PRECINCT 1 - COMMISSIONER LISA BIRKMAN<br />

RM 620 Safety Improvements<br />

(Cornerwood to Wyoming Springs)<br />

CSJ: 0683-01-079<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

2000/2006 <strong>ROAD</strong> <strong>BOND</strong> COMPLETED PROJECTS PROJECT NO.<br />

ENGINEER / CONTRACTOR<br />

START<br />

CONSTRUCTION<br />

SUBSTANTIAL<br />

COMPLETION*<br />

FINAL<br />

COMPLETION<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

Pond Springs Road/Turtle Rock Road Signal 02WC405 WHM & Huggins / Austin Bridge & Road<br />

01/03/02 04/30/02 07/26/02 Project complete.<br />

McNeil Road<br />

Phase I (SH 45 to north of CR 172)<br />

03WC527 Gray-Jansing & Associates / RGM<br />

02/09/04 01/29/05 02/18/05 Project complete.<br />

Avery Ranch Blvd.<br />

(183A to Parmer Lane)<br />

N/A By Developer<br />

11/01/06 - 05/10/07 Project complete.<br />

McNeil Road<br />

Phase II (SH 45 to Howard Lane)<br />

RM 620 Interim Improvements Phase I<br />

05WC318 Gray-Jansing & Associates / Ranger<br />

01/23/06 02/02/07 07/25/07 Project complete.<br />

(Turn Lanes at Wyoming Springs, Oaklands & Deep<br />

Wood; Pedestrian Improvements)<br />

08WC605 Halff Associates / Aaron Concrete<br />

06/02/08 01/26/09 01/27/09 Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

Pond Springs Road<br />

(McNeil Rd to US 183)<br />

09WC710 URS / RGM Constructors<br />

06/24/09 09/23/10 02/18/11 Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

Wyoming Springs Drive<br />

(RM 620 to Brightwater Blvd)<br />

N/A Klotz Associates / RGM Constructors<br />

11/2009 11/2010 Winter 2010 Project complete - managed by the City of Round Rock.<br />

CR 174 (Hairy Man Rd) at Brushy Creek<br />

Bridge Rail Replacement<br />

11WC911 HNTB / Patin Construction<br />

05/09/11 06/20/11 06/30/11 Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

O'Connor Extension (RM 620 to just north of SH 45)<br />

Dan Williams (DWCO) cleaned erosion control devices. Vegetation establishment is not yet complete and the pavers in the<br />

(Includes O'Connor and Great Oaks Intersection<br />

11WC906 Klotz Associates / Dan Williams / HDR & Atkins<br />

04/06/11 04/30/<strong>12</strong> Pending O'Connor median north of RM 620 still need to be reset. PE Structural is analyzing the project documentation to determine<br />

Improvements at RM 620)<br />

regarding the bridge deck sealing at Lake Creek.<br />

King of Kings Crossing <strong>12</strong>IFB00025 HNTB / Smith Contracting<br />

06/25/<strong>12</strong> 08/24/<strong>12</strong> Pending<br />

The Ribbon Cutting Ceremony was held on 8/29/<strong>12</strong>. Smith Construction is watering for vegetative establishment, which is the only<br />

remaining punchlist item. Anticipate a request for Substantial Completion to issue Notice as of 8/24/<strong>12</strong>.<br />

<strong>ROAD</strong> <strong>BOND</strong> PROJECTS UNDER CONSTRUCTION ENGINEER CONTRACTOR OBSERVER BID AWARD<br />

NOTICE TO<br />

PROCEED<br />

CONSTRUCTION<br />

START FINISH<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

Ballenger’s crushing operation continues to produce embankment, bedding, and backfill material. In Pond 1A, the Contractor<br />

continues to tie steel and set forms for the walls and footing. Ballenger continues to place embankment for the O’Connor overpass<br />

O'Connor Overpass (at SH 45)<br />

CSJ: 0683-06-027<br />

Atkins Ballenger TxDOT Aug 2011 Oct 2011 Nov 2011 Nov 2013<br />

from Abutment 1 back to the north between MSE Walls 1 & 2 and east and west between Walls 3 & 7. Subcontractor Texas<br />

Highway Walls (THW) is currently setting MSE panels and placing backfill behind Wall 5. Ballenger poured the footing shafts for<br />

Abutment 16, columns for Abutment 1, and placed concrete for one column at Bent 11 of the westbound frontage road bridge. A<br />

Subcontractor is drilling for the footings of the eastbound frontage road bridge.<br />

Subcontractor APAC primed and paved Great Oaks after Ross Construction completed fine grading the final course of flex base.<br />

Anticipate opening this section of Great Oaks to traffic the end of next week, pending weather and striping. The Contractor also<br />

South Great Oaks Extension (to O'Connor) HD Engineering Ross Construction GEC 06/22/<strong>12</strong> Jul 20<strong>12</strong> Jul 20<strong>12</strong> Oct 20<strong>12</strong> completed the placement of the sidewalks. Ross Construction is fine grading topsoil in the median and along the east side of the<br />

project and has began general site clean-up. Other contractor Sun Tech trenched and installed conduit in the medians for the street<br />

lights and poured the street light foundations (working for HD Engineering).<br />

PROJECTS BIDDING / CONTRACTING ENGINEER<br />

ESTIMATED CONST. SCHEDULE<br />

START FINISH<br />

Halff Associates 09/23/<strong>12</strong> 10/17/<strong>12</strong> 10/30/<strong>12</strong> Dec 20<strong>12</strong> Jan 2013 Sep 2014<br />

DESIGN<br />

BID<br />

ESTIMATED CONST. SCHEDULE<br />

2006 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS IN DESIGN ENGINEER BID LETTING<br />

START FINISH ADVERTISEMENT<br />

START FINISH<br />

RM 620 at Railroad/Chisholm Trail - Schematic and<br />

Environmental<br />

Forest North Drainage Study<br />

Halff Associates<br />

K.Friese<br />

ADVERTISEMENT<br />

BEGINS<br />

-<br />

Spring 2013<br />

Sep 2011 Sep 20<strong>12</strong><br />

BID LETTING BID AWARD<br />

ANTICIPATED<br />

N.T.P.<br />

City of Round Rock<br />

N/A<br />

Bids will be received & opened on 10/17/<strong>12</strong>. A PreBid meeting was held on 10/3/<strong>12</strong> with 15 contractors in attendance. Project was<br />

approved by the Court for advertisement on 9/18/<strong>12</strong>. Received LOA from TxDOT on 9/11/<strong>12</strong>. Received additional Division<br />

comments on 8/20/<strong>12</strong> and returned responses & revisions on 8/25/<strong>12</strong>. The AT&T utility agreement was approved by the Court on<br />

7/31/<strong>12</strong>. Oncor relocations are complete, except for pole removal. Atmos relocations are complete. AT&T was anticipated to<br />

advertise plans for bidding at the end of last week with bids due on 10/19/<strong>12</strong> and the successful Contractor anticipated to go to work<br />

in late <strong>October</strong> in order to clear by the end of 20<strong>12</strong>. AT&T has a mandatory shutdown period between <strong>12</strong>/17/<strong>12</strong> - 1/4/13 where they<br />

cannot cut around any fiber. The final driveway permit for the joint driveway at Sta 363+95 was submitted to TxDOT on 7/2/<strong>12</strong>. A<br />

