12.12.2012 Views

QCLNG Project Update Newsletter Edition 1 June 2102 - QGC

QCLNG Project Update Newsletter Edition 1 June 2102 - QGC

QCLNG Project Update Newsletter Edition 1 June 2102 - QGC

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

PIPELINE UPDATE Good progress<br />

With all pipe in country<br />

and transported to infield<br />

locations, work on the<br />

540km pipeline network has<br />

continued to gain momentum.<br />

On the 197km Gas Collection<br />

Header, all of the pipe is now<br />

strung out along the Right of<br />

Way and the work continues<br />

to advance on welding the<br />

sections of pipe together. To<br />

date over 90 per cent of the<br />

required welding has been<br />

achieved, with rigorous testing<br />

procedures being undertaken<br />

to ensure the integrity and<br />

safety of the finished product<br />

Preparation for Gas Collection Header pipe lowering-in<br />

PAGE 7<br />

and compliance with all<br />

regulatory requirements prior<br />

to burial.<br />

On the 334km Export Pipeline<br />

several work fronts have<br />

progressed with activities<br />

such as Right of Way clearing<br />

and grading, pipe stringing<br />

and bending, and welding,<br />

as well as work on some<br />

of the road crossings. At a<br />

location approximately 40<br />

kilometres north of Miles,<br />

construction has started on<br />

the Gas Collection Header<br />

Receipt Station. Once built,<br />

the Receipt Station will consist<br />

The Narrows Crossing Temporary Access way, construction of the Humpy Creek bridge complete<br />

of monitoring, control and<br />

maintenance equipment for<br />

the gas pipeline. The Receipt<br />

Station will gather the gas<br />

from the Collection Header and<br />

prepare it for transport along<br />

the Export Pipeline ultimately<br />

arriving for processing at the<br />

Delivery Station on Curtis<br />

Island prior to entering<br />

the LNG Plant.<br />

At the Narrows Crossing<br />

where the pipeline crosses<br />

from the mainland to Curtis<br />

Island, construction of the<br />

second temporary access<br />

bridge, over Targinie Creek,<br />

Lowering-in of the Gas Collection Header pipe<br />

is underway. This follows the<br />

completion last month of the<br />

shorter Humpy Creek Bridge<br />

and the temporary access<br />

way between the bridges.<br />

The installation of piling has<br />

commenced on what will<br />

be the longer of the two<br />

bridges at some 300 metres<br />

in total length.<br />

The first clearing works have<br />

also commenced at the site<br />

on Curtis Island where the<br />

pipeline will come onshore in<br />

the first half of next year and<br />

on the right of way connecting<br />

to the LNG Plant.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!