11.07.2015 Views

The planning and Programming Process - Directrouter.com

The planning and Programming Process - Directrouter.com

The planning and Programming Process - Directrouter.com

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>The</strong> Planning&<strong>Programming</strong> <strong>Process</strong>Major Pat Miller, USAF, PE1


LESSON OBJECTIVEOBJECTIVE: Comprehend Basic Planning <strong>and</strong><strong>Programming</strong> Fundamentals for Application in aContingency EnvironmentTOPICS:Key TermsPlanning<strong>Programming</strong>Project DevelopmentAFIT Graphic2


REFERENCES– AFI 32-1032, Plan/Program APF Projects– AFI 32-1021, Plan/Program MILCON Projects– AFI 65-601 V1, Budget <strong>and</strong> Guidance Procedures– HQ USCENTCOM Regulation 425-1: Construction <strong>and</strong>Base Camp Development in the USCENTCOM AOR, “<strong>The</strong>S<strong>and</strong> Book”- 15 April 2009– AR 420-1, Facilities <strong>Programming</strong>– DA PAM 420-11– DOD Financial Mgt Regs– USFOR-A Pub 1-06, MAAWS-A– AFCENT & ARCENT <strong>Programming</strong> Guidance3


SETTING THE STAGEIMPORTANT TO REMEMBER: In a contingencyenvironment: All “normal” programming rules apply– Tax payer dollars still used to fund requirementsWhat Differs, then?– Time <strong>and</strong> Resource balance is very different– Some unique funding avenues– Some different construction st<strong>and</strong>ards/practices– Some different Policies4


KEY TERMS“<strong>Programming</strong> is the process of acquiringboth the authority <strong>and</strong> the resourcesnecessary to ac<strong>com</strong>plish planned work.---AFI 32-10325


THE PROCESSPLANNINGPROGRAMMINGPROJECTDEVELOPMENTIdentifyRqmtsValidateDevelopScopeDevelopCostCLASSIFYWORKMaintRepairConstDETERMINEFUNDSOURCEAPFNAFSELECTPROGRAMAVENUEO&MMILCONP-341NAFProject RecordCoordinationFacilities BoardDocumentationApprovalE.A.MFH7


NEED TO UNDERSTANDPLANNING TOOLS<strong>The</strong>ater Posture Plan (J5 document ):• Articulates basing strategy <strong>and</strong> posture ( “Dots on the Map” )• Approved by Comm<strong>and</strong>er; adjusted during implementation• Under pins all other productsMaster Plan (J4 document ICW with J5):• Summarizes basing presence (personnel, equipment,mission…aka “Blocks on the Dots” ) <strong>and</strong> the associatedinfrastructure requirements to support presence• Primary document for driving implementation of overall TPPrequirements9


NEED TO UNDERSTANDResponsible PartyBase Operating Support Integrator (BOS-I)– Manage Base Master <strong>planning</strong> efforts for all Services/forces– Provide contingency construction project requirements onDD1391– Responsible for programming <strong>and</strong> funding projectsSenior Airfield Authority (SAA)– Prepare Airfield Master Plans– Coordinate with appropriate BOS-I– Responsible for programming <strong>and</strong> funding projectsNOTE: Lead Component BOS-I Matrix can befound on CCJ4-P’s website10


NEED TO UNDERSTANDCONSTRUCTION STANDARDSConstruction at contingency locations is typically limited to“expeditionary” or “temporary” st<strong>and</strong>ards– “<strong>The</strong> S<strong>and</strong> Book “(CENTCOM Reg 415-1) defines constructionst<strong>and</strong>ards; use in conjunction w/ AT/FP OPORDs, UFCs <strong>and</strong> FRAGOsConstruction at GDP locations can be “expeditionary,”“temporary,” or “permanent”– Surge rqmnts typically met w/ expeditionary or temporary st<strong>and</strong>ards– Steady state rqmnts are met w/ permanent construction st<strong>and</strong>ardsExpeditionary Temporary Permanent11


PROJECT PLANNING― ID Requirements― Verify Necessity― Is there already a project planned?― Can it be added to an existing project?― Does this already exist?― Check for Compatibility w/ Base Master Plan― Check Against Other Criteria― CENTCOM Reg 415-1, “<strong>The</strong> S<strong>and</strong> Book”― Space criteria― AT/FP― CENTAFI 32-1056 (airfield st<strong>and</strong>ards)12


PROJECT PLANNING― Cost Estimating Tools― Historical costs/contractor bids― Previous 1391s― MAAWS-A cost estimating template― DOD Pricing Guide (UFC 3-701-09)― Consider― Influencing factors (security, transportation,location, etc.)― Contingency― SIOH13