Participation Agreement for mitigation through the RHCP was approved on 5/8/<strong>12</strong> with a mitigation fee of $550,897. All ROW<br />

parcels are closed or have PUAs.<br />

ENVIRONMENTAL<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

CLEARANCE<br />

Categorical Exclusion<br />

Public Meeting Date:<br />

Fall 20<strong>12</strong><br />

N/A<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

An ILA with the City of Round Rock is being developed. The City is managing the planning effort for this<br />

project, and has received TxDOT comments on the schematic. FHWA has concurred with the level of<br />

environmental documentation (Categorical Exclusion), and Halff is proceeding with environmental field<br />

investigations. A public meeting is being scheduled for later this year.<br />

K. Friese addressed comments and submitted the final project report to Road and Bridge on 9/10/<strong>12</strong>.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 1 of 9


PRECINCT 1 - COMMISSIONER LISA BIRKMAN<br />

2006 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS IN DESIGN ENGINEER<br />

Pearson Ranch Underpass @ SH 45 / RM 620 Brown & Gay<br />

Pearson Ranch Road<br />

(South of Avery Ranch Blvd to SH 45 ROW)<br />

IH 35 Corridor Operational Analysis<br />

(SH 45 to RM 1431)<br />

TBD<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

DESIGN<br />

BID<br />

ESTIMATED CONST. SCHEDULE<br />

BID LETTING<br />

START FINISH ADVERTISEMENT<br />

START FINISH<br />

Sep 20<strong>12</strong><br />

TBD<br />

Mar 2013<br />

TBD<br />

Jul 2013 Aug 2013 Sep 2013 TBD<br />

Cunningham Allen Jul 20<strong>12</strong> Mar 2013 TBD<br />

N/A<br />

ENVIRONMENTAL<br />

CLEARANCE<br />

State Categorical<br />

Exclusion: Approval<br />

Anticipated Spring 20<strong>12</strong><br />

Due Diligence<br />

Investigations To Be<br />

Completed:<br />

TBD<br />

N/A<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

TxDOT concurred with the proposed intersection improvements on 4/23/<strong>12</strong>. Brown and Gay submitted a<br />

work authorization PS&E preparation, and HNTB submitted a work authorization for environmental<br />

documentation, both are being held pending execution of the Pearson Ranch Road ILA.<br />

The Work Authorization for Cunningham Allen for PS&E has been executed. Final negotiations are<br />

underway for the interlocal agreement. A kickoff meeting for PS&E will be scheduled once the interlocal<br />

agreement has been executed.<br />

Letters of Interest were received from engineering firms on 8/29/<strong>12</strong>, and interviews were held on 10/11/<strong>12</strong>.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 2 of 9


PRECINCT 2 - COMMISSIONER CYNTHIA LONG<br />

2000/2006 <strong>ROAD</strong> <strong>BOND</strong> COMPLETED PROJECTS<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

START<br />

CONSTRUCTION<br />

SUBSTANTIAL<br />

COMPLETION*<br />

FINAL<br />

COMPLETION<br />

CR 175 (FM 1431 to Regional Park) 02WC425 Baker-Aicklen / Garey Construction<br />

06/07/02 06/16/03 10/09/03<br />

River Bend Oaks Subdivision 02WC417 Haynie Consulting / Ellis-McGinnis<br />

05/30/02 - 02/28/03<br />

SH 29 at FM 1869 (Traffic Signal) N/A WHM /<br />

05/01/02 - 08/20/02<br />

CR 200 (CR 201 to Lackey Creek) 02WC440 KC Engineering / Joe Bland<br />

03/17/03 09/22/03 09/22/03<br />

CR 214 (SH 29 to Rolling Hills Rd.) 03WC518 Carter & Burgess / Capital Excavation<br />

02/23/04 02/21/05 05/11/05<br />

Ronald W. Reagan Blvd. South<br />

Phase I (FM 1431 to FM 2243)<br />

02WC433 TC&B / Capital Excavation<br />

10/14/02 01/01/05 6/8/2005<br />

CR 258 (US 183 to Sunset Ridge) 05WC323 Haynie Consulting / Austin Bridge & Road<br />

01/09/06 09/23/06 11/02/06<br />

San Gabriel Parkway Phase I (Halsey Dr. to CR 273) 05WC321 Malone Wheeler / J.C. Evans<br />

05/08/06 02/15/07 03/08/10<br />

Ronald W. Reagan Blvd. North<br />

Phase I (SH 29 to FM 3405)<br />

04WC214 PBS&J / Chasco<br />

04/22/05 03/08/07 06/14/07<br />

Lakeline Blvd.<br />

(Lyndhurst to Parmer Lane)<br />

05WC325 Carter & Burgess / J.C. Evans<br />

10/25/06 07/20/07 08/25/07<br />

Ronald W. Reagan Blvd. South<br />

Phase II (FM 2243 to SH 29)<br />

05WC324 TC&B / Ranger<br />

01/23/06 02/13/08 09/17/08<br />

US 183 Widening at CR 274 (Turn Lane Improvements) 07WC507 Malone Wheeler / Austin Bridge & Road<br />

07/09/07 02/18/08 04/28/08<br />

Kauffman Loop<br />

(S. of SH 29, East and West of Reagan)<br />

N/A TC&B and Randall Jones / Williamson County<br />

Jan 2008 Sep 2008 June 2009<br />

CR 175 Phase 2A Extension<br />

(Regional Park to Creekside Meadows)<br />

09WC707 Haynie Consulting / RGM Constructors<br />

04/20/09 01/28/10 02/03/10<br />

Signal at US 183 and FM 3405 09WC713 Brown & Gay / Republic ITS<br />

11/19/09 03/09/10 04/08/10<br />

Left Turn Lanes on US 183 at FM 3405 10WC805 Brown & Gay / Aaron Concrete<br />

03/11/10 05/25/10 <strong>12</strong>/17/10<br />

CR 214 Ph 2A<br />

(Rolling Hills Rd to San Gabriel Ranch Rd.)<br />

09WC723 Rogers Design Services / FTWoods<br />

06/25/10 01/07/11 01/31/11<br />

RM 1431 (183A to Cottonwood Creek Trail) N/A CP&Y / Hunter<br />

Feb 2010 Feb 2010 Aug 2011<br />

San Gabriel Parkway, Phase 2 (183A to CR 270) 11WC903 Malone/Wheeler / Ranger Excavating<br />

04/15/11 10/26/11 03/14/<strong>12</strong><br />

Brushy Creek Road (Parmer Ln. to Arrowhead Trail) N/A LAN / Chasco<br />

05/06/11 Mar 20<strong>12</strong> Apr 20<strong>12</strong><br />

10WC823<br />

Hero Way (US 183 to CR 269)<br />

(formerly Reveille Blvd)<br />

Pape Dawson DNT Construction GEC 11/09/10<br />

02/01/11 Limited<br />

01/23/<strong>12</strong> Full NTP<br />

CONSTRUCTION<br />

START FINISH<br />

02/07/11 Winter 20<strong>12</strong><br />

San Gabriel Parkway West (Halsey Dr to Bagdad Rd) Malone/Wheeler Cash City of Leander 06/16/11 Jun 2011 Jun 2011 Fall 20<strong>12</strong><br />

11WC915<br />

SH 29 TWLTL at Liberty Hill<br />

(4000' west of Cemetery to CR 200)<br />

(SH 29 Safety Improvements)<br />

CSJ: 0151-03-036<br />

PROJECT NO.<br />

Chiang Patel &<br />

Yerby, Inc.<br />

ENGINEER / CONTRACTOR<br />

<strong>ROAD</strong> <strong>BOND</strong> PROJECTS UNDER CONSTRUCTION ENGINEER CONTRACTOR OBSERVER BID AWARD<br />

