RRAP Report - HVPNL
RRAP Report - HVPNL
RRAP Report - HVPNL
- TAGS
- rrap
- hvpnl
- www.hvpn.gov.in
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
HARYANA POWER SYSTEM IMPROVEMENT PROJECT<br />
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
DRAFT RESETTLEMENT AND REHABILITATION ACTION PLAN<br />
PACKAGE G-1<br />
400 KV SUBSTATIONS AT<br />
NEVADA TIGAON (FARIDABAD DISTRICT)<br />
&<br />
NUHIANWALI (SIRSA DISTRICT)<br />
for<br />
HARYANA VIDYUT PRASARAN NIGAM LIMITED<br />
Prepared by<br />
5 th Floor, Tower C, DLF Building No.8, Cyber city Phase II<br />
Gurgaon 122 022 (Haryana), India<br />
Tel.(91) 124 4380042, 4501100 Fax.no. (91) 124-4380043<br />
Email: smec@vsnl.com Web: www.smec.com.au/india<br />
January 2009<br />
Page 1
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
TABLE OF CONTENTS<br />
LIST OF ABBREVIATIONS .................................................................................................... 4<br />
EXECUTIVE SUMMARY ........................................................................................................ 5<br />
CHAPTER -1: INTRODUCTION AND METHODOLOGY..................................................................... 7<br />
1.1 Background ................................................................................................................. 7<br />
1.2 The Proposed Project .................................................................................................. 7<br />
1.3 Haryana Vidyut Prasaran Nigam Limited .................................................................. 7<br />
1.4 Sub-Project Package G-1 (400 KV Sub-Station) ....................................................... 8<br />
1.5 Measures Taken to Minimize Impacts........................................................................ 9<br />
1.6 Objectives and Scope of the Study ............................................................................. 9<br />
1.7 Approach and Methodology ....................................................................................... 9<br />
1.8 Structure of the <strong>Report</strong> ................................................................................................. 10<br />
CHAPTER -2: PROFILE OF THE PROJECT AREA............................................................................ 12<br />
2.1 Introduction .............................................................................................................. 12<br />
2.2 Profile of Faridabad and Sirsa District ..................................................................... 12<br />
2.3 Socio-economic Profile of the Affected Villages ..................................................... 13<br />
CHAPTER -3: LAND ACQUISITION AND ANALYSIS OF ALTERNATIVES ...................................... 15<br />
3.1 Introduction .............................................................................................................. 15<br />
3.1.1 400 KV Sub-station at village – Nevada Tigaon village, Faridabad district ........ 15<br />
3.1.2 Analysis of Alternatives ....................................................................................... 15<br />
3.1.3 Transaction Details ............................................................................................... 16<br />
3.2 400 KV Sub-station at the village – Nuhianwali ...................................................... 17<br />
3.2.1 Analysis of Alternatives ....................................................................................... 17<br />
3.2.2 Transaction Details ............................................................................................... 18<br />
CHAPTER – 4: IMPACT ASSESSMENT .......................................................................................... 19<br />
4.1 Introduction .............................................................................................................. 19<br />
4.2 Impact on Village Nevada Tigaon ............................................................................ 19<br />
4.3 Impact on Village Nuhianwali .................................................................................. 20<br />
CHAPTER – 5: COMMUNITY CONSULTATIONS ............................................................................ 21<br />
5.1 Introduction .............................................................................................................. 21<br />
5.2 Perceptions towards the project at Nevada Tigaon .................................................. 21<br />
5.3 Perceptions towards the project at Nuhianwali ........................................................ 24<br />
CHAPTER – 6: RESETTLEMENT POLICY AND LEGAL FRAMEWORK ............................................. 27<br />
6.1 Policy, Legal and Regulatory Framework ................................................................ 27<br />
6.2 Procedure for Land Acquisition ............................................................................... 27<br />
6.3 World Bank Operational Policy on Involuntary Resettlement (OP 4.12) ................ 29<br />
