No. 18906<br />

APPROVED<br />

Change Order<br />

No. 002 for<br />

the PB15<br />

Project<br />

Yeas<br />

Noes<br />

No. 18907<br />

APPROVED<br />

Allowance<br />

Expenditure<br />

Authorization<br />

(AEA) Owners<br />

Contingency<br />

Allowance<br />

(OCC) No. 20<br />

for BP01,<br />

Schneider<br />

Middle <strong>School</strong><br />

Motion by Mrs. Morgan, seconded by Mr. Braden, that the Board<br />

approve Change Order No. 002 to DT Construction for the BP15<br />

project to extend the Substantial Completion dates, as shown on page<br />

209, Section IX of the agenda, and copied below.<br />

On April 27, <strong>2006</strong>, <strong>Pasadena</strong> <strong>Independent</strong> <strong>School</strong> <strong>District</strong> approved the<br />

Construction Contract to DT Construction as part of the 2004 Bond<br />

Program for the BP15, Meador, LF Smith, Freeman, and Fisher<br />

Elementary and Queens Intermediate <strong>School</strong> project. The attached<br />

Change Order No. 002 reflects an extension to the construction<br />

contract schedule due to permitting.<br />

The Substantial Completion dates are as follows:<br />

LF Smith ES: October 1, <strong>2006</strong><br />

Queens IS: October 14, <strong>2006</strong><br />

Freeman ES: <strong>November</strong> 17, <strong>2006</strong><br />

Fisher ES: <strong>November</strong> 17, <strong>2006</strong><br />

Meador ES: <strong>November</strong> 18, <strong>2006</strong><br />

No financial implications.<br />

We recommend that the Board of Trustees approve Change Order No.<br />

002 to DT Construction for the BP15 project to extend the Substantial<br />

Completion dates.<br />

Trustees Sullivan, Braden, Morgan, Kendrick<br />

None<br />

Motion by Mrs. Morgan, seconded by Mr. Braden, that the Board<br />

approve AEA OCC No. 20 to Durotech for the Schneider Middle <strong>School</strong><br />

in the credit amount of ($8,563), as shown on page 210, Section IX of<br />

the agenda, and copied below.<br />

On June <strong>28</strong>, 2005 <strong>Pasadena</strong> <strong>Independent</strong> <strong>School</strong> <strong>District</strong> approved the<br />

Construction Contract to Durotech Inc. as part of the 2004 Bond<br />

Program.<br />

AEA OCC No. 20 reflects credits to the construction contract as follows:<br />

PR No. 04R3, Kitchen plumbing: ($ 830)<br />

PR No. 036-RFI 36, Revise remainder of<br />

grease waste lines from CPVC<br />

to schedule 40PVC: ($4,167)<br />

PR No. 44R3, Revise selected<br />

food service Items: ($2,987)