This project consisted of a 3-story, 42,000 SF<br />

Health & Wellness Center with Parking deck,<br />

Pool, Rehabilitaon Center, and Resident<br />

Rooms. The exisng kitchen serves three<br />

meals a day to 350 residents and approximately<br />

250 staff. As kitchen deliveries are made via<br />

the loading dock it must remain operaonal<br />

throughout construcon. Since the new HWC<br />

would restrict access to the loading dock,<br />

APM developed a sequence of construcon<br />

to provide temporary access via the use of<br />

a man li and temporary pla orm, prior to<br />

construcon commencing. APM managed this<br />

complex task to design, permit, schedule, and<br />

physically relocate the ulies in order to meet<br />

schedule requirements. The inial Schemac<br />

construcon cost esmate had a mulmillion<br />

dollar overage. APM developed value<br />

engineering to reduce the construcon cost<br />

without affecng the required programming.<br />

EXISTING TOWER RENOVATIONS<br />

The most challenging aspect of this project was that the exisng facility is<br />

operaonal twenty-four hours a day, seven days a week. Due to the constrained<br />

site, every part of the construcon process affected the Owner’s<br />

daily operaons, as well as the residents’ lives. Construcon was proposed<br />

to occur around three quarters of the exisng building, the first three floors<br />

would be renovated, and both entrance drives would be torn up and reconstructed<br />

with new ulies. The Owner’s preliminary plan was to construct<br />

the enre project all at once in a twenty-four month period. APM<br />

evaluated this approach and determined that it would be too intrusive on<br />

the daily operaons of the facility. A longer, but phased and sequenced<br />

construcon schedule was developed, which minimized the disrupon to<br />

facility operaons and the residents’ lives by liming the number of reloca-<br />

ons of operaons and exisng residents to the fullest extent possible. This<br />

new phased construcon approach allowed the Owner and Contractor to<br />

cohabitate onsite in harmony.