NOTICE TO<br />

PROCEED<br />

Joe Bland HDR 09/20/11 <strong>12</strong>/02/11 <strong>12</strong>/17/11 10/25/<strong>12</strong><br />

Cottonwood Creek Trail (CR 185) Klotz Capital Excavation City of Cedar Park 05/24/<strong>12</strong> Jun 20<strong>12</strong> Jul 20<strong>12</strong> Sep 2013<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

Project complete. Contract close-out package is ready for transmittal to the County.<br />

Project complete. Close-out is resuming. Waiting on Ranger to submit lien waivers or final affidavit of all bills paid to issue Final<br />

Acceptance.<br />

Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

Project constructed by County forces.<br />

Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

Project complete. The Contract close-out package will be prepared for transmittal to the County.<br />

Project complete. Managed by TxDOT.<br />

Final Completion was issued with an effective date of 3/14/<strong>12</strong>. The final balancing Change Order has been executed and close-out<br />

documentation has been requested from Ranger.<br />

Project complete. Managed by Cedar Park.<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

DNT is completed the fine grading on topsoil and prepared for seeding at the east end along CR 269, which Subcontractor Matoka<br />

performed on Tuesday and Wednesday along CR 269. DNT is grading subgrade at the west end of Hero Way and hauling off<br />

excess materials and stockpiles. Subcontractor Progress Rail's subcontractor Spec will resume work when the remaining railroad<br />

signal materials are delivered. Subcontractor M&M installed the underdrain pipes at the railroad crossing. Subcontractor ATS bored<br />

and installed conduit to tie the intersection signals into the railroad crossing gates. A meeting with AT&T was held two weeks ago to<br />

discuss required adjustments necessary for the height of the overhead lines on the east side of the railroad tracks (do not currently<br />

meeting minimum required clearances) - no resolution from AT&T yet.<br />

Subcontractor Ramming paved everything at the west end at the tie-into CR 279 except the new portion of CR 279. Cash is<br />

rebuilding and processing subgrade for the right turn lane off of CR 279 onto San Gabriel West. Traffic continues to be detoured<br />

down Halsey and down San Gabriel West through the project to get back onto CR 279 during this phase of construction. Cash also<br />

installed the box culverts along the west side of CR 279. Subcontractor ATS is trenching and installing conduit across CR 279 at the<br />

intersection with San Gabriel West.<br />

Joe Bland is pouring concrete riprap adjacent to the westbound lanes between Sta 351+00 and 318+75 and between Driveways 14<br />

and 15. The Contractor is fine grading the ditches near Driveway 23 and Deep Lake Drive, working back to the west. Joe Bland<br />

continues to place topsoil along the westbound lanes and installed additional culvert pipes for the new driveways added on the last<br />

CO.<br />

Capital Excavation continues to excavate to subgrade for the southbound lanes of Cottonwood Creek Trail and eastbound lanes of<br />

New Hope and hauling the excess material offsite. The Contractor completed excavating, setting, and backfilling the double barrel<br />

10’x 6’ concrete box culverts at Cottonwood Creek. Subcontractor G Carter poured the last signal foundation at the New Hope and<br />

Cottonwood Creek Trail intersection and began installing conduit.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 3 of 9


PRECINCT 2 - COMMISSIONER CYNTHIA LONG<br />

<strong>ROAD</strong> <strong>BOND</strong> PROJECTS UNDER CONSTRUCTION<br />

(CONT'D)<br />

<strong>12</strong>IFB00005<br />

CR 260/266 Intersection Improvements at SH 29<br />

(SH 29 Safety Improvements)<br />

2000 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS IN DESIGN<br />

CR 179 (Ronald Reagan Blvd. to CR 175)<br />

2006 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS IN DESIGN<br />

Lakeline Blvd.<br />

(Crystal Falls Pkwy to Old 2243)<br />

Seward Junction Improvements Study<br />

(CR 213, CR 259, CR 260, CR 263, CR 266)<br />

US 183 at RM 1869<br />

CR 258 (Sunset Ridge to Reagan Blvd)<br />

ENGINEER CONTRACTOR OBSERVER BID AWARD<br />

Chiang Patel &<br />

Yerby, Inc.<br />

ENGINEER<br />

Karen Friese &<br />

Associates<br />

ENGINEER<br />

Baker-Aicklen<br />

Loomis Partners<br />

Gonzalez-De La<br />

Garza &<br />

Associates<br />

CEC<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

CONSTRUCTION<br />

START FINISH<br />

Patin Construction GEC 07/31/<strong>12</strong> 10/05/<strong>12</strong> 10/15/<strong>12</strong> 03/14/13<br />

DESIGN<br />

BID<br />

ESTIMATED CONST. SCHEDULE<br />

BID LETTING<br />

START FINISH ADVERTISEMENT<br />

START FINISH<br />

06/01/04<br />

DESIGN<br />

BID<br />

ESTIMATED CONST. SCHEDULE ENVIRONMENTAL<br />

BID LETTING<br />

START FINISH ADVERTISEMENT<br />

START FINISH<br />

CLEARANCE<br />

Aug 2011<br />

Oct 2011<br />

08/29/05 Oct 20<strong>12</strong><br />

Nov 20<strong>12</strong> Dec 20<strong>12</strong> Oct 2013<br />

Jan 20<strong>12</strong> Sep 20<strong>12</strong> Oct 20<strong>12</strong><br />

May 20<strong>12</strong><br />

Sep 20<strong>12</strong><br />

Nov 20<strong>12</strong><br />

Nov 20<strong>12</strong><br />

Lakeline Blvd. at US 183 Kimley Horn Nov 2011 Jan 2013 Jan 2013 Feb 2013<br />

Dec 20<strong>12</strong><br />

NOTICE TO<br />

PROCEED<br />

N/A<br />

N/A<br />

TBD<br />

Dec 20<strong>12</strong><br />

Dec 2013<br />

Mar 2013 Apr 2013<br />

Notice to Proceed was issued on 10/5/<strong>12</strong> and the US 183 driveways are scheduled to be completed by 11/19/<strong>12</strong>. A Groundbreaking<br />

Ceremony is tentatively scheduled for 10/18/<strong>12</strong>. The PreConstruction Meeting was held on 9/20/<strong>12</strong>. The Court awarded the<br />

construction contract to Patin Construction in the amount of $568,980.50 for the base plus alternate bid on 7/31/<strong>12</strong>.<br />

ENVIRONMENTAL<br />

CLEARANCE<br />

Managed by<br />

City of Leander<br />

Due Diligence<br />

Investigations To Be<br />

Completed:<br />

Fall 20<strong>12</strong><br />

Due Diligence<br />

Investigations To Be<br />

Completed:<br />

TBD<br />

N/A<br />

N/A<br />

Due Diligence<br />

Investigations To Be<br />

Completed:<br />

Fall 20<strong>12</strong><br />

PROGRESS - ACTION ITEMS - REMARKS<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

K.Friese submitted 100% PS&E to the City of Leander on 7/24/<strong>12</strong> and will make some minor revision prior<br />

to bidding. The City anticipates bidding the project this fall. Project is proceeding with a modified urban 4lane<br />

section (ribbon curb with vegetative filter strips).<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

A meeting with the City of Leander and the Gilpens was held on 10/3/<strong>12</strong>. A meeting with KB Home and<br />

their engineer was held on 9/20/<strong>12</strong>. A developer agreement with KB Home is being drafted. Comments<br />

were returned on Draft Karst Report, Draft Hazardous Materials Report, and Draft Threatened/Endangered<br />

