here - Atomic Energy Regulatory Board
here - Atomic Energy Regulatory Board
here - Atomic Energy Regulatory Board
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
! The experts committee, which reviewed the seismic<br />
qualification report, noted that the stresses as brought<br />
out in the analysis for seismic response of Calandria -<br />
End Shield integral assembly of KGS-1&2 (also<br />
applicable for KGS-3&4/RAPP-5&6) are found to meet<br />
the stipulated requirements of ASME Section-III,<br />
subsection-NB.<br />
! NPCIL has agreed, as per AERB stipulation, for<br />
upgradation of Equipment Decontamination Facility to<br />
handle equipment with surface dose rate upto 50 mSv/<br />
h, as against 10 mSv/h envisaged in the earlier design.<br />
! It was noted, during regulatory inspections, that<br />
dimensional mismatch between foundation and<br />
equipment base-plate has occurred for few equipment<br />
(e.g., Active Process Water Cooling System pumps and<br />
pedestal of HP Heater 6 at KGS-3 and PHT Storage<br />
Tank, Vapour Suppression Pool Re-circulation Pump<br />
and End-shield Cooling Pumps of RAPP-5). The site<br />
has been asked to prepare a complete list of such<br />
equipment for measurement of vibrations of piping and<br />
equipment during commissioning phase. Designers were<br />
asked to re-look into the stress analysis carried out earlier,<br />
in view of changes in the support design.<br />
! NPCIL was asked to ensure proper maintenance of<br />
water chemistry in the vapour suppression pool to<br />
minimise the corrosion effect on the down-comers in<br />
the system. This is based on the operational experience<br />
from NAPS/KAPS.<br />
! Geometric imperfections were noticed on the outer<br />
surface profile of inner containment dome of KGS-3.<br />
Based on the review by AERB, corrective measures were<br />
incorporated for the subsequent dome construction.<br />
Safety of as-built dome was found satisfactory under<br />
all applicable design load combinations.<br />
KK- NPP-1&2<br />
For KK-NPP consisting of two Russian design VVER<br />
reactors, each of 1000 MWe capacity, Co-ordination Group<br />
(KK-CG) along with the Specialist Groups (SGs) carries out<br />
the first level of review. The ACPSR-LWR, at the second<br />
level, reviews the recommendations of KK-CG/SGs along<br />
with the relevant documents. The review process is currently<br />
focused on the next stage of regulatory consent, i.e.,<br />
Clearance for Erection of Major Equipment (EE).<br />
The 88 th <strong>Board</strong> meeting was held at KK-NPP site.<br />
The members were apprised of the status of the construction<br />
of the Units. The members visited the power project and<br />
12<br />
witnessed the construction work in progress. A visit was also<br />
made to the IREL plant at Manavalakurichi.<br />
AERB <strong>Board</strong> Members with Site Officials at KK-NPP Site<br />
The review of specific topics like Reactor Pressure<br />
Vessel Design and related aspects, Water Chemistry and<br />
Materials has been completed. Specialist Group on PSA<br />
has been reviewing the PSA Level - 1 Report. Most of the<br />
issues that were brought out during the review of PSAR<br />
(Rev.1) have been satisfactorily addressed in PSAR (Rev.-<br />
2). Actions have been initiated towards resolution of the<br />
balance issues, as relevant to EE.<br />
Some of the salient observations/recommendations<br />
are the following.<br />
! The design requirements as given in PSAR packages on<br />
seismic and environmental qualification of safety related<br />
equipments and components have been reviewed.<br />
! The Validation and Verification (V&V) document for<br />
thermal hydraulic codes for accident analysis was<br />
reviewed and found acceptable. The methodology for<br />
review of V&V of Computer Based systems is under<br />
formulation.<br />
! Unbonded cables are being used for the first time for<br />
internal pre-stressing of the containment. A mock up<br />
using modified scheme for threading of cables in the<br />
horizontal duct has been conducted satisfactorily.<br />
! The plant is provided with a special cooling system,<br />
which caters to the heat load of spent fuel pond and<br />
core residual heat removal following reactor shut down.<br />
The consequences of sharing a normal process function<br />
and safety performance under different off-normal<br />
conditions were reviewed. This design practice followed<br />
in Russian plants was accepted subject to certain<br />
stipulations.