THE PROCESS: PROGRAMMINGPLANNINGPROGRAMMINGPROJECTDEVELOPMENTIdentifyRqmtsValidateDevelopScopeDevelopCostCLASSIFYWORKMaintRepairConstDETERMINEFUNDSOURCEAPFNAFSELECTPROGRAMAVENUEO&MMILCONP-341NAFProject RecordCoordinationFacilities BoardDocumentationApprovalE.A.MFH14


IMPACT OF WORK CLASS:APPROVAL LEVELS$7.5 M$5 MCongressSAF/IEIInstall/CCMAJCOMCongress$750KConstMAJCOMMaintRpr15Construction


SPECIAL CASE:MINOR CONSTRUCTION$3M$2M$750K$0K(UMC)P-341LHSMILCONP-341O&MMC-LHSO&M Minor ConstConstructionO&M FUNDS (3400)MILCON FUNDS (3300)• National DefenseAuthorization act for FY 96:– For work solely to correctdeficiencies that threatenlife, health, safety:• O&M MC thresholdincreased to $1.5 M$1.5M• P-341 (UnspecifiedMinor Construction,$750K UMC) thresholdincreased to $3 M– Authorization: SAF/IEI16


Maintenance….?Repair……?Construction…..?Minor Construction…..?Work Classificationdescribes the nature ofthe work that is to beac<strong>com</strong>plished on afacility.SOURCES:• 10 USC• AF: AFI 32-1032• Army: AR PAM 420-11& AR 420-1


WORK CLASSIFICATIONMaintenance:Work required to preserve real propertysystems or <strong>com</strong>ponents <strong>and</strong> preventpremature failure or wearing out of the same.Includes work to prevent <strong>and</strong> arrest<strong>com</strong>ponent deterioration, as well asl<strong>and</strong>scaping or planting work which is notcapitalized.18


WORK CLASSIFICATION:MAINTENANCE EXAMPLES― Protective Coatings― Painting― Cathodic Protection― Sealants― Roofs― Roads― Pothole repair19


WORK CLASSIFICATIONRepair:Work to restore real property systems or<strong>com</strong>ponents to such condition that theymay effectively be used for theirdesignated functional purposes.…Need not have failed to permit a repairproject.20


WORK CLASSIFICATION:REPAIR EXAMPLES― Repair by replacement― Remedy Code Deficiencies (NEC a big issue)― All Interior Rearrangements (including load-bearingmembers)― Utility Modifications for Current Usage― Installation of Mezzanines (


WORK CLASSIFICATIONConstruction:To build, develop, or extend realproperty systems or <strong>com</strong>ponents22


WORK CLASSIFICATION:CONSTRUCTION EXAMPLES― Creating new or enlarging (volume or footprint)― Facility Replacement/Relocation―Upgrading Surface of Unpaved Transportation Systems(gravel placement on dirt)―All Work Associated with New Construction/FacilityReplacement―Site work/L<strong>and</strong>scaping―Demolishing facilities in way of construction―Environmental remediation23


FUNDING AUTHORITIES― Host Nation― OCO MILCON― Regular MILCON― Contingency Construction Authority― Unspecified Minor Military Construction (P-341)― Troop Labor― O&M/OMA24


O&M DELEGATED APPROVAL LEVELS:EXAMPLE OF DELEGATION FOR USFOR-ADocument Approval AuthorityOrganizationARCENT/CongressHQ USFOR-A DCDR-SHQ USFOR-A CoSCSTC-A/CCRegional or USFOR-A Detachment CCTF Rushmore/CCThresholdAll construction over $750K (Exceptionfor Life Health Safety)Construction < $750K; LHS > $750K<strong>and</strong> < $1.5M; Repair < $5M; Total


O&M DELEGATED APPROVAL LEVELS:EXAMPLE OF DELEGATION FOR USAFBase Support (APF 3400)MinorConstructionRepairMaintenanceUSAFCENT/A7 $700K $4,000K $4,000KUSAFCENT/A7-2 $700K $4,000K $4,000K332 AEW/CC (Balad) $300K $500K $500K376 AEW/CC (Manas) $300K $500K $500K379 AEW/CC (Al Udeid) $300K $500K $500K380 AEW/CC (Al Dhafra) $300K $500K $500K386 AEW/CC (Ali Al Salem) $300K $500K $500K407 AEG/CC (Ali) $300K $500K $500K447 AEG/CC (Baghdad IAP) $300K $500K $500K451 AEW/CC (K<strong>and</strong>ahar) $300K $500K $500K455 AEW/CC (Bagram) $300K $500K $500K506 AEG/CC (Kirkuk) $300K $500K $500K26


