Period order coverage is one period.<br />
1. Complete the MPS due line and the MPS<br />
released line.<br />
2. Complete the PAB line.<br />
3. Complete the ATP line.<br />
<strong>BSOP</strong> Master Planning, <strong>Week</strong> 5 Assignment,<br />
<strong>Problem</strong> Two<br />
Make-to-Stock MPS<br />
GIVENS FOR THE MPS PROBLEM:<br />
1. Beginning on-hand inventory prior to week<br />
one is 200 units.<br />
2. If the forecast is larger than the book<br />
orders, complete the MPS using the forecast<br />
demand. If the booked orders is larger than<br />
the forecast complete the MPS using the<br />
booked orders<br />
3. Lead-time for MPS planned orders is one<br />
week.<br />
4. All MPS releases must be in lot sizes of 200<br />
or multiples of 200.<br />
REQUIRED:<br />
Complete the MPS due and MPS planned lines.<br />
Calculate the new projected on-hand<br />
inventory line.<br />
Calculate the ATP line for the entire MPS.