Control Room<br />
• TSV closed <strong>and</strong> water continued to flow.<br />
• I was told to clear the building.<br />
• Me….”you guys hit the top deck, I am not losing<br />
this *.%^^$$ing Powerhouse.”<br />
• Back down to start installing bolts.<br />
• Four bolts left out of twenty with two of them loose.<br />
• Pressure was extreme.<br />
• Install bolts against no air.<br />
• Used air wrench to tighten each as I installed them.<br />