Species Report on 9/4/<strong>12</strong>. SWCA submitted the Cultural Resources Report to THC on 8/23/<strong>12</strong>. Baker-<br />

Aicklen submitted field notes and sketches for proposed easements on 8/23/<strong>12</strong>, and redesign to remove<br />

retaining walls will begin once the easements have been acquired from the Gilpens. One ROW parcel<br />

(Spring/Summer tract) remains to be closed.<br />

An Open House was held on 10/11/<strong>12</strong>. Loomis submitted draft exhibits for review on 10/5/<strong>12</strong>. A project<br />

update meeting was held 7/19/<strong>12</strong>. Loomis and 3 Point Partners completed meetings with stakeholders in<br />

advance of the Open House to get public input on the alternatives. Loomis has developed and evaluated<br />

alternative alignments based on technical constraints and public input, and has determined a<br />

recommended alignment.<br />

An informal meeting with TxDOT to discuss design criteria was held on 7/27/<strong>12</strong>. Final comments on the<br />

revised schematic and preliminary PS&E were sent on 8/30/<strong>12</strong>. The preliminary schematic and traffic<br />

warrant study were received on <strong>12</strong>/30/11.<br />

Kimley-Horn submitted 60% plans on 10/3/<strong>12</strong>, and they are currently under review. A meeting with TxDOT<br />

to discuss future plans for US 183 was held on 8/10/<strong>12</strong>, and a weaving analysis was submitted on 9/4/<strong>12</strong>.<br />

TxDOT provided comments on the weaving analysis on 9/6/<strong>12</strong>. Kimley-Horn submitted the final report on<br />

1/18/<strong>12</strong>, and it was transmitted to TxDOT and the City of Austin on 1/18/<strong>12</strong>.<br />

Comments on 30% PS&E were returned on 9/14/<strong>12</strong>, and a comment review meeting was held on 9/14/<strong>12</strong>.<br />

CEC is moving forward with 60% PS&E. Blanton received the archeological permit from THC on 9/11/<strong>12</strong>.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 4 of 9


PRECINCT 3 - COMMISSIONER VALERIE COVEY<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

2000/2006 <strong>ROAD</strong> <strong>BOND</strong> COMPLETED PROJECTS PROJECT NO. ENGINEER / CONTRACTOR<br />

START<br />

CONSTRUCTION<br />

SUBSTANTIAL<br />

COMPLETION*<br />

FINAL<br />

COMPLETION<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

Cedar Hollow at SH 29 Signal N/A Haynie Consulting /<br />

- - -<br />

Project complete.<br />

Georgetown Inner Loop - Project 2<br />

(Middle Fork to SH 29) D.B. Wood<br />

N/A PBS&J / Austin Bridge & Road<br />

01/23/02 - 08/04/03 Project complete.<br />

Georgetown Inner Loop - (CO to Project 2)<br />

(Middle Fork to SH 29) D.B. Wood<br />

N/A Steger Bizzell / Austin Bridge & Road<br />

- - 08/04/03 Project complete.<br />

Georgetown Inner Loop - Project 4<br />

(FM 2243 to IH-35)<br />

N/A HDR / N/A<br />

- - -<br />

Project complete.<br />

CR 152 Bridge 04WC207 Steger & Bizzell / Chasco<br />

03/08/04 09/13/04 09/18/04 Project complete.<br />

Georgetown Inner Loop - Project 1<br />

(FM 2338 to D.B. Woods) Cedar Breaks<br />

PBS&J / Austin Bridge & Road<br />

05/28/02 06/24/04 06/24/04 Project complete.<br />

Georgetown Inner Loop East<br />

(SH 29 to FM 971)<br />

Steger Bizzell / Chasco<br />

04/14/03 06/13/04 01/04/05 Project complete.<br />

Georgetown Inner Loop East Extension<br />

(CR 151 to I-35 BUS)<br />

05WC311 Steger Bizzell / Joe Bland<br />

06/27/05 10/20/05 <strong>12</strong>/21/05 Project complete.<br />

Ronald W. Reagan Blvd. North<br />

Phase II (FM 3405 to FM 2338)<br />

07WC502 PBS&J / J.C. Evans<br />

03/<strong>12</strong>/07 05/23/08 05/04/09 Project complete. Final Project Close-out package to the County is being prepared.<br />

<strong>12</strong>" Water Main Relocation for SH 29 Widening 08WC604 Steger Bizzell / Herschap<br />

03/05/08 06/11/08 10/01/08 Project complete. Final Project Close-out package to the County is being prepared.<br />

SH 29/CR 104, Phase 1<br />

(At New High School and CR 104 Intersection)<br />

08WC602 Steger Bizzell / Cash Construction<br />

03/01/08 07/28/08 09/23/09 Project complete. Final Project Close-out package to the County is being prepared.<br />

SE Inner Loop @ FM 1460<br />

(Intersection Improvements)<br />

09WC708 LAN / JO'B Site Construction<br />

06/01/09 11/06/09 01/28/10<br />

Processing balancing Change Order with Bonding Company for closure of construction contract. TxDOT has accepted the ditches<br />

along FM 1460 in the current conditions.<br />

CR 111 / Westinghouse Rd.<br />

(From Hewlett Loop to FM 1460)<br />

08WC608 Huggins Seiler & Associates / J.C. Evans<br />

06/16/08 06/16/10 Pending<br />

Received documentation from the Bonding Company that all claims have been settled and the pay application for release of<br />

retainage has been paid. The Certificate of Acceptance is being prepared.<br />

CR 104, Phase 2<br />

Chasco has completed the punchlist items. Coordinating with TxDOT on project acceptance due to TxDOT off-system bridge<br />

(From SH 130 to South of New School property)<br />

10WC8<strong>12</strong> Steger Bizzell / Chasco<br />

09/02/10 05/26/11 Pending funding in project. The Materials Certification has been received back to the engineer sealed in order to obtain TxDOT Final<br />

CSJ: 0914-05-141<br />

Completion.<br />

SH 29 Intersection Improvements at Park Place & Jack<br />

Nicklaus<br />

11WC916 CP&Y / Wolff Construction<br />

01/14/<strong>12</strong> 05/23/<strong>12</strong> 06/19/<strong>12</strong><br />

Close-out documentation has been received from Wolff Construction and the Certificate of Acceptance has been sent out for<br />

signature.<br />

Williams Drive (RM 2338)<br />

A letting granting Substantial Completion is being prepared. A Ribbon Cutting Ceremony was held on <strong>12</strong>/16/10. Subcontractor RSI<br />

(D.B Wood to FM 3405)<br />

09WC706 KBR / JC Evans / Atkins<br />

03/16/<strong>12</strong> Spring 2011 Pending completed the punchlist items clean up behind the MBGF. Awaiting schedule for ADA corrections from KBR and the installation of<br />

CSJ: 2211-01-016<br />

additional signs on FM 3405 by County forces.<br />

<strong>ROAD</strong> <strong>BOND</strong> PROJECTS UNDER CONSTRUCTION ENGINEER CONTRACTOR OBSERVER BID AWARD<br />

NOTICE TO<br />

PROCEED<br />

CONSTRUCTION<br />

START FINISH<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

11WC902<br />

Ronald W. Reagan Blvd. North Phase III<br />

(FM 2338 - SH 195)<br />

Stanley (Design)<br />

Cobb Fendley<br />

(Construction)<br />

Ranger<br />

(for American<br />

States Insurance<br />

Company)<br />

Huitt-Zollars<br />

GEC / CP&Y<br />

01/11/11<br />

03/30/11 Limited<br />

05/23/11 Full NTP<br />

04/04/11 02/20/13<br />

Subcontractor Ramming reapplied prime to the finished flex base and paved 3” Type B asphalt from north of CR 245 to Berry Creek.<br />

