Rural Water News Autumn 2006<br />

Leinster Region<br />

by Barry Deane &<br />

Joe Gallagher<br />

Since contract signing in<br />

May of this year with EPS<br />

Ltd., <strong>the</strong> contractor has been<br />

busy preparing <strong>the</strong>ir designs<br />

for each of <strong>the</strong> schemes. The<br />

majority of <strong>the</strong>se designs<br />

have now been sent to <strong>the</strong><br />

employer’s representative, T.<br />

J. O’Connor & Associates for<br />

<strong>the</strong>ir approval. EPS have<br />

also now submitted <strong>the</strong>ir construction<br />

programme for<br />

phase one of <strong>the</strong> project. It is<br />

hoped that construction will<br />

be commencing on some of<br />

<strong>the</strong> schemes in October. At<br />

this stage all ESB applications<br />

have also been made and<br />

are currently being processed.<br />

***<br />

Most of <strong>the</strong> Advance Works<br />

have been completed at this<br />

stage, with one or two contracts<br />

to be finished in <strong>the</strong><br />

coming weeks. At this stage<br />

most schemes are looking at<br />

ways to reduce <strong>the</strong>ir unaccounted<br />

for water. The majority<br />

of schemes are progressing<br />

with universal metering,<br />

analysing <strong>the</strong>ir distribution<br />

systems and identifying problem<br />

areas.<br />

scheme is currently surveying<br />

<strong>the</strong> entire network for<br />

service connections. Meetings<br />

were held with all schemes in<br />

<strong>the</strong> bundle during August to<br />

progress universal metering.<br />

Borrmount GWS is also currently<br />

considering a network<br />

upgrade.<br />

Kildare<br />

Gormanstown GWS is currently<br />

upgrading sections of<br />

<strong>the</strong>ir scheme including<br />

replacing old copper fittings.<br />

The scheme is hoping that<br />

this, along with universal<br />

metering, will help to reduce<br />

unaccounted for water. The<br />

scheme met Kildare County<br />

Council and <strong>the</strong> NFGWS in<br />

August to look at ways of<br />

combating UFW.<br />

Kilkenny<br />

Upgrades are currently complete<br />

on Ballycallan,<br />

Baunmore, Coolagh<br />

Caherlesk, Kiloshulan,<br />

Newtown/Ovenstown and<br />

Parks Rathclevin. There are a<br />

number of proposals for fur<strong>the</strong>r<br />

upgrades to Coolagh<br />

Caherlesk and Highrath<br />

GWS and it is hoped <strong>the</strong>se<br />

will commence in <strong>the</strong> coming<br />

weeks. Any GWS with<br />

upgrading proposals for <strong>the</strong><br />

remainder of 2006 or 2007<br />

should contact Kilkenny<br />

County Council as <strong>the</strong>y will<br />

soon be preparing <strong>the</strong>ir submission<br />

for next year’s<br />

allocation.<br />

Laois<br />

Ballacolla GWS has begun a<br />

major upgrade on its network.<br />

Phase one of <strong>the</strong><br />

upgrade is now well underway.<br />

The group is also<br />

installing universal metering<br />

and bulk meters to try and<br />

reduce UFW.<br />

Offaly<br />

Upgrading works have started<br />

on Rath GWS and Killeigh<br />

GWS. These works consist of<br />

<strong>the</strong> laying of new mains and<br />

extension to <strong>the</strong> schemes and<br />

should be completed by <strong>the</strong><br />

end of November.<br />

***<br />

Reservoirs are almost complete<br />

on Ballinagar GWS and<br />

Bracknagh GWS. These will<br />

supply <strong>the</strong> growing schemes<br />

with <strong>the</strong> additional storage<br />

that <strong>the</strong>y require.<br />

***<br />

All GWS are encouraged to<br />

send details into Offaly Co.<br />

Co. of works that <strong>the</strong>y wish<br />

to complete in <strong>the</strong> coming<br />

year. These should be submitted<br />

before 10 November.<br />

Schemes are asked to send in<br />

design drawings, bill of<br />

quantities and costs so that<br />

<strong>the</strong>y can be included in next<br />

years RWP allocations.<br />

Wicklow<br />

Works on <strong>the</strong> Baltyboys<br />

GWS pipeline is substantially<br />

complete, with only snagging<br />

and minor works left to be<br />

taken care of.<br />

Carlow & Wexford<br />

Carlow Rural Water<br />

Monitoring Committee met<br />

during September. While <strong>the</strong><br />

number of GWS in <strong>the</strong> county<br />

has reduced <strong>the</strong>re are still a<br />

number of very active<br />

schemes. Although most of<br />

<strong>the</strong> water quality issues in <strong>the</strong><br />

county will be dealt with<br />

once <strong>the</strong> DBO contract is<br />

complete, <strong>the</strong>re are still a few<br />

small schemes outside of this<br />

process that need attention. It<br />

was proposed that <strong>the</strong>se items<br />

should be discussed at <strong>the</strong><br />

next meeting of <strong>the</strong> County<br />

Federation.<br />

***<br />

In Wexford, work is almost<br />

complete on <strong>the</strong> Blackstairs<br />

advance works contract. The<br />

The newly constructed 250,000 gallon reservoir at Ballinagar GWS. This was built to cater for <strong>the</strong> increasing<br />

demand on <strong>the</strong> scheme and will give <strong>the</strong> extra storage needed for fur<strong>the</strong>r development.<br />