attachment 1 & AFI 65-601 V1 -9.14.340
EXCLUDED COSTS (NO-CLASS WORK)Furniture including pre-wired work stationsComputers, electronics, etcEnd User type of equipmentUser should pay for these from their own funds!!!!41
SPECIAL CASE:BUILDING DEMOLITIONIncident (In way of construction project)– APF Project: ConstructionIsolated: No Class42
EQUIPMENT CLASSIFICATIONA piece of equipment (i.e. not RPIE) can be purchasedwith O&M funds if $250K or less– Considered an unfunded cost– If >$250K must use Appn 3080 – long process– Relocateable Buildings (RLB)Tension Fabric Structures (TFSs) with a rigid frame– Cannot be purchased as “equipment” using perspecific Congressional instruction, purchase asconstruction– <strong>The</strong> TSF, foundations, utilities, <strong>and</strong> site prep areall considered Construction <strong>and</strong> included asfunded items on 1391s43
COMMUNICATIONS REQUIREMENTSIf project is new construction: everything is included asfunded costs except:– Actual <strong>com</strong>m equipment• Computers• Servers• UPS44
FUNDINGSOURCES45
HOST NATIONType of work: Construction &SustainmentScope of work: Large ScaleFacilities & RepairsTiming/<strong>Process</strong>: Unknown/VariesLocation Issues: Country Specific– Countries “Can Pay - ShouldPay” (CP-SP) principleTypical Uses: Infrastructure &Large FacilitiesHow to get started: Talk w/ HHQ onrequirement <strong>and</strong> strategy46
OCO MILCONType of work: ConstructionScope of work: Large ScaleTiming/<strong>Process</strong>: 1 year/CongressionalAppropriationLocation Issues: Locations driven byOSD <strong>and</strong> CongressTypical Uses: New Facilities <strong>and</strong>InfrastructureHow to get started: Submit 1391– CENTCOM validates, prioritizes<strong>and</strong> advocates requirements47
REGULAR MILCONType of work: ConstructionScope of work: Large ScaleTiming/<strong>Process</strong>: > 2 years/CongressionalAppropriation <strong>and</strong> AuthorizationLocation Issues: GDP LocationsTypical Uses: New Facilities &InfrastructureHow to get started: Submit 1391– Aligned with Base Master Plan– Can take five years to execute– May require TOA– May require HN approval48
CONTINGENCY CONSTRUCTIONAUTHORITY - CCAType of work: ConstructionScope of work: Large ScaleTiming/<strong>Process</strong>: < 1 year/OSD Approval(limited to $200M)Location Issues: Limited to IraqTypical Uses: “Break the Glass” rqmntsHow to get started: Submit 1391– CENTCOM validates, prioritizes<strong>and</strong> advocates requirements49
CONTINGENCY CONSTRUCTIONAUTHORITY – CCA (Cont.)• Project must meet the followingcriteria:• Construction > $750K necessary tomeet urgent operational rqmnts• Construction is not carried out atlocation where U.S. is reasonablyexpected to have a long termpresence• U.S. has no intention of usingconstruction after the operationalrqmnts satisfied• Level of construction is minimumnecessary to meet the temp rqmnts50
UNSPECIFIED MINOR MILITARYCONSTRUCTIONType of work: ConstructionScope of work: Medium ScaleTiming / <strong>Process</strong>: 4 months/Congressional NotificationLocation Issues: NoneTypical Uses: New Facilities <strong>and</strong>InfrastructureHow to get started: Submit 139151
TROOP LABORType of work: Construction &RepairsScope of work: Small ScaleFacilitiesTiming/<strong>Process</strong>: < 1 year / HHQApprovalLocation Issues: NoneTypical Uses: “Break the Glass”requirementsHow to get started: Submit 1391– RED HORSE reports directlyto COMUSAFCENT52
OPERATIONS & MAINTENANCE - O&MType of work: Minor Construction (MC),Repair, MaintenanceScope of work: Small Scale (MC
Operations & MaintenanceMain source for construction projectsCommon programming rqmnts:– Stress Tension Shelter (Fabric)– Billeting– Relocatable Buildings (RLBs)– Repair by Replacement– Tilt-up Construction– Troop Labor– MSA Berms– Runway/Taxiway Repair54
75%RULE55
Historic Facility?No75% RuleYesRepair Costs > 75% ofPlant ReplacementValue?NoProceedYesReplaceFacilityORTo proceed with proposed work:1) Ac<strong>com</strong>plish Economic Analysis-- If repair notmore economical, must reclassify work asconstruction2) Obtain waiver to 75% rule3) Still must obtain approval for project. Waiverauthority may be different than approvalauthority!!NOTE: At NO time shall cost to repair facility exceed replacement cost. Ifrepair work exceeds replacement cost, facility MUST be replaced.