DEVRY BSOP 330 Week 5 Homework Problems Mater Production Schedule Problem 1
devry bsop 330 week 5 homework problems mater production schedule problem 1, 2 and 3,devry bsop 330 week 5 quiz,devry bsop 330,bsop 330,devry bsop 330 week 5 tutorial,bsop 330 week 5 assignment,devry bsop 330 week 5 help
devry bsop 330 week 5 homework problems mater production schedule problem 1, 2 and 3,devry bsop 330 week 5 quiz,devry bsop 330,bsop 330,devry bsop 330 week 5 tutorial,bsop 330 week 5 assignment,devry bsop 330 week 5 help
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>DEVRY</strong> <strong>BSOP</strong> <strong>330</strong> <strong>Week</strong> 5 <strong>Homework</strong><br />
<strong><strong>Problem</strong>s</strong> <strong>Mater</strong> <strong>Production</strong> <strong>Schedule</strong><br />
<strong>Problem</strong> 1, 2 and 3<br />
Check this A+ tutorial guideline at<br />
http://www.assignmentclick.com/bsop-<strong>330</strong>-<br />
devry/bsop-<strong>330</strong>-week-5-homeworkproblems-mater-production-scheduleproblem-1-2-and-3<br />
MASTER PRODUCTION SCHEDULE<br />
MAKE-TO-STOCK<br />
Beginning PAB prior to week number one is<br />
500.<br />
If the forecast is larger than the book orders,<br />
complete the MPS using the forecast demand.<br />
If the booked orders is larger than the<br />
forecast complete the MPS using the booked<br />
orders<br />
Lead-time for MPS releases is one week.<br />
All MPS releases must be in lot sizes of 250<br />
units.
Period order coverage is one period.<br />
1. Complete the MPS due line and the MPS<br />
released line.<br />
2. Complete the PAB line.<br />
3. Complete the ATP line.<br />
<strong>BSOP</strong> Master Planning, <strong>Week</strong> 5 Assignment,<br />
<strong>Problem</strong> Two<br />
Make-to-Stock MPS<br />
GIVENS FOR THE MPS PROBLEM:<br />
1. Beginning on-hand inventory prior to week<br />
one is 200 units.<br />
2. If the forecast is larger than the book<br />
orders, complete the MPS using the forecast<br />
demand. If the booked orders is larger than<br />
the forecast complete the MPS using the<br />
booked orders<br />
3. Lead-time for MPS planned orders is one<br />
week.<br />
4. All MPS releases must be in lot sizes of 200<br />
or multiples of 200.<br />
REQUIRED:<br />
Complete the MPS due and MPS planned lines.<br />
Calculate the new projected on-hand<br />
inventory line.<br />
Calculate the ATP line for the entire MPS.
<strong>BSOP</strong><strong>330</strong> Master Planning, <strong>Week</strong> 5, <strong>Problem</strong> 3<br />
Forecast Disaggregation<br />
Product Family Blenders<br />
Model Number<br />
Percent of the Annual Forecast<br />
B-100<br />
10.00%<br />
B-200<br />
7.00%<br />
B-300<br />
25.00%<br />
B-400<br />
30.00&<br />
B-500<br />
12.00%<br />
B-600<br />
16.00%<br />
Total<br />
100.00%<br />
Note: the total percentage must equal exactly<br />
100%.<br />
If the aggregate forecast for the family of<br />
blenders for the month of September is 5,000<br />
units, complete the chart below.