Preparing the Installation

• Ensure sufficient air circulation is provided around the inverter when it is installed. If the

inverter is to be installed inside a panel, enclosure, or cabinet rack, carefully consider

the position of the inverter’s cooling fan and the ventilation louver. The cooling fan must

be positioned to efficiently transfer the heat generated by the operation of the inverter.

• If you are installing multiple inverters in one location, arrange them side-by-side and

remove the vent covers. Use a flat head screwdriver to remove the vent covers. Only

the H100 inverters rated for up to 30 kW may be installed side-by-side.