We think that the Sardar Sarovar Projects as they stand are flawed, that resettlement and rehabilitation <strong>of</strong>all those displaced by the projects is not possible under the prevailing circumstances, and that theenvironmental impacts <strong>of</strong> the projects have not been properly considered or adequately addressed.The history <strong>of</strong> environmental aspects <strong>of</strong> Sardar Sarovar is a history <strong>of</strong> non-compliance. There is nocomprehensive impact statement. The nature and magnitude <strong>of</strong> environmental problems and solutionsremain elusive.94. Shri Shanti Bhushan submitted that it had become necessary for some independent judicial authority to reviewthe entire project, examine the current best estimates <strong>of</strong> all costs (social, environmental, financial), benefits andalternatives in order to determine whether the project is required in its present form in the national interest, orwhether it needs to be restructured/modified.95. Shri Shanti Bhushan further submitted that environmental impacts <strong>of</strong> the projects were going to be massiveand full assessment <strong>of</strong> these impacts had not been done. According to him the latest available studies show thatstudies and action plans had not been completed and even now they were lagging behind pari passu. It was alsocontended that mere listing <strong>of</strong> the studies does not imply that everything is taken care <strong>of</strong>. Some <strong>of</strong> the studies were<strong>of</strong> poor quality and based on improper data and no independent body had subjected these to critical evaluation.Re: Environmental clearance96. As considerable stress was laid by Shri Shanti Bhushan challenging the validity <strong>of</strong> the environmental clearancegranted in 1987 inter alia on the ground that it was not preceded by adequate studies and it was not a consideredopinion and there was non-application <strong>of</strong> mind while clearing the project, we first propose to deal with the contention.97. The events after the Award and upto the environmental clearance granted by the Government vide its letterdated 24 June 1987 would clearly show that some studies, though incomplete, had been made with regard todifferent aspects <strong>of</strong> the environment. Learned counsel for the respondents stated that in fact on the examination <strong>of</strong>the situation, the claim made with regard to the satisfactory progress was not correct. In order to carry out thedirections in the Award about the setting up <strong>of</strong> an authority, the Inter-State Water Disputes Act, 1956 was amendedand Section 6-A was inserted to set out how a statutory body could be constituted under the Act. On 10 September1980 in exercise <strong>of</strong> the powers conferred by Section 6-A <strong>of</strong> the Act the Central Government framed a scheme,constituted the <strong>Narmada</strong> Control Authority to give effect to the decision <strong>of</strong> the Award.98. In January 1980, the Government <strong>of</strong> Gujarat submitted to the Central Water Commission a detailed projectreport in 14 volumes. This was an elaborate report and dealt with various aspects like engineering details, canalsystems, geology <strong>of</strong> area, coverage <strong>of</strong> command area, etc. On 15 February 1980 the Central Water Commissionreferred SSP to the then Department <strong>of</strong> Environment in Department <strong>of</strong> Science and Technology. At that point <strong>of</strong>time, environmental clearance was only an administrative requirement. An environmental checklist was forwardedto Government <strong>of</strong> Gujarat on 27 February 1980 which sought to elucidate information including following ecologicalaspects:i. Excessive sedimentation <strong>of</strong> the reservoir,ii.iii.iv.Waterlogging,Increase in salinity <strong>of</strong> the groundwater,Ground water recharge,v. Health hazard-water borne diseases, industrial pollution etc.,vi.vii.viii.ix.Submergence <strong>of</strong> important minerals,Submergence <strong>of</strong> monuments,Fish culture and aquatic life,Plant life-forests,x. Life <strong>of</strong> migratory birds,17
xi.xii.National park and sanctuaries,Seismicity due to filling <strong>of</strong> reservoir.The Government <strong>of</strong> Gujarat accordingly submitted information from September 1980 till March 1983. Thisinformation was also submitted on physio-social and economic studies for <strong>Narmada</strong> Command Area coveringcropping pattern, health aspects, water requirement etc. A note <strong>of</strong> influence <strong>of</strong> Navagam dam on fish yield includingimpact on downstream fisheries was also submitted.99. The techno-economic appraisal <strong>of</strong> the project was undertaken by the Central Water Commission which examinedwater availability, command area development, construction etc. The project was considered in the twenty-secondmeeting <strong>of</strong> the Technical Advisory Committee on Irrigation, Flood Control