Ranger Excavating continues to spread topsoil along the roadway in various locations and began removing the haul road across<br />

Berry Creek, including final clean up and grading in this area. Subcontractor Greater Austin applied linseed oil concrete surface<br />

treatment to the surface of the Berry Creek Bridge. Material supplier Organics By Gosh continued processing mulch onsite for use<br />

on the project.<br />

James Construction continues to set deck panels and tie rebar for the bridge slab on southbound mainlane bridge east of Florence<br />

on Spans 10, 11, and <strong>12</strong>. Subcontractor Indus is tying the reinforcing steel for the bridge slabs. James poured the bridge slab on<br />

SH 195 Project 1<br />

(Bell County Line to 3.4 mi south of SH 138)<br />

ROW Acquisition and Utility Coordination<br />

ARCADIS<br />

James<br />

Construction<br />

TxDOT 01/27/11 Mar 2011 Mar 2011 Mar 2014<br />

Spans 7,8, and 9. The Contractor placed forms and poured a concrete headwall on a box culvert that crosses the mainlanes east of<br />

the bridge, as well as forming and pouring concrete wingwalls and aprons. Subcontractor Ranger is placing topsoil along the<br />

mainlanes east of Florence and continues to crush rock with the crusher to make flex base and embankment materials for use on<br />

the project. Ranger is finishing the flex base on the new southbound mainlanes east of Florence, which need to be paved so that<br />

existing traffic can be switched from existing SH 195 to the new roadway to provide room for the completion of the embankment on<br />

the mainlane bridges header banks.<br />

Ranger completed clearing the right-of-way from CR 239 to one half mile north of CR 234 and continued excavating and embanking<br />

material north of SH 195. Subcontractor BMP installed erosion control devices behind the right of way clearing operations.<br />

<strong>12</strong>IFB00010<br />

Ronald W. Reagan Blvd. North<br />

Phase IV (SH 195 to CR 237)<br />

AECOM (TCB)<br />

Ranger<br />

Excavating<br />

CP&Y 03/29/<strong>12</strong> 05/15/<strong>12</strong> 05/25/<strong>12</strong> 11/14/13<br />

Subcontractor JKB continued backfilling the tunnel pipe and is now 21 feet up (70% complete). Subcontractor Greater Austin placed<br />

forms and poured the bottom slab of Culvert 2 near Hillstone Quarry. Subcontractor M & D Drilling drilled drill shaft foundations at<br />

Abutments 1 & 4 and Bents 2 & 3 at the Smalley Branch Bridge. PEC and Verizon relocations on Phase 1 are complete, and they<br />

have completed the design of their remaining relocations on Parcels 7-10. PEC is scheduled to be complete at the end of December<br />

20<strong>12</strong>, with Verizon completing shortly after PEC. Oncor completed their relocations on 5/9/<strong>12</strong> and will remove the poles after<br />

Verizon has relocated.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 5 of 9


PRECINCT 3 - COMMISSIONER VALERIE COVEY<br />

ADVERTISEMENT<br />

PROJECTS BIDDING / CONTRACTING ENGINEER<br />

BID LETTING BID AWARD<br />

BEGINS<br />

SH 195 Project 3<br />

(South of Ronald Reagan to IH 35)<br />

ROW Acquisition and Utility Coordination<br />

CR 245<br />

(RM 2338 to 0.223 miles east of RM 2338)<br />

ARCADIS<br />

2006 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS IN DESIGN ENGINEER<br />

CR 110/Arterial A<br />

(US 79 to Inner Loop)<br />

(Preliminary Alternatives and Constraints Mapping)<br />

TxDOT<br />

Advertising<br />

Schedule<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

ESTIMATED CONST. SCHEDULE<br />

START FINISH<br />

09/07/<strong>12</strong> Sep 20<strong>12</strong> Late 20<strong>12</strong> TBD TBD<br />

DESIGN<br />

BID<br />

ESTIMATED CONST. SCHEDULE<br />

BID LETTING<br />

START FINISH ADVERTISEMENT<br />

START FINISH<br />

Steger Bizzell Jul 2010 Aug 20<strong>12</strong><br />

Southwest Bypass (RM 2243 to IH 35) HDR<br />

TBD<br />

TBD TBD<br />

CR 111<br />

(FM 1460 to SH 130)<br />

(Constraints Mapping and Alternatives Analysis)<br />

SH 195 Project 2<br />

(3.4 mi south of SH 138 to south of Ronald Reagan)<br />

ROW Acquisition and Utility Coordination<br />

2006 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS<br />

Managed by the Georgetown<br />

FM 1460 North<br />

(North of University/Chandler to Quail Valley Drive)<br />

Kennedy Feb 20<strong>12</strong> Sep 20<strong>12</strong><br />

Steger Bizzell<br />

ARCADIS<br />

ENGINEER<br />

Brown & Gay<br />

Mar 20<strong>12</strong><br />

Sep 20<strong>12</strong><br />

TxDOT Managing Design of SH 195<br />

Letting is Scheduled for June 2013<br />

ANTICIPATED<br />

N.T.P.<br />

DESIGN BID<br />

ESTIMATED CONST. SCHEDULE<br />

BID LETTING<br />

START FINISH ADVERTISEMENT<br />

START FINISH<br />

TBD<br />

TBD<br />

TBD<br />

Winter 20<strong>12</strong> Dec 2013 TBD, Anticipated in 2015<br />

TBD TBD<br />

Due Diligence<br />

Investigations<br />

Completed:<br />

Fall 2011<br />

TBD<br />

Due Diligence<br />

Investigations<br />

Completion Date: TBD<br />

Due Diligence<br />

Investigations<br />

Completion Date: TBD<br />

EA approved (FONSI<br />

re-validated) <strong>12</strong>/13/11<br />

ENVIRONMENTAL<br />

CLEARANCE<br />

Due Diligence<br />

Investigations<br />

Completion Date: TBD<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

Seven (7) bids were received on 9/7/<strong>12</strong> with SEMA Construction being the low bidder at $18,778,887.62, 3.1% over the Engineer’s<br />

estimate. All ROW parcels for Project 3 have been acquired or have PUA. PEC, CTSUD, and Verizon relocations are underway.<br />

LCRA and Georgetown Electric relocations are complete. Brazos Valley River Authority (BRA) has received TxDOT permit and is<br />

working on relocation schedule. GEC is coordinating with TxDOT and Sheets & Crossfield regarding status of fence relocations.<br />

ENVIRONMENTAL<br />

CLEARANCE<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

The Court tabled a request to authorize advertisement for construction bids, pending discussions on<br />

funding. Verizon and PEC relocations are complete. ROW and temporary construction easement<br />

acquisition is complete.<br />

The City of Georgetown has HDR under contract to begin the planning process. An ILA between the City<br />

and County was approved by Georgetown's City Council on 1/25/11, and by the Court on 2/15/11.<br />

A project update meeting was held on 10/4/<strong>12</strong>. Two open houses for CR 110 are tentatively planned for<br />

the week of 11/<strong>12</strong>/<strong>12</strong>. Coordination meetings with elected officials and stakeholders are underway. A<br />

coordination meeting with staff from the Cities of Georgetown, Round Rock, and Hutto was held on 8/2/<strong>12</strong>.<br />

