Rural Water News Autumn 2006<br />
Leinster Region<br />
by Barry Deane &<br />
Joe Gallagher<br />
Since contract signing in<br />
May of this year with EPS<br />
Ltd., <strong>the</strong> contractor has been<br />
busy preparing <strong>the</strong>ir designs<br />
for each of <strong>the</strong> schemes. The<br />
majority of <strong>the</strong>se designs<br />
have now been sent to <strong>the</strong><br />
employer’s representative, T.<br />
J. O’Connor & Associates for<br />
<strong>the</strong>ir approval. EPS have<br />
also now submitted <strong>the</strong>ir construction<br />
programme for<br />
phase one of <strong>the</strong> project. It is<br />
hoped that construction will<br />
be commencing on some of<br />
<strong>the</strong> schemes in October. At<br />
this stage all ESB applications<br />
have also been made and<br />
are currently being processed.<br />
***<br />
Most of <strong>the</strong> Advance Works<br />
have been completed at this<br />
stage, with one or two contracts<br />
to be finished in <strong>the</strong><br />
coming weeks. At this stage<br />
most schemes are looking at<br />
ways to reduce <strong>the</strong>ir unaccounted<br />
for water. The majority<br />
of schemes are progressing<br />
with universal metering,<br />
analysing <strong>the</strong>ir distribution<br />
systems and identifying problem<br />
areas.<br />
scheme is currently surveying<br />
<strong>the</strong> entire network for<br />
service connections. Meetings<br />
were held with all schemes in<br />
<strong>the</strong> bundle during August to<br />
progress universal metering.<br />
Borrmount GWS is also currently<br />
considering a network<br />
upgrade.<br />
Kildare<br />
Gormanstown GWS is currently<br />
upgrading sections of<br />
<strong>the</strong>ir scheme including<br />
replacing old copper fittings.<br />
The scheme is hoping that<br />
this, along with universal<br />
metering, will help to reduce<br />
unaccounted for water. The<br />
scheme met Kildare County<br />
Council and <strong>the</strong> NFGWS in<br />
August to look at ways of<br />
combating UFW.<br />
Kilkenny<br />
Upgrades are currently complete<br />
on Ballycallan,<br />
Baunmore, Coolagh<br />
Caherlesk, Kiloshulan,<br />
Newtown/Ovenstown and<br />
Parks Rathclevin. There are a<br />
number of proposals for fur<strong>the</strong>r<br />
upgrades to Coolagh<br />
Caherlesk and Highrath<br />
GWS and it is hoped <strong>the</strong>se<br />
will commence in <strong>the</strong> coming<br />
weeks. Any GWS with<br />
upgrading proposals for <strong>the</strong><br />
remainder of 2006 or 2007<br />
should contact Kilkenny<br />
County Council as <strong>the</strong>y will<br />
soon be preparing <strong>the</strong>ir submission<br />
for next year’s<br />
allocation.<br />
Laois<br />
Ballacolla GWS has begun a<br />
major upgrade on its network.<br />
Phase one of <strong>the</strong><br />
upgrade is now well underway.<br />
The group is also<br />
installing universal metering<br />
and bulk meters to try and<br />
reduce UFW.<br />
Offaly<br />
Upgrading works have started<br />
on Rath GWS and Killeigh<br />
GWS. These works consist of<br />
<strong>the</strong> laying of new mains and<br />
extension to <strong>the</strong> schemes and<br />
should be completed by <strong>the</strong><br />
end of November.<br />
***<br />
Reservoirs are almost complete<br />
on Ballinagar GWS and<br />
Bracknagh GWS. These will<br />
supply <strong>the</strong> growing schemes<br />
with <strong>the</strong> additional storage<br />
that <strong>the</strong>y require.<br />
***<br />
All GWS are encouraged to<br />
send details into Offaly Co.<br />
Co. of works that <strong>the</strong>y wish<br />
to complete in <strong>the</strong> coming<br />
year. These should be submitted<br />
before 10 November.<br />
Schemes are asked to send in<br />
design drawings, bill of<br />
quantities and costs so that<br />
<strong>the</strong>y can be included in next<br />
years RWP allocations.<br />
Wicklow<br />
Works on <strong>the</strong> Baltyboys<br />
GWS pipeline is substantially<br />
complete, with only snagging<br />
and minor works left to be<br />
taken care of.<br />
Carlow & Wexford<br />
Carlow Rural Water<br />
Monitoring Committee met<br />
during September. While <strong>the</strong><br />
number of GWS in <strong>the</strong> county<br />
has reduced <strong>the</strong>re are still a<br />
number of very active<br />
schemes. Although most of<br />
<strong>the</strong> water quality issues in <strong>the</strong><br />
county will be dealt with<br />
once <strong>the</strong> DBO contract is<br />
complete, <strong>the</strong>re are still a few<br />
small schemes outside of this<br />
process that need attention. It<br />
was proposed that <strong>the</strong>se items<br />
should be discussed at <strong>the</strong><br />
next meeting of <strong>the</strong> County<br />
Federation.<br />
***<br />
In Wexford, work is almost<br />
complete on <strong>the</strong> Blackstairs<br />
advance works contract. The<br />
The newly constructed 250,000 gallon reservoir at Ballinagar GWS. This was built to cater for <strong>the</strong> increasing<br />
demand on <strong>the</strong> scheme and will give <strong>the</strong> extra storage needed for fur<strong>the</strong>r development.<br />