6.4 <strong>HVPNL</strong> Environment and Social Policy and Procedures ........................................ 30<br />
6.5 Social Entitlement framework .................................................................................. 31<br />
CHAPTER – 7: COMPENSATION AND ASSISTANCE ...................................................................... 36<br />
7.1 Introduction .............................................................................................................. 36<br />
7.2 Compensation and assistance for Nevada Tigaon .................................................... 36<br />
7.3 Compensation and assistance for Nuhianwali .......................................................... 36<br />
CHAPTER – 8: INSTITUTIONAL ARRANGEMENTS AND GRIEVANCE REDRESSAL MECHANISMS... 37<br />
8.1 Introduction .............................................................................................................. 37<br />
8.2 Institutional Framework ........................................................................................... 37<br />
8.3 Social Procedures ..................................................................................................... 38<br />
Page 2
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
8.4 Capacity Building ..................................................................................................... 39<br />
8.5 Grievance Redress Mechanism ................................................................................ 40<br />
CHAPTER – 9: BUDGET ESTIMATES............................................................................................ 42<br />
9.1 Introduction .............................................................................................................. 42<br />
9.2 Budget and Costs (Nevada Tigaon and Nuhianwali) ............................................... 42<br />
CHAPTER – 10: IMPLEMENTATION SCHEDULE ............................................................................ 44<br />
10.1 Introduction .............................................................................................................. 44<br />
10.2 Implementation issues and Schedule ........................................................................ 44<br />
LIIST OF ANNEXURES<br />
Annexure -1A: Photographs and Layout Map of proposed site at NevadaTigaon. .................. 46<br />
Annexure -1B: Details of Land Transfer of proposed site at Nevada Tigaon.............................. 48<br />
Annexure -1C: Details of Stakeholder Consultations for Sub-Station at Nevada Tigaon........ 52<br />
Annexure -2A: Layout Map and Photographs of proposed site at Nuhianwali........................ 56<br />
Annexure -2B: Details of Land Transfer of proposed site at Nuhianwali.................................... 58<br />
Annexure -2C: Details of Stakeholder Consultations for Sub-Station at Nuhianwali. ............ 62<br />
Annexure - 3: Consultation Checklist ...................................................................................... 64<br />
Annexure - 4: Census/Socio Economic Survey Questionnaire ................................................ 66<br />
Annexure – 5: Notification regarding rate applicable for Nevada Tigaon Sub-station ............ 71<br />
Annexure - 6: Notification on circle rate applicable for Sirsa District ..................................... 72<br />
Page 3
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
LIST OF ABBREVIATIONS<br />
BPL Below Poverty Line<br />
ESMC Environment and Social Management Committee<br />
ER&RC Environmental Rehabilitation and Resettlement Committee<br />
ESIU Environmental and Social Implementation Unit<br />
ESPP Environmental and Social Policy and Procedures<br />
GOI Government of India<br />
GRC Grievance Redressal Committee<br />
HPGCL Haryana Power Generation Corporation Limited.<br />
<strong>HVPNL</strong> Haryana Vidyut Prasaran Nigam Limited<br />
IT Information Technology<br />
KV Kilo volts<br />
LAA Land Acquisition Act, 1894 (1984)<br />
LILO Loop In Loop Out<br />
NGO Non Government Organization<br />
NREGS National Rural Employment Guarantee Scheme<br />
NRRP National Resettlement and Rehabilitation Policy 2007<br />
OP Operational Policy<br />
PAF Project Affected Family<br />
<strong>RRAP</strong> Resettlement and Rehabilitation Action Plan<br />
ROW Right of Way<br />
SAMP Social Assessment and Management Plan<br />
SC Scheduled Castes<br />
WB World Bank<br />
Page 4
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
EXECUTIVE SUMMARY<br />
The proposed project – Haryana Power System Improvement Project, funded by the World<br />
Bank and implemented by Haryana Vidyut Prasaran Nigam Limited (<strong>HVPNL</strong>), aims to<br />
improve the accountability, efficiency and quality of electricity services in Haryana through<br />
investments in power supply infrastructure, training/capacity building and technologytransfer,<br />
and overall institutional strengthening.<br />
Scope of the Resettlement and Rehabilitation Plan<br />
This plan looks into the land acquisition issues and other impacts through social analysis.<br />
