ILW Planning and Scheduling_2_Animation.pdf
ILW Planning and Scheduling_2_Animation.pdf
ILW Planning and Scheduling_2_Animation.pdf
- No tags were found...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Schedule Updates & Maintenance• Formal Progress Meetings did not start until after c.3moths of the Project start. This was because the planwas still being constructed over this period• Fortnightly meeting with Design Office to check onprogress during the Design Stage• Schedule was updated formally fortnightly during DesignStage• Formal, minuted planning meetings dealt withmanagerial issues (resources required/available etc)• Schedule was maintained by planning resourceinteracting with WP Managers <strong>and</strong> attending meetings• Only applied detailed linkages carefully <strong>and</strong> whennecessary to see the effects of slippage• Schedule was re-baselined once