QCLNG Project Update Newsletter Edition 1 June 2102 - QGC
QCLNG Project Update Newsletter Edition 1 June 2102 - QGC
QCLNG Project Update Newsletter Edition 1 June 2102 - QGC
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
PIPELINE UPDATE Good progress<br />
With all pipe in country<br />
and transported to infield<br />
locations, work on the<br />
540km pipeline network has<br />
continued to gain momentum.<br />
On the 197km Gas Collection<br />
Header, all of the pipe is now<br />
strung out along the Right of<br />
Way and the work continues<br />
to advance on welding the<br />
sections of pipe together. To<br />
date over 90 per cent of the<br />
required welding has been<br />
achieved, with rigorous testing<br />
procedures being undertaken<br />
to ensure the integrity and<br />
safety of the finished product<br />
Preparation for Gas Collection Header pipe lowering-in<br />
PAGE 7<br />
and compliance with all<br />
regulatory requirements prior<br />
to burial.<br />
On the 334km Export Pipeline<br />
several work fronts have<br />
progressed with activities<br />
such as Right of Way clearing<br />
and grading, pipe stringing<br />
and bending, and welding,<br />
as well as work on some<br />
of the road crossings. At a<br />
location approximately 40<br />
kilometres north of Miles,<br />
construction has started on<br />
the Gas Collection Header<br />
Receipt Station. Once built,<br />
the Receipt Station will consist<br />
The Narrows Crossing Temporary Access way, construction of the Humpy Creek bridge complete<br />
of monitoring, control and<br />
maintenance equipment for<br />
the gas pipeline. The Receipt<br />
Station will gather the gas<br />
from the Collection Header and<br />
prepare it for transport along<br />
the Export Pipeline ultimately<br />
arriving for processing at the<br />
Delivery Station on Curtis<br />
Island prior to entering<br />
the LNG Plant.<br />
At the Narrows Crossing<br />
where the pipeline crosses<br />
from the mainland to Curtis<br />
Island, construction of the<br />
second temporary access<br />
bridge, over Targinie Creek,<br />
Lowering-in of the Gas Collection Header pipe<br />
is underway. This follows the<br />
completion last month of the<br />
shorter Humpy Creek Bridge<br />
and the temporary access<br />
way between the bridges.<br />
The installation of piling has<br />
commenced on what will<br />
be the longer of the two<br />
bridges at some 300 metres<br />
in total length.<br />
The first clearing works have<br />
also commenced at the site<br />
on Curtis Island where the<br />
pipeline will come onshore in<br />
the first half of next year and<br />
on the right of way connecting<br />
to the LNG Plant.