Constraints maps have been completed and preliminary alignments are being finalized. A stakeholder<br />

meeting with Southwestern University was held on 6/19/<strong>12</strong>. A follow-up coordination meeting with all three<br />

cities was held on 4/11/<strong>12</strong>, and all three cities concurred on the typical section and study area. A public<br />

meeting is tentatively planned for Fall 20<strong>12</strong>. Initial coordination meetings were held with the City of<br />

Georgetown on 3/22/<strong>12</strong>, the City of Round Rock on 3/23/<strong>12</strong>, and the City of Hutto on 4/3/<strong>12</strong>.<br />

A project update meeting was held on 10/4/<strong>12</strong>. Coordination meetings with major landowners are<br />

underway. Coordination meetings with the City of Georgetown were held on 8/17/<strong>12</strong> and 8/28/<strong>12</strong>. Steger<br />

Bizzell submitted a constraints and preliminary alignments exhibit on 7/5/<strong>12</strong>, in preparation for a public<br />

meeting in Fall 20<strong>12</strong>. A coordination meeting was held with the City of Georgetown and TxDOT on<br />

4/27/<strong>12</strong>, to discuss the study area and typical section.<br />

FHWA determined on <strong>12</strong>/13/11 that the previous FONSI is still valid, and entire project is now clear for<br />

ROW acquisition & utility relocation. A ROW update meeting was held on 9/6/<strong>12</strong>. Offers are underway for<br />

Project 2, and 17 of 27 parcels have been acquired or have PUA. Utility Agreement forms and plans were<br />

distributed to CenturyLink (formerly Embarq), Oncor Electric, PEC, CTSUD, LCRA, and SBA. CTSUD ILA<br />

has been executed. An amendment to the ILA was approved by the Court on 5/17/11. CTSUD plans are<br />

complete, and agreement has been executed. PEC submitted revised plans, and they are currently under<br />

review. Oncor submitted an updated Utility Agreement on 6/25/<strong>12</strong> and it was sent to TxDOT for review.<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

An Interlocal Agreement was approved on 10/9/<strong>12</strong> with the City of Georgetown for the development and<br />

construction of FM1460 from University Blvd to Quail Valley Dr. The County will provide $4.5M within 60<br />

days of execution of the revised funding agreement between TxDOT and the City and will provide notice to<br />

CAMPO & TxDOT that the 2014 CAMPO STP-MM allocation for CSJ 2211-02-026 in the amount of<br />

$3,367,580 with a non-Federal share provided by TxDOT of $841,895 to the FM 1460 project will be<br />

administered by the City. The City of Georgetown agreed to amend the current AFAs to complete the FM<br />

1460 improvements described above with the City completing PS&E by December 31, 2014 and TxDOT<br />

bidding, constructing & inspecting the project. The City will provide all right-of-way & easements,<br />

environmental mitigation, and utility conflict resolution for the FM 1460 project to enable a 2015 bidding<br />

schedule. The City will provide all construction funding not secured by agreement from other sources for<br />

the FM 1460 project to enable a 2015 bidding schedule, and will work with the City of Round Rock and<br />

other parties for additional funding through interlocal agreements, developer participation, and other<br />

financing methods.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 6 of 9


PRECINCT 4 - COMMISSIONER RON MORRISON<br />

2000/2006 <strong>ROAD</strong> <strong>BOND</strong> COMPLETED PROJECTS<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

START<br />

CONSTRUCTION<br />

SUBSTANTIAL<br />

COMPLETION*<br />

FINAL<br />

COMPLETION<br />

Bridge Replacements<br />

Package I (CR 406, CR 390 & CR 427)<br />

02WC426 HDR / Ellis-McGinnis<br />

06/25/02 11/22/02 <strong>12</strong>/05/02<br />

CR 4<strong>12</strong> (FM 619 to CR 421) N/A Inland Civil / RGM<br />

10/31/02 - 08/27/03<br />

CR 368/369 (CR 101 to CR 366) 02WC418 Haynie Consulting / Camp Excavation and Contracting 06/03/02 - Apr 2003<br />

CR 300/CR 301 (FM 972 to FM 971) 03WC517 Pate Engineers / Capital Excavation<br />

08/04/03 01/10/04 10/05/04<br />

Bridge Replacements<br />

Package IIA (CR 424)<br />

03WC520 HDR / FT Woods<br />

11/03/03 - 01/06/04<br />

Chandler Road (West of FM 1460 to CR110) 03WC516 Denmon Engineering / J.C. Evans<br />

08/04/03 03/16/05 03/14/06<br />

CR 137 (County Line to FM 1660) 05WC304 Pate Engineers / J.C. Evans<br />

01/24/05 10/20/05 04/<strong>12</strong>/06<br />

CR 1<strong>12</strong> - Phase I (Chandler Rd to FM 1460) 05WC310 Baker-Aicklen / J.C. Evans<br />

03/05/05 08/31/05 09/07/06<br />

Limmer Loop Phase 1A (CR 136, CR 164 & CR 119) 04WC216 Pate Engineers / Chasco<br />

11/15/04 07/07/06 02/08/07<br />

US 79 Section 3A: CR 402 to Mustang Creek N/A Carter & Burgess / Joe Bland<br />

Jan 2005 - Nov 2006<br />

Chandler Road - Phase II (CR110 to FM 1660) 06WC407A Reynolds Smith & Hills / Rodman<br />

09/18/06 <strong>12</strong>/10/07 05/23/08<br />

Limmer Loop Phase 1B (Haybarn Lane to CR 119) 06WC420 Pate Engineers / Cash<br />

03/<strong>12</strong>/07 03/05/08 04/07/08<br />

US 79 Section 1: McNutt Creek to FM 685 N/A Jacobs Carter Burgess<br />

- Summer 2008<br />

Limmer Loop Phase 1C (CR 110 to SH 130) 08WC603 Pate Engineers / JC Evans<br />

04/30/08 10/02/08 05/11/09<br />

Gattis School Rd (Red Bud Ln. to east of Winterfield Dr.) N/A Halff Associates / Cash<br />

02/09/09 June 2010 Fall 2010<br />

Chandler Road - Phase 3B (CR 368/369 to SH 95) 09WC717 Jacobs Carter Burgess / Chasco<br />

10/01/09 10/14/10 07/23/11<br />

FM 1660 @ CR <strong>12</strong>8 (Landfill Road)<br />

CSJ: 1566-01-0<strong>12</strong><br />

11WC913 HNTB / Aaron Concrete<br />

07/25/11 09/14/11 Pending<br />

FM 1460 (Old Settler's Blvd. to North of University) N/A Huggins Seiler & Associates / Hunter Industries<br />

Oct 2009 - Oct 2011<br />

Second Street Drainage Improvements<br />

(Various Locations in Taylor)<br />

09WC7<strong>12</strong> Halff Associates / Austin Engineering<br />

03/26/10 <strong>12</strong>/23/11 02/21/<strong>12</strong><br />

<strong>ROAD</strong> <strong>BOND</strong> PROJECTS UNDER CONSTRUCTION ENGINEER CONTRACTOR OBSERVER BID AWARD<br />

