Jobsite Updates<br />
1111 I-20 Monroe<br />
The I-20 project in Monroe is complete! This was a challenging project due to<br />
the time constraint, 7 am – 7 pm work hours; traffic count; and lane closure restrictions.<br />
We paved SMA during the winter months with over a 100 mile<br />
haul. The I-20 project team would like to thank everyone for their help and support<br />
in completing this job.<br />
Leanne Bagley, Project Manager<br />
1140 Bayou Rigolette Emergency Bridge Replacement<br />
Ribbon cutting for Bayou Rigolette Emergency Bridge Replacement<br />
was held March 12, <strong>2012</strong>. Those in attendance were Mayor Clarence<br />
Fields of Pineville, members of the Rapides Parish Police Jury and<br />
Chamber of Commerce, as well as several local residents. <strong>Construction</strong><br />
began in October 2011 and finished March <strong>2012</strong>. The project consisted<br />
of removal of the existing bridge which burnt March of 2011,<br />
constructing a 275' 11 span pre-cast bridge, 3500 cu/yds of embankment<br />
and 273 tons of asphalt. Through the addition of two change orders, we added approximately<br />
41,000 dollars worth of revenue to the project bringing it from 830,000 to 871,000. Those key to the<br />
project were Jerry Burnaman, who's crew drove all the piles and built the bridge, Bert Dauzat and Phillip<br />
Dauzat, who's crew placed embankment, Jimmy Lachney, who's crew laid the asphalt, and Tina<br />
Huffman who was the project accountant. Special thanks to the Equipment/Transportation division<br />
for making equipment moves/hauls in a timely manner.<br />
Davis Bordelon, Project Coordinator<br />
1141 Patterson Slough to Morman Slough Bridges and Approaches<br />
Job 1141 is located in Starks, Louisiana near the Texas State line.<br />
<strong>Construction</strong> consists of building one mile of detour road and four<br />
temporary detour bridges. Traffic will be relocated onto the detours<br />
and the four existing concrete bridges on La State Hwy 12 will be<br />
replaced. Estimated cost of the project is $10,289,000. Project<br />
start date is March 1, 2102 and completion is expected September<br />
2013.<br />
Alsey Lachney,III Project Manager<br />
1144 La 107 Ruby Wise Elementary/Pine Grove Drive<br />
We began Job 1144 the last week of January. As of mid-March, we<br />
have completed Site 1 and are roughly 50% complete with Site 2. Brent<br />
Ducote’s base crew was able to battle through a wet February and complete<br />
all the base work on the project. Our milling crew has completed all<br />
the cold planning on the project, and Jimmy Lachney’s team has laid all<br />
the binder course on Site 2. Ride data for the binder course indicates<br />
great IRI numbers. We are now gearing up to start our wearing course<br />
operation, and the project completion date is set for <strong>April</strong> 20 th . Thanks to all the site crews, support<br />
teams, and sub-contractors who have made the project a success thus far.<br />
Justin Gaspard, Project Manager<br />