Resettlement and Rehabilitation Plan has been prepared for G-1 Package consisting of two<br />
400 KV sub-stations in villages of Nevada Tigaon in Faridabad district and Nuhianwali in<br />
Sirsa district of Haryana. The <strong>Report</strong> has been prepared for the Project in compliance with<br />
the Environment and Social Policy and Procedures (ESPP) of the <strong>HVPNL</strong>.<br />
Scope of Land Acquisition and Resettlement<br />
<strong>HVPNL</strong> in its attempt to locate an ideal spot for siting of the sub-station had identified a site<br />
in the village – Nevada Tigaon in Faridabad district. The 33 acres of land selected for<br />
construction of sub-station is barren uncultivable piece of land that has not been unutilized for<br />
a long period of time. This site finalized on the available Panchayat land has avoided impact<br />
on habitations, agricultural land, residential and commercial areas. Nevada Tigaon Panchayat<br />
has agreed to transfer the selected land to <strong>HVPNL</strong> as per the circle rate of land as applicable.<br />
The proposed 400 KV sub-station at the village Nuhianwali, is located in Sirsa district. Only<br />
one site was considered and finalized by <strong>HVPNL</strong>. Its’ siting is consistent with the principle<br />
enshrined in <strong>HVPNL</strong>’s Environmental and Social Policy and Procedures (ESPP) that lays<br />
emphasis on avoidance, mitigation and alleviation. This piece of land in Nuhianwali is one<br />
such patch of un-used land amidst other fertile pieces. For this sub-station, the Panchayat<br />
resolution has agreed to transfer 52.425 acres of land to <strong>HVPNL</strong> for constructing the substation<br />
and staff quarters.<br />
During the social impact assessment, it was confirmed that as a loss of this barren,<br />
uncultivable land, there shall be no displacement of any person, any adverse impacts on<br />
vulnerable group of persons, or any loss of livelihood or common property resource at both<br />
sites.<br />
Community Consultations<br />
The consultation was used as an important tool to gauge people’s perceptions and record their<br />
views with reference to the important infrastructure development in their area. Consultations<br />
were conducted with the Panchayat, village community and women group. Consultation with<br />
Panchayat brought forth that the land is being given to <strong>HVPNL</strong> and in lieu of that they will be<br />
compensated as per <strong>HVPNL</strong>’s policy. However, the Panchayat resolution does not mention<br />
the compensation and assistance amount. The outcomes of these consultations indicate that<br />
while the sub-stations would not help address the many development challenges the villages<br />
face, they certainly will help improve a few. The discussions revealed that more reliable<br />
power supply would prove immensely beneficial to increase agricultural productivity, ensure<br />
water supply for domestic and agricultural use and industrial development. They also<br />
understood that subsequently this would also lead to improvement of the approach road and<br />
would benefit both the sub-station staff and villagers. With regard to the issue of provision of<br />
employment opportunities in the project, villagers indicated that any opportunities would be<br />
Page 5
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
really beneficial as the village currently has a large number of unemployed youth. Women<br />
groups opined that this was a long and much needed development measure and uninterrupted<br />
electricity will have very positive impact on the village.<br />
Resettlement Principles and Policy Framework<br />
This project is based on the resettlement principles of avoidance, minimization and<br />
alleviation. Among other principles, special attention has been paid for the improvement in<br />
living standards of marginalized and vulnerable groups and ensuring the delivery of R&R<br />
entitlements and compensation for lost assets based on <strong>HVPNL</strong>’s entitlement framework.<br />
This project has taken into account the <strong>HVPNL</strong>’s Environment and Social Policy and<br />
Procedures, which cover the mandatory social requirements for <strong>HVPNL</strong> transmission works<br />
including Land Acquisition Act 1894, Haryana Government Rehabilitation & Resettlement<br />
Policy for land acquisition, WB OP 4.12 involuntary resettlement and WB OP 4.10<br />
Indigenous People. These policies National Rehabilitation and Resettlement Policy 2007 has<br />
also been consulted while framing the ESPP. Public is informed about the project at every<br />
stage of execution by press notes and media release etc. During the social impact assessment<br />
the survey team disseminated information on land requirement for the substation, proposed<br />
R&R measures and compensation packages was disseminated.<br />
Entitlement Framework<br />
<strong>HVPNL</strong>’s framework is to ensure realistic rehabilitation and compensation of the acquired<br />
assets of affected covering categories such as loss of land (homestead land, agriculture land,<br />