MAJOR PROGRAMMING RULES― 75% Rule for Repair Projects (50% for Army)― Complete <strong>and</strong> Useable Facility―12-month rule for New Construction―Current Repair Rule (24-month Repair Rule)― Re-<strong>Programming</strong>: exceeding threshold, exceedingPA or scope by 10% (25% for Army)― Don’t Mix O&M MC with:― P-341 MC― MILCON27


PLANNINGTHE PROCESS:PROJECT DEVELOPMENTPROGRAMMINGPROJECTDEVELOPMENTIdentifyRqmtsValidateDevelopScopeDevelopCostCLASSIFYWORKMaintRepairConstDETERMINEFUNDSOURCEAPFNAFSELECTPROGRAMAVENUEO&MMILCONP-341NAFProject RecordCoordinationFacilities BoardDocumentationApprovalE.A.MFH28


JOINT FACILITIES UTILIZATION BOARD(JFUB)― Evaluates <strong>and</strong> Reconciles Component Rqmnts― Reviews All Facility Rqmnts― Authorizes/Prioritizes (but does not fund) Projects― Members― Voting: J3, J4, J6, <strong>and</strong> J8― Non-voting: SJA, Force Protection, Contracting, <strong>and</strong>others as required29


PURPOSE OF JFUB PACKAGE― Project Documents Must Be Sufficient to Allow anIndependent Reviewer to Underst<strong>and</strong> <strong>The</strong>:― Requirement― Benefit― Classification of Work― Total Cost (Funded <strong>and</strong> Unfunded)― Impact If Not Provided― Timing of Project Requirements― Captured in a JFUB package30


JFUB PACKAGE ELEMENTS― Operational Needs Statement/Letter of Justification― Independent Gov’t Cost Estimate―Site Map/Location Map―JFUB Quad Chart― Legal Opinion― Statement from Master Planner― LOGCAP Checklist31


1391 PACKAGETypical items in 1391 Package for higher approval:DD Form 13911391c with Location & Site Plan– Include st<strong>and</strong>off from US Controlled perimeterE-mail transmittal– List of projects <strong>com</strong>pleted with that Cat Code inthe last 12 months32


SUMMARYOBJECTIVE: Comprehend Basic Planning <strong>and</strong><strong>Programming</strong> Fundamentals for Application in aContingency EnvironmentTOPICS:Key TermsPlanning<strong>Programming</strong>Project Development33


PARTING COMMENTS― <strong>Programming</strong> Rules Apply No Matter What― Fighting a War w/ CONUS Fiscal Restraints― Environment Adds Constraints (Time, Mission, etc.)― Your Job is to Keep the Boss Out of Trouble― Balance the Rules with the Mission― Underst<strong>and</strong> the Rules for the Service Employing You34


QUESTIONS35


BACK-UPSLIDES36


COSTESTIMATING37


FUNDED VS. UNFUNDED VS.EXCLUDED COSTSFunded Costs– Costs charged to thefacility projects– Count towardsstatutory approvallimits - $750KUnfunded Costs– Cost charged toother appropriationsor fund sources– Capitalized, but donot count againstapproval limitsExcluded Costs– Does not count againstapproval limits– Not capitalized38


FUNDED COSTSMaterials, Contract Labor, Non-US LaborRPIE – equipment that is integral to the facilitySite work– Utility connections– Site clearing– L<strong>and</strong>scapingTransportation <strong>and</strong> travel costs (even for RED HORSE)Supervision, Inspection, & Overhead (SIOH)Air Force Real Property Government FurnishedEquipment (GFE)SOURCE: AFI 32-1021 – Attachment 1, AFI 65-601 V1


UNFUNDED COSTS (NO-CLASS WORK)Design (except design-build)U.S. Military labor, including RED HORSEReal Property GFE from other DOD or governmentagencies– If the AF gives GFE to itself, it’s a funded costWar Reserve Materials (Tents, ECUs, generators, etc)Modular Force Protection (T-walls, barriers)Relocateable facilities (trailers, pods, CHUs, etc)SOURCE: AFI 32-1021 – Attachment 1 & AFI 65-601 V1 -9.14.340


EXCLUDED COSTS (NO-CLASS WORK)Furniture including pre-wired work stationsComputers, electronics, etcEnd User type of equipmentUser should pay for these from their own funds!!!!41