and Multi-purpose projects held on6.1.1983 and found it acceptable subject to environmental clearance.100. At this point <strong>of</strong> time, the matter was handled by the Department <strong>of</strong> Science and Technology which also hada Department dealing with the environment. The Environmental Appraisal Committee <strong>of</strong> the Department <strong>of</strong>Environment, then headed by a Joint Secretary, had in its meeting held on 12.4.1983 approved the project, inprinciple, and required that further data be collected. This Environmental Appraisal Committee dealt with theproject on two other occasions, namely on 29.3.1985 when it deferred meeting to await report <strong>of</strong> Dewan Committeeon soil conservation and thereafter on 6.12.1985 when it deferred the meeting to await comments from the ForestDepartment. As stated hereafter, subsequently the Secretary <strong>of</strong> newly constituted Ministry <strong>of</strong> Environment andForests took up further consideration <strong>of</strong> this project along with other higher <strong>of</strong>ficials.101. After the project was approved, in principle, studies and collections <strong>of</strong> data were continuing. In May 1983 the<strong>Narmada</strong> Planning Group, Government <strong>of</strong> Gujarat after completion <strong>of</strong> preliminary surveys submitted work plansfor various activities such as cropping pattern, health aspects, water requirements, distribution system, lay out andoperation, development plan <strong>of</strong> the command, drainage and ground water development.102. In July 1983, a study report on ‘Ecology and Environment Impact <strong>of</strong> Sardar Sarovar Dam and its Environs’prepared by MS University was also submitted by Government <strong>of</strong> Gujarat, covering the issues as mentionedbelow: climate, geology, soil, land use, forest and wildlife, aquatic vegetation, water regime (salinity, tidal movementsetc.), fisheries, health, seismicity.103. A review meeting was convened by the Secretary, Ministry <strong>of</strong> Water Resources in January 1984 which wasattended by a representative <strong>of</strong> the Department <strong>of</strong> Environment. During this meeting, it was emphasised that theissues regarding catchment area treatment, impact on wildlife, health, water logging etc. should be studied indepth for assessment. The issue <strong>of</strong> charging <strong>of</strong> cost <strong>of</strong> catchment area treatment to the project was also discussed.To sort out this matter, a meeting was subsequently convened by the Member, Planning Commission on 23 May1984 in which the Ministry <strong>of</strong> Environment & Forests took a stand that there was a need for an integrated approachto basin development covering the catchment and command area. A project report, therefore, should be preparedto cover these aspects. Since the catchment area <strong>of</strong> <strong>Narmada</strong> Sagar and Sardar Sarovar was very vast, it wasdecided that an Inter-Departmental Committee should be set up by the Ministry <strong>of</strong> Agriculture under theChairmanship <strong>of</strong> Dr M.L. Dewan. This group could submit its report only in August 1985 covering areas <strong>of</strong>catchment <strong>of</strong> <strong>Narmada</strong> and Sardar Sarovar and recommended that at least 25-30 percent <strong>of</strong> the area might requiretreatment for these projects.104. The consideration <strong>of</strong> the project in the Ministry, therefore, got deferred for this report on catchment areatreatment. During this time, Government <strong>of</strong> Madhya Pradesh entrusted the studies on flora for <strong>Narmada</strong> ValleyProject to the Botanical Survey <strong>of</strong> <strong>India</strong> and other related surveys were being carried out. Even though there wasa request on 10 June 1985 from the Chief Minister <strong>of</strong> Gujarat to the Minister <strong>of</strong> State for Environment and Forestsfor delinking <strong>of</strong> catchment area treatment works on clearance <strong>of</strong> the project, but this request was not agreed.105. By this time the approval <strong>of</strong> SSP was being considered by the Secretary, Ministry <strong>of</strong> Environment and Forestswho invited other high <strong>of</strong>ficials in a review meeting which was held on 31 December 1985 under his Chairmanship.In this meeting, detailed presentations were made by the state <strong>of</strong>ficials <strong>of</strong> Gujarat, Madhya Pradesh and Maharashtraas well as the experts who were involved in preparation <strong>of</strong> plans. The Secretary, Ministry <strong>of</strong> Environment andForests assessed and reviewed readiness on various environmental aspects like catchment area treatment,compensatory afforestation, rehabilitation, command area development, labour force and health issues, aquaticspecies, seismicity etc. and discussed the available reports in detail in the presence <strong>of</strong> the <strong>of</strong>ficers <strong>of</strong> the Central/18