tenants, lease holders, encroachers/ squatters etc), loss of structure ( with valid title, tenants,<br />
leaseholders, squatters, cattle sheds, workshop sheds etc.), loss of livelihood, loss of standing<br />
crops/ trees, loss of access to common property resources (CPR) and facilities, losses to host<br />
communities, Panchayat land and additional benefits for vulnerable person. The entitlements<br />
for this subproject adopt and comply with the <strong>HVPNL</strong>’s framework. In Package G-1 only<br />
transfer of Panchayat land has been covered as per the entitlement framework.<br />
Institutional Framework and Grievance Redressal<br />
A three-tier set up is proposed in the ESPP of <strong>HVPNL</strong> viz., Divisional, Zonal and at<br />
Headquarters, comprising of Officials at respective levels. At the Head Quarter Level it is<br />
Environment, Resettlement and Rehabilitation Committee (ERRC), at Zonal level it is<br />
Environment and Social Monitoring Committee (ESMC), and at the Division level it is<br />
Environment and Social Implementation unit (ESIU). Grievance’s if any will be first<br />
addressed by the ESMC.<br />
Compensation and Budget Estimates<br />
Since the said pieces of land have not been officially transferred and are not getting reflected<br />
in the revenue record, budget estimates have been worked at circle rate The budget estimate<br />
for implementation of <strong>RRAP</strong> at Nevada Tigaon village is Rs. 43312500/- (Rupees Four<br />
Crores Thirty Three Lakhs Twelve Thousand Five Hundred)ly only. The budget estimate for<br />
implementation of <strong>RRAP</strong> at Nuhianwali village is Rs. 1,92,66,188/- (Rupees One Crore<br />
Ninety Two Lakhs Sixty Six Thousand One Hundred and Eighty Eight Only Only. The total<br />
estimate for both the sub-stations under G-1 Package is Rs. 6,25,78,687 (Rupees Six Crores<br />
Twenty Five Lakhs Seventy Eight Thousand Six Hundred and Eighty Seven only<br />
Page 6
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER -1: INTRODUCTION AND METHODOLOGY<br />
1.1 Background<br />
As part of the Haryana Power System Improvement Project, the G-1 Package consisting of<br />
construction of two 400 Kv substations at Nevada Tigaon and Nuhianwali are located in<br />
Faridabad and Sirsa districts of Haryana. The state of Haryana in Northern India is located<br />
strategically close to the National Capital of India New Delhi, and one third of its area falls<br />
within the National Capital Region (NCR). It is bordered by Himachal Pradesh and Punjab to<br />
the north and by Rajasthan to south and west. Its borders to Uttar Pradesh and Uttaranchal in<br />
the East are defined by the River Yamuna. The capital of the state is Chandigarh which is<br />
administered as a Union Territory and is also the capital of Punjab.<br />
With a population of 21 million people, it is one of the fastest growing economies in India.<br />
The state’s Gross State Domestic Product (GSDP) grew by 7.6% during the period 2003 -<br />
2007 and is expected to grow by 11% during next five years as per Eleventh Five Year Plan.<br />
The state was a pioneer of green revolution with a significant portion of its economy and<br />
population dependent on agriculture. Southern part of the State that falls under the National<br />
Capital Region (NCR) has experienced exceptional growth in industrial activity, particularly<br />
in sectors such as automobiles, textile and ready-made Garments and Information Technology<br />
(IT).<br />
1.2 The Proposed Project<br />
The proposed project – Haryana Power System Improvement Project, funded by the World<br />
Bank, aims to improve the accountability, efficiency and quality of electricity services in<br />
Haryana through investments in power supply infrastructure, training/capacity building and<br />
technology-transfer, and overall institutional strengthening. Major objectives include<br />
improving service delivery; enhancing operational efficiency and institutional capacities.<br />
1.3 Haryana Vidyut Prasaran Nigam Limited<br />
In 1998, the Haryana State Electricity Board (HSEB) was re-organized into State owned<br />
corporation namely Haryana Vidyut Prasaran Nigam Limited (<strong>HVPNL</strong>) for Transmission and<br />
Haryana Power Generation Corporation Limited (HPGCL). HPGCL was made responsible<br />
for operation and maintenance of State’s own power generating stations. <strong>HVPNL</strong> was<br />
entrusted the power transmission and distribution functions. Simultaneously, an independent<br />
Page 7
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
regulatory body i.e. Haryana Electricity Regulatory Commission (HERC), was constituted to<br />
aid and advise the State Government on the development of the power sector, to regulate the<br />
power utilities and take appropriate measures to balance the interest of various stake-holders<br />
in the power sector, namely electricity consumers, power entities and generation companies<br />
etc.<br />
<strong>HVPNL</strong> was further reorganized on July 1, 1999 by carving out two more Corporations,<br />
namely Utter Haryana Bijli Vitran Nigam Ltd. (UHBVNL) and Dakshin Haryana Vitran<br />