NOTICE TO<br />

PROCEED<br />

CONSTRUCTION<br />

START FINISH<br />

10WC821<br />

Second Street Roadway Improvements<br />

(US 79 west of Taylor to SH 95)<br />

10WC822<br />

Chandler Road - Phase 3A<br />

(FM 1660 to CR 368/369)<br />

Kenney Fort Boulevard (formerly Arterial A Ph 1)<br />

(Joe DiMaggio Blvd. to Forest Creek Dr.)<br />

CR 351 @ Donahoe Creek<br />

CSJ# 0914-05-172<br />

PROJECT NO. ENGINEER / CONTRACTOR<br />

Halff Associates FTWoods<br />

SD Kallman<br />

(Design)<br />

HNTB<br />

(Construction)<br />

SD Kallman /<br />

Dannenbaum /<br />

HDR<br />

Brown & Gay<br />

GEC &<br />

City of Taylor<br />

Chasco Wilco 10/26/10<br />

Chasco<br />

James<br />

Construction<br />

City of Round<br />

Rock<br />

11/16/10 02/17/11 2/17/11 <strong>12</strong>/15/<strong>12</strong><br />

09/08/11 Limited<br />

11/07/11 Full NTP<br />

11/17/11 11/16/<strong>12</strong><br />

06/23/11 Sep 2011 Sep 2011 Sep 2013<br />

TxDOT Jun 20<strong>12</strong> Aug 20<strong>12</strong> Aug 20<strong>12</strong> Dec 20<strong>12</strong><br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

Project complete.<br />

TxDOT project complete.<br />

Project complete. Contract close-out package was sent to the County on 3/30/10.<br />

Project complete. Final Project Close-out package to the County is under review.<br />

TxDOT Project complete.<br />

Project complete. Final Project Close-out package to the County is being prepared.<br />

Project complete. Managed by Travis County.<br />

Chasco has submitted the close-out documentation and the As-built plans are under review for acceptance.<br />

Aaron has submitted the close-out documentation. Awaiting TxDOT concurrence. The Materials Certification has been sent back to<br />

the Engineer to seal.<br />

TxDOT Project complete.<br />

Austin Engineering is preparing close-out documentation.<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

FTWoods continues to form and pour inlet tops, brick paver footings, curb and gutter and driveways and sidewalk, and install brick<br />

pavers between Fowzer Street and Main Street. The Contractor excavated out the old eastbound lanes to Debus Street, blue topped<br />

subgrade to Victoria Street, placed first course flex base from Fowzer Street to Howard Street, and began placing second course flex<br />

base from Main Street to Davis Street. The Contractor is completed installing curb inlets and laterals on the project and began<br />

raking rocks and spreading topsoil throughout the north side of the roadway.<br />

Chasco completed placing third course flex base on the project and has begun blue topping and finishing flex base between the<br />

Atmos gas crossing and the east end. Topsoil placement has begun between Sta 110+00 and 170+00 on the future lanes and<br />

between Sta 177+00 and 203000 along the eastbound front slope. Chasco formed and poured the SETs for Driveways K and O, and<br />

the upstream headwall & wingwall for Culvert D.<br />

Chasco continues forming sidewalk, traffic rail and handrail on the Brushy Creek Bridge and completed placing railing on the UPRR<br />

Bridge. Subcontractor Trac Works completed placing railroad ballast and setting rail and ties on the UPRR Bridge. Subcontractor<br />

ATS completed installing junction boxes on the Brushy Creek Bridge for illumination poles. Chasco is placing flex base for various<br />

driveways along both sides of the proposed roadway.<br />

James Construction continues to form and pour rip rap around the bridge abutments. The Contractor completed roadway excavation<br />

on both sides of the proposed bridge. Subcontractor Rice Environmental continued rock gabion basket installation downstream of<br />

the bridge.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 7 of 9


PRECINCT 4 - COMMISSIONER RON MORRISON<br />

<strong>ROAD</strong> <strong>BOND</strong> PROJECTS UNDER CONSTRUCTION<br />

(CONT'D)<br />

CR 138<br />

(SH 130 to CR 137)<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> <strong>ROAD</strong> <strong>BOND</strong> <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

NOTICE TO<br />

PROCEED<br />

CONSTRUCTION<br />

START FINISH<br />

Baker-Aicklen Aaron Concrete GEC 07/24/<strong>12</strong> 09/21/<strong>12</strong> 10/01/<strong>12</strong> 06/28/13<br />

DESIGN<br />

BID<br />

ESTIMATED CONST. SCHEDULE<br />

2006 <strong>ROAD</strong> <strong>BOND</strong> PROJECTS IN DESIGN ENGINEER<br />

BID LETTING<br />

START FINISH ADVERTISEMENT<br />

START FINISH<br />

CR 170<br />

(South of SH 45 to North of Pflugerville Parkway)<br />

CR 119<br />

(Limmer Loop to Chandler Rd)<br />

CR 108<br />

(US 79 to Limmer Loop)<br />

Chandler Road Expansion<br />

(FM 1460 to SH 130)<br />

ENGINEER CONTRACTOR<br />

Baker-Aicklen<br />

Bury & Partners Jan 2011<br />

Karen Friese &<br />

Associates<br />

Feb 2010<br />

June 2011<br />

OBSERVER<br />

Jul 20<strong>12</strong><br />

TBD<br />

Aug 20<strong>12</strong><br />

BID AWARD<br />

Nov 20<strong>12</strong> Dec 20<strong>12</strong> Jan 2013<br />

Seiler Lankes May 20<strong>12</strong> Apr 2013 TBD<br />

TBD<br />

TBD<br />

Jan 2014<br />

Aaron Concrete set the perimeter barricades and started installing the erosion control devices. The Contractor is laying out the<br />

project and trimming trees along the ROW.<br />

ENVIRONMENTAL<br />

CLEARANCE<br />

Due Diligence<br />

Investigations<br />

Completed<br />

May 2011<br />

Due Diligence<br />

Investigations<br />

Completion Date: Winter<br />

2011/20<strong>12</strong><br />

Due Diligence<br />

Investigations<br />

Completion Date: March<br />

20<strong>12</strong><br />

Due Diligence<br />

Investigations<br />

Completion Date: TBD<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

Atmos relocations are complete. A ROW update meeting was held on 9/6/<strong>12</strong>. ROW acquisition is<br />

underway and fifteen parcels have been acquired. Manville and Suddenlink's utility agreements were<br />

approved by the Court on 7/17/<strong>12</strong>. Baker-Aicklen submitted 100% PS&E on 5/15/<strong>12</strong>. A project update<br />

meeting with Round Rock was held on 2/29/<strong>12</strong>. Round Rock will not be taking over maintenance of the<br />

section of roadway not within their City Limits. Cultural resources clearance received from the THC on<br />

5/24/11.<br />

A 60% comment resolution meeting was held on 9/27/<strong>12</strong>. Comments on 60% PS&E were returned on<br />

9/14/<strong>12</strong>. A project update meeting was held on 9/13/<strong>12</strong>. A re-kickoff meeting was held on 5/1/<strong>12</strong>, and a<br />

meeting with the developer for Cottonwood Creek Section 3 was held on 5/10/<strong>12</strong>. 30% PS&E comments<br />

were returned on 6/25/<strong>12</strong>.<br />

Submittal of 100% PS&E is anticipated on 10/26/<strong>12</strong>. ROW acquisition is complete with all 5 parcels<br />

donated by the adjacent property owners. Comments on the 90% PS&E were returned on 6/28/<strong>12</strong>.<br />

Blanton has completed due diligence investigations. Seminole relocations are complete. Oncor<br />

relocations are complete. TWC and CenturyLink's relocations are anticipated to begin 10/22/<strong>12</strong>. Jonah<br />

WSC has completed their relocation design and has the utility agreement for execution. Atmos is<br />

designing new facilities to be installed on CR 108 and is coordinating their design approval with Cobb<br />