SPECIAL CASE:BUILDING DEMOLITIONIncident (In way of construction project)– APF Project: ConstructionIsolated: No Class42


EQUIPMENT CLASSIFICATIONA piece of equipment (i.e. not RPIE) can be purchasedwith O&M funds if $250K or less– Considered an unfunded cost– If >$250K must use Appn 3080 – long process– Relocateable Buildings (RLB)Tension Fabric Structures (TFSs) with a rigid frame– Cannot be purchased as “equipment” using perspecific Congressional instruction, purchase asconstruction– <strong>The</strong> TSF, foundations, utilities, <strong>and</strong> site prep areall considered Construction <strong>and</strong> included asfunded items on 1391s43


COMMUNICATIONS REQUIREMENTSIf project is new construction: everything is included asfunded costs except:– Actual <strong>com</strong>m equipment• Computers• Servers• UPS44


FUNDINGSOURCES45


HOST NATIONType of work: Construction &SustainmentScope of work: Large ScaleFacilities & RepairsTiming/<strong>Process</strong>: Unknown/VariesLocation Issues: Country Specific– Countries “Can Pay - ShouldPay” (CP-SP) principleTypical Uses: Infrastructure &Large FacilitiesHow to get started: Talk w/ HHQ onrequirement <strong>and</strong> strategy46


OCO MILCONType of work: ConstructionScope of work: Large ScaleTiming/<strong>Process</strong>: 1 year/CongressionalAppropriationLocation Issues: Locations driven byOSD <strong>and</strong> CongressTypical Uses: New Facilities <strong>and</strong>InfrastructureHow to get started: Submit 1391– CENTCOM validates, prioritizes<strong>and</strong> advocates requirements47


REGULAR MILCONType of work: ConstructionScope of work: Large ScaleTiming/<strong>Process</strong>: > 2 years/CongressionalAppropriation <strong>and</strong> AuthorizationLocation Issues: GDP LocationsTypical Uses: New Facilities &InfrastructureHow to get started: Submit 1391– Aligned with Base Master Plan– Can take five years to execute– May require TOA– May require HN approval48


CONTINGENCY CONSTRUCTIONAUTHORITY - CCAType of work: ConstructionScope of work: Large ScaleTiming/<strong>Process</strong>: < 1 year/OSD Approval(limited to $200M)Location Issues: Limited to IraqTypical Uses: “Break the Glass” rqmntsHow to get started: Submit 1391– CENTCOM validates, prioritizes<strong>and</strong> advocates requirements49


CONTINGENCY CONSTRUCTIONAUTHORITY – CCA (Cont.)• Project must meet the followingcriteria:• Construction > $750K necessary tomeet urgent operational rqmnts• Construction is not carried out atlocation where U.S. is reasonablyexpected to have a long termpresence• U.S. has no intention of usingconstruction after the operationalrqmnts satisfied• Level of construction is minimumnecessary to meet the temp rqmnts50


UNSPECIFIED MINOR MILITARYCONSTRUCTIONType of work: ConstructionScope of work: Medium ScaleTiming / <strong>Process</strong>: 4 months/Congressional NotificationLocation Issues: NoneTypical Uses: New Facilities <strong>and</strong>InfrastructureHow to get started: Submit 139151


TROOP LABORType of work: Construction &RepairsScope of work: Small ScaleFacilitiesTiming/<strong>Process</strong>: < 1 year / HHQApprovalLocation Issues: NoneTypical Uses: “Break the Glass”requirementsHow to get started: Submit 1391– RED HORSE reports directlyto COMUSAFCENT52


OPERATIONS & MAINTENANCE - O&MType of work: Minor Construction (MC),Repair, MaintenanceScope of work: Small Scale (MC


Operations & MaintenanceMain source for construction projectsCommon programming rqmnts:– Stress Tension Shelter (Fabric)– Billeting– Relocatable Buildings (RLBs)– Repair by Replacement– Tilt-up Construction– Troop Labor– MSA Berms– Runway/Taxiway Repair54


75%RULE55


Historic Facility?No75% RuleYesRepair Costs > 75% ofPlant ReplacementValue?NoProceedYesReplaceFacilityORTo proceed with proposed work:1) Ac<strong>com</strong>plish Economic Analysis-- If repair notmore economical, must reclassify work asconstruction2) Obtain waiver to 75% rule3) Still must obtain approval for project. Waiverauthority may be different than approvalauthority!!NOTE: At NO time shall cost to repair facility exceed replacement cost. Ifrepair work exceeds replacement cost, facility MUST be replaced.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!