5. Major Accomplishments<br />

◈ Commissioning, Tuning & Test<br />

Project Description<br />

Project Name : Shuqaiq 720MW x 4unit Steam<br />

Power Plant Project<br />

Client : Saudi Electric Company<br />

Contractor : Hyundai Heavy Industries<br />

Scope of Work : Commissioning & Technical<br />

advise for system engineer.<br />

Contract Period : Nov.2016 ~ Aug.2017<br />

UMC/APC Tuning<br />

It fine-tunes the control and process of each<br />

plant to optimize the plant's operation and<br />

optimizes the plant's characteristics so that the<br />

plant can operate with contracted performance.<br />

Project commissioning is for the process of Power Plant Project assuring that all components<br />

and systems of the plant are designed, installed, tested, operated, and maintained according to<br />

the contractual requirements.<br />

The main objective of commissioning is the final handover of the unit to the owner,<br />

guaranteeing its operability in terms of performance, reliability, safety and information<br />

traceability.<br />

The objectives of the commissioning are to:<br />

1) Ensure that the structures, systems and components have been constructed,<br />

manufactured and installed correctly and that they are functioning as anticipated by the design<br />

specification.<br />

2) Demonstrate that the systems, structures, and components operate in accordance<br />

with design bases, specifically in accordance with the contractual requirements.<br />

This demonstration primarily implies verifying:<br />

• That the unit operates correctly under steady state and transient conditions,<br />

• That plant performance complies with the contractual requirements,<br />

• That contractual operating requirements are suitably adapted to the plant.<br />

3) Provide measured data for use as a reference in subsequent plant operation and testing<br />

during plant-life.<br />

4) Bring the plant to rated capacity and sustained power operation and confirm that the plant<br />

is capable of generating the power required under the specified operating conditions.<br />