PROJECT<br />
REPORT<br />
Gomaa Ice Cream<br />
Factory & warehouse project<br />
Egypt
PROJECT FINANCE<br />
AND SUPPLY MANAGEMENT<br />
ABOUT THE PROJECT:<br />
Gomaa Ice Cream, a leading ice cream producer<br />
in Egypt, has started the construction of a new<br />
production facility and warehouse in the 10th of<br />
Ramadan industrial zone, about an hour’s drive northeast<br />
of Cairo.<br />
SCHNAITER Engineering & Consulting GmbH<br />
developed the structure of the financing and also<br />
supported Gomaa in putting together the suppliers<br />
and technology provider network.<br />
Main suppliers are located in Germany and Italy.<br />
A local contractor is doing the civil works onsite.<br />
STAGE 1 (WAREHOUSE PROJECT)<br />
10,000 sqm<br />
› steel structure building for cold store rooms,<br />
raw material storage, loading area and<br />
two production lines<br />
› admin building, 3 floors<br />
› underground water tank, power station and<br />
concrete streets (4,800 sqm in total)<br />
STAGE 2 (NEW FACTORY PROJECT)<br />
26,000 sqm<br />
› production line building for six independent<br />
production lines<br />
› GEA building for chocolate production and<br />
refrigerators<br />
› pasteurization building<br />
› underground water tank, power station<br />
and lockers building
Gomaa Ice Cream<br />
Factory & warehouse project<br />
Egypt<br />
KEY FACTS:<br />
value stage 1 and 2 EUR 14 Mio.<br />
for further expansion EUR 14 Mio.<br />
bank<br />
LBBW Landesbank BW, Germany<br />
buyerscredit<br />
ECA (Export Credit Agency) Euler Hermes, Germany<br />
credit term<br />
cost of financing<br />
8 years plus 2 years grace period<br />
3% per year on average<br />
MOHAMED GOMAA<br />
Owner and CEO<br />
› Thanks to the professional support of SCHNAITER<br />
Engineering & Consulting GmbH, the German bank<br />
LBBW approved a long-term loan for our project<br />
without any further guarantees from our local bank.<br />
We are now confident of being able to open the new<br />
production lines in early 2023. ‹<br />
ABDALLAH G. MAHARIK<br />
Head of Finance<br />
› SCHNAITER Engineering & Consulting GmbH is<br />
an important interface in the coordination with the<br />
suppliers and the financing bank in Germany. All the<br />
suppliers get paid on time. Mr. Schnaiter also visits us<br />
personally on a regular basis to discuss further steps.<br />
We greatly appreciate his support. ‹
SCHNAITER Engineering & Consulting GmbH<br />
Oberes Buchenfeld 18<br />
77736 Zell am Harmersbach<br />
Germany<br />
Phone: +49 7835 634 9277<br />
Fax: +49 7835 634 9278<br />
info@schnaiter.de<br />
www.schnaiter.de<br />
Gomaa Ice Cream<br />
Factory & warehouse project<br />
Egypt<br />
WEBPAGE<br />
LINKED IN<br />
WE SET YOU UP<br />
FOR SUCCESS<br />
CONTACT