Fendley to avoid conflicts with the proposed project improvements.<br />

The 30% PS&E Submittal was received on 9/18/<strong>12</strong> and is currently under review. Comments were<br />

returned on the median cut locations exhibit and Design Summary Form on 7/5/<strong>12</strong>. A meeting is being<br />

scheduled with Avery to finalize / approve the location of the two median cuts specified in the original ROW<br />

acquisition contract.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 8 of 9


IH-35 @ SH 29 Turnarounds<br />

CSJ: 0015-08-<strong>12</strong>2<br />

COMPLETED PROJECTS PROJECT NO.<br />

US 79 Section 5b (FM 1063 to Milam County Line)<br />

CSJ: 0204-04-042<br />

US 79, Section 5a (E. Taylor to FM 1063)<br />

CSJ: 0204-04-040<br />

US 183 (San Gabriel River to SH 29)<br />

CSJ: 0151-04-063<br />

09WC722A<br />

RM 2338 (FM 3405 to Reagan Blvd.)<br />

CSJ: 2211-01-023<br />

10WC817<br />

US 79, Section 3 (E. Hutto to CR 402)<br />

CSJ: 0204-02-027<br />

PROJECTS IN DESIGN ENGINEER<br />

FM 1660 (CR 134 to CR 101) Schematic & ENV Clearance<br />

CSJ: 1566-01-009<br />

IH-35 Northbound Ramps and Frontage Road<br />

(Westinghouse Rd to SH 29)<br />

CSJ: 0015-08-<strong>12</strong>8, etc.<br />

<strong>WILLIAMSON</strong> <strong>COUNTY</strong> PASS THROUGH FINANCING <strong>PROGRAM</strong><br />

<strong>October</strong> <strong>12</strong>, 20<strong>12</strong><br />

START<br />

CONSTRUCTION<br />

SUBSTANTIAL<br />

COMPLETION*<br />

FINAL<br />

COMPLETION<br />

07WC513 HNTB Corporation / PBS&J / Austin Bridge & Road 10/29/07 08/26/08 06/02/09<br />

08WC607 LAN / Huitt-Zollars / JC Evans<br />

01/27/09 08/07/10 Pending<br />

08WC619 Jacobs Carter Burgess / Huitt-Zollars / Hunter<br />

01/27/09 05/02/11 Pending<br />

09WC720 Dannenbaum / HDR / Dan Williams<br />

<strong>12</strong>/21/09 04/06/<strong>12</strong> Pending<br />

09WC722A Steger Bizzell / Atkins / Joe Bland<br />

09/28/10 07/<strong>12</strong>/<strong>12</strong> Pending<br />

10WC817 Klotz / JD Ramming / Raba Kistner<br />

09/13/10 Summer 20<strong>12</strong> Pending<br />

Cobb, Fendley &<br />

Assoc.<br />

DESIGN<br />

BID<br />

ESTIMATED CONST. SCHEDULE<br />

BID LETTING<br />

START FINISH ADVERTISEMENT<br />

START FINISH<br />

<strong>12</strong>/13/05<br />

ENGINEER / CEI / CONTRACTOR<br />

Dec 2010<br />

HNTB 04/25/06 Aug 20<strong>12</strong><br />

Begins 10/28/<strong>12</strong><br />

(Pending TxDOT<br />

LOA)<br />

TBD<br />

Nov 20<strong>12</strong> Nov 20<strong>12</strong> May 2014<br />

Project Complete. All necessary documentation has been submitted to TxDOT. Preparing closeout package for County.<br />

ENVIRONMENTAL<br />

CLEARANCE<br />

Env Assessment<br />

FONSI Approval<br />

Date: Early 2013<br />

Public Hearing<br />

Date: Fall 20<strong>12</strong><br />

Categorical Exclusion<br />

Approved: 8/2/20<strong>12</strong><br />

PROGRESS - ACTION ITEMS - REMARKS<br />

The sealed Materials Certification has been sent in order to obtain TxDOT Final Completion. Preparing final documentation for<br />

submittal to TxDOT.<br />

The Engineer has submitted a design revision for approval to address recent rain events at TxDOT's direction and the GEC is<br />

finalizing the design of one additional driveway that was added during construction. The GEC will submit the Engineer's design and<br />

the additional driveway under a single driveway permit to TxDOT next week. The sealed Materials Certification has been sent in<br />

order to obtain TxDOT Final Completion. Preparing final documentation for submittal to TxDOT.<br />

The Ribbon Cutting Ceremony was held on 2/8/20<strong>12</strong>. The CEI is negotiating the final change orders and closing out the project files.<br />

The sign change order was approved by Commissioners Court on 9/25/<strong>12</strong> and the Contractor has ordered the additional signs for<br />

the project.<br />

A Ribbon Cutting Ceremony was held on 11/18/11. The Ride Quality and final HMAC production & placement Change Order is being<br />

processed. The CEI is finalizing all the project records for submission and close out.<br />

Ramming is nearing completion of punchlist items. A Ribbon Cutting Ceremony was held on 6/14/<strong>12</strong>. The CEI is turning over all<br />

project records and the GEC is working to close out the project.<br />

PROGRESS - ACTION ITEMS - REMARKS<br />

The revised document was submitted TxDOT on 9/7/<strong>12</strong>, for submittal to FHWA in response to additional<br />

TxDOT ENV comments received on 8/1/<strong>12</strong> from a new reviewer. The revised EA was resubmitted TxDOT<br />

on 6/5/<strong>12</strong> with approval from SHPO and THC clearance and is under review by TxDOT ENV. The EA has<br />

been approved by SHPO and on 5/16/<strong>12</strong> written notification was received of THC clearance of the<br />

archeology. Tribal clearance was received on 2/9/<strong>12</strong>. Received TxDOT Division approval of the<br />

schematic for further processing on <strong>12</strong>/15/10.<br />

The three final sets of plans & manuals were submitted for the TxDOT Division, District and Area Offices in<br />

anticipation of receiving LOA by Friday, 10/<strong>12</strong>/<strong>12</strong>. Anticipate a request to authorize advertisement for<br />

construction bid on the 10/23/<strong>12</strong> Court agenda for approval pending receipt of LOA. On 10/4/<strong>12</strong>,<br />

responses and revisions were submitted to address the Division Design comments received on 9/26/<strong>12</strong>.<br />

On 9/25/<strong>12</strong>, responses and revisions were submitted to address the Traffic comments received on 9/13/<strong>12</strong><br />

and Bridge comments received on 9/17/<strong>12</strong>. Illumination comments were received on 9/10/<strong>12</strong> and<br />

responses & revisions were returned to TxDOT on 9/13/<strong>12</strong>. Final plans were submitted for division review<br />

on 8/31/<strong>12</strong> to address TxDOT District comments. Approval of the environmental document was received<br />

from FHWA on 8/2/<strong>12</strong>. TxDOT District comments on the plans were received 8/2/<strong>12</strong>. A meeting with<br />

Georgetown Railroad was held 8/1/<strong>12</strong>, a meeting with St David's Hospital was held 8/3/<strong>12</strong>, and a meeting<br />

with Longhorn Junction was held on 8/21/<strong>12</strong>; all to discuss Control of Access release and driveway<br />

location requests. Approval of the schematic and IAJR was received from FHWA on 7/11/<strong>12</strong>. A meeting<br />

with Wolff was held on 5/17/<strong>12</strong> to discuss Control of Access release and driveway locations. A meeting<br />

with TxDOT to discuss release of Control of Access was held on 5/8/<strong>12</strong>. A Participation Agreement for<br />

mitigation through the RHCP was approved on 4/28/09 with a mitigation fee of $252,556.00.<br />

* Substantial Completion = Open to Traffic, Minor Construction Items Remain to be Completed Page 9 of 9