Coal Dust Management Presentation - August 2012

Coal Dust Management Presentation - August 2012

Coal Dust Management Presentation - August 2012

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Dalrymple Bay <strong>Coal</strong> TerminalExpansionStage Capacity Construction Construction CostMtpa Start Completion $ million1 15 1980 1983 2501A 22.5 1988 1990 42 26.5 1991 1995 1402A 28.5 1995 1996 43 33 Oct-96 Dec-98 1854 37.5 Jun-98 Oct-99 255 45.5 Apr-01 Feb-02 45*6 56 Apr-02 Jun-03 88*Short Gain 59 Jul-04 Aug-06 31.1*7x Phase 1 68 Sep-04 Mar-08 561.7*7x Phase 2/3 Step A 72 Oct-04 Dec-08 746*7X Phase 2/3 85 Jun-09* Excludes finance costs