Warranty applications

Structural Glazing applications are typically high

profile buildings and structures. Because of this, and

the obvious risks involved, AFTC’s customers can apply

for warranties on their applications. If a warranty is

issued highly depends on the project, the location and

the approval of the AFTC Head office. To obtain these

warranties, the customer will need to follow the steps

as shown in the Warranty Business Map;

When all steps are fulfilled and the required

paperwork has been arranged, AFTC will grant

a written warranty on the application. For more

information concerning warranties in structural

glazing, please contact your AFTC Representative.

Facade building

The difference between structural glazing and façade

panels is the material the panel is made of. Where

in structural glazing the panel obviously is made of

glass, in facades, the panel can be made of different

materials. In most cases an aluminium composite or

sandwich panel is used but wood or plastic can also

be used in the manufacturing of these panels. The

requirements concerning warranty are the same as

for Structural Glazing applications

Products: SC12G, SC12W, SC12B

AFTC Warranty Business Process Map

Only once for System Business

At system designer

Steps

First

Customer

visit

Samples for

Tesng at

laboratory

Build

Prototype

at

customer

Equipment

for

producon

Audit

Producon

by AFTC/

Instute

Producon

finished

Customer

project

Inspecon

Data

Project

specs.

Drawings

etc..

Representave

Substrates

Go/No Go

details

Prototype

Producon

site. Signing

contract for

warranty

Producon

data

Complete

package

producon

data

Inspecon

reports

1,3,5 years

to AFTC

Result

Project

Timing

Go/No Go

project

Go/No Go

Equipment,

maunals &

training

Product

delivery

Audit

report

Sign Final

warranty

Timeline

8-10 weeks aer signing for the project