2.2 PROJECT SEGMENTS<br />

Contaminant Management Plan, SVRT/BART Extension<br />

As previously noted, the SVRT project has been divided into five segments for design and construction:<br />

• Line Segment<br />

• Tunnel Segment<br />

• Yard and Shops Segment<br />

• Stations Segment<br />

• Systems Segment<br />

This CMP is intended to cover the Line Segment, the Stations Segment, Yard and Shops Segment (which<br />

includes the planned maintenance facility), and portions (cut-and-cover stations and retained cuts) of the<br />

Tunnel Segment. These areas are discussed in further detail below.<br />

2.2.1 Line Segment<br />

The Line Segment of the SVRT project is a 9.8-mile section of track that will be located along the former<br />

UPRR ROW. The UPRR ROW was owned and operated by Western Pacific Railroad (WPRR) before it was<br />

purchased by UPRR. <strong>VTA</strong> has since purchased the alignment from UPRR.<br />

The Line Segment project will include the construction of twin tracks from the Warm Springs Station (to be<br />

constructed by BART) south to the retained cut leading to the portal for the tunnel. The Line Segment will be<br />

primarily built at-grade, though the preliminary design currently includes: aerial sections, two retained cuts,<br />

and new depressed roadways. The retained cuts currently planned include:<br />

• Retained cut for Montague Expressway and Trade Zone Boulevard, approximately 5,650 feet long<br />

and 20 to 24 feet deep; and<br />

• Retained cut for Hostetter Road, Lundy Avenue, and Sierra Road, approximately 5,100 feet long and<br />

30 to 35 feet deep.<br />

It should be noted that an aerial alternative replacing the retained cut for Montague Expressway and Trade<br />

Zone Boulevard is currently under consideration.<br />

The new depressed roadways include:<br />

• East Warren Avenue (to be designed and constructed by others);<br />

• Kato Road; and<br />

• Dixon Landing Road.<br />

For design purposes, the stations along the Line Segment are included as part of the Line Segment. These<br />

stations include:<br />

101248 – July 2008 Page 14