12.07.2015 Views

David Evans & Associates Section 203 update - the Oregon ...

David Evans & Associates Section 203 update - the Oregon ...

David Evans & Associates Section 203 update - the Oregon ...

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Oregon</strong> InternationalPort of Coos Bay<strong>Section</strong> <strong>203</strong> StudiesChannel ModificationsFeasibility Studies/Environmental Impact Statement(FS/EIS)


<strong>Oregon</strong> InternationalPort of Coos BayWRDA <strong>Section</strong> <strong>203</strong> Process:Channel Modification Project• Investigate potential navigation improvements under WaterResources Development Act of 1986 (<strong>Section</strong> <strong>203</strong>)• U.S. Army Corps of Engineers (Corps) is <strong>the</strong> lead agency• Authorizes non-Federal interest to undertake <strong>the</strong>ir ownfeasibility study of proposed navigation improvements• Studies must comply with Corps guidance• ASA makes a recommendation to Congress


<strong>Oregon</strong> InternationalPort of Coos BayWhy <strong>Section</strong> <strong>203</strong> Process?• Potential for Federal cost sharing of channel modificationconstruction• Maintain Federal navigation channel status (O&M costscovered or cost shared by <strong>the</strong> Federal government)• Permitting process somewhat streamlined


<strong>Oregon</strong> InternationalPort of Coos BayStudy Phases• Phase 1: Preliminary Studies (2007–2008)• Phase 2a: Alternative Formulation & Detailed TechnicalStudies (2009-2011)• Phase 2b: Draft FS & EIS (2012-2013)• Phase 3: Final FS & EIS (2013-2014)


<strong>Oregon</strong> InternationalPort of Coos BayPhase 1: Preliminary Studies (2007-2008)• Fatal Flaw Analysis– Economic (Benefit/Cost)– Environmental (Henderson Marsh Mitigation)– Engineering (Dredge Disposal, Preliminary Costs)• Wetland Delineation of Henderson Marsh• Preliminary Mitigation Plan for Henderson Marsh• Public Scoping for FS/EIS


<strong>Oregon</strong> InternationalPort of Coos BayPhase 2a: Alternative Formulation &Detailed Studies (2009-2011)• Preliminary Screening of Possible Commodities and TerminalLocations• Selected Configurations to Study in Detail (AlternativeFormulation)• Detailed Technical Studies– Engineering– Economics– Environmental


<strong>Oregon</strong> InternationalPort of Coos BayPhase 2a: Preliminary Screening Results• Expansion or development of terminals downstream of RM 9• Full range of commodities examined• Alternative Formulation– No deepening, 400’ wide channel– 45’ deep, 400’ wide channel– 49’deep, 450’ wide channel• Henderson Marsh used for dredge disposal, so site can bedeveloped as a terminal (49’ deep, 450’ wide)


<strong>Oregon</strong> InternationalPort of Coos BayChannel Modifications AlternativesWidthsconsidered:400 ft to 450 ftDepthsconsidered:-37 ft to -49 ft


<strong>Oregon</strong> InternationalPort of Coos BayPhase 2b: Draft Feasibility Study &Environmental Impact Study (2012-2013)• Complete Review of Detailed Technical Studies (April 2012)• Complete Draft FS/EIS (May 2013)Phase 3: Final FS/EIS (2013-2014)• Complete Final FS/EIS & Record of Decision (February 2014)


<strong>Oregon</strong> InternationalPort of Coos BayWhat is in <strong>the</strong> Feasibility Study?• Statement of Problem• Description of Alternatives• Public Involvement and Coordination• Engineering Studies to support economic and environmentalanalysis• Economics Analysis (National Economic Development)• Environmental Analysis (NEPA & o<strong>the</strong>r compliance)• Study Conclusions and Recommendations


<strong>Oregon</strong> InternationalPort of Coos BayPhase 2a: Detailed Studies – Engineering• Main Engineering Report– Federal Project– Non-Federal Improvements– Dredging Feasibility– Costs• Hydrodynamic, Sediment Transport Modeling andWater Quality Report• Ocean Entrance & Offshore Modeling Report• Shoreline Change Report• Geotechnical Report


<strong>Oregon</strong> InternationalPort of Coos BayPhase 2a: Detailed Studies – Economics• Benefit/Cost Analysis Report– Market Share– Socioeconomics– Benefit/Cost Analysis• Financial Plan


<strong>Oregon</strong> InternationalPort of Coos BayPhase 2a: Detailed Studies - Environmental• Environmental Inventory Report• Ecological Mitigation Analysis Report• Cultural Resources Report• Biological Resources Technical Report• Sediment Analysis Report• Traffic & Transportation Report• Light Pollution and Visual Resources Report• Land Use Report• Biological Assessment


<strong>Oregon</strong> InternationalPort of Coos BayPhase 2b: Draft FS / EIS• Respond to and incorporate comments from <strong>the</strong> Port and<strong>the</strong> Corps on Detailed Technical Studies• Conduct technical studies indicated by Phase 2a results orCorps review• Use Alternative Formulation Screening Report and DetailedTechnical Studies to develop full Draft FS / EIS Report forPort and Corps review• Develop Administrative Draft FS / EIS


<strong>Oregon</strong> InternationalPort of Coos BayPhase 2b: Draft FS / EIS• Complete Draft Technical Studies – April 2012• Preliminary Draft FS/EIS - September 2012• Corps Agency Technical Review – November 2012• Independent Expert Panel Review – February 2013• Draft FS/EIS – May 2013


<strong>Oregon</strong> InternationalPort of Coos BayPost-Phase 3:Permitting, Design, & Construction• Final FS/EIS & Record of Decision – February 2014• ASA Recommendation to Congress – February 2015• Acquire Land Use Permits – January 2015• Acquire Environmental Permits – November 2015• Complete Design – November 2015• Complete Construction – August 2018


Questions??<strong>Oregon</strong> InternationalPort of Coos Bay


<strong>Section</strong> <strong>203</strong>/204 Flowchart

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!