Nigam Ltd. (DHBVNL) with the responsibility of distribution and retail supply of power<br />
within their jurisdiction. While UHBVNL is responsible for Panchkula, Ambala,<br />
Yamunanagar, Kurukshetra, Kaithal, Karnal, Panipat, Sonepat, Rohtak, Jhajjar and Jind<br />
districts, DHBVN caters to Hisar, Fatehabad, Bhiwani, Sirsa, Faridabad, Gurgaon, Mewat,<br />
Rewari and Narnaul districts.<br />
The power demand in Haryana on an average has been of the order of 7 to 8% in the past, but<br />
now it is in the range of 14% for the state as a whole and between 20-25% in certain pockets<br />
like Gurgaon. In response to this increasing demand, <strong>HVPNL</strong> has prepared a comprehensive<br />
transmission program that proposes power load growth and evacuation of the proposed<br />
capacity addition of power at an estimated cost of Rs. 7643 crore during the 11 th Five year<br />
plan. Under this program <strong>HVPNL</strong> will undertake construction of new sub-stations,<br />
installations of additional transformers and laying of new transmission lines interlinking of<br />
lines of existing substations.<br />
1.4 Sub-Project Package G-1 (400 KV Sub-Station)<br />
Under the Package G-1 two 400 KV sub-stations are being proposed. The sub-station in<br />
Faridabad district is located at the village Nevada Tigaon and shall cater to the needs of<br />
industrial Faridabad. The other sub-station project is located in the village of Nuhianwali, in<br />
Sirsa district shall cater to the power demands of the district. The present report contains the<br />
findings of the social assessment for the affected area and its inhabitants. The report is<br />
prepared in conformity with the provisions of the Environment and Social Policy and<br />
Procedures of <strong>HVPNL</strong>.<br />
Page 8
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
1.5 Measures Taken to Minimize Impacts<br />
In line with the principles underlined in <strong>HVPNL</strong>’s social policy of avoidance, minimization<br />
and alleviation, efforts were made to minimize the adverse impacts of the project, while<br />
selecting the site. Various parameters considered for finalizing the site are listed below:<br />
� Availability of infrastructure facilities such as access roads, railheads, etc;<br />
� Type of land viz. government, revenue, private, agriculture;<br />
� Number of families; and<br />
� Cost of compensation and rehabilitation.<br />
1.6 Objectives and Scope of the Study<br />
The main objective of the study was to:<br />
� Identify the impacts of land acquisition and other adverse impacts as a result of the<br />
proposed substations; and<br />
� Present an action plan for delivery of the compensation and assistances outlines in the<br />
policy to the persons identified as entitled to such assistance<br />
Scope of the Study: The scope of the present study is to conduct a comprehensive survey for<br />
these sub-stations for:<br />
a) identifying potentially affected populations with special attention to vulnerable group<br />
such as indigenous/tribal populations, scheduled caste, landless households and<br />
women headed/physically handicapped households, through a baseline socio-<br />
economic survey.<br />
b) gathering information on the various categories of losses and other adverse impact<br />
likely to take place under the project. These include:<br />
� loss of land and other productive assets such as trees;<br />
� loss of structures, temporary or fixed;<br />
� loss of access to public services (roads, drinking water, schools, medical, etc);<br />
� loss of access to common property resources; and<br />
� disruption of social, cultural, religious or economic ties and networks.<br />
1.7 Approach and Methodology<br />
Approach and methodology devised for the project mainly consisted of qualitative and<br />
quantitative tools and techniques. The study was conducted in three phases:<br />
Page 9
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Phase I: Pre-survey Activities: This phase included collection of secondary data, collection of<br />
site details from <strong>HVPNL</strong>, preparation of questionnaires and checklist for conducting Focus<br />
Group Discussions. Documents from the <strong>HVPNL</strong> included site map, requirements for<br />
substations and other relevant maps. The Consultants also collected information from<br />
secondary sources viz. Census of India and District Census Handbook and revenue records.<br />
The phase was important to identify and scope the activities. The entire exercise was carried<br />
out through an appropriate mix of social research techniques including desk research through<br />
review of information available with <strong>HVPNL</strong>. Checklist for structured and semi-structured<br />
interviews, group discussions with the affected people and relevant government agencies and<br />
community were planned. A questionnaire was designed to facilitate collection of relevant<br />
socio-economic and land holding information. The Questionnaires and Checklist for FGDs<br />
used in this study are presented in the Annexure-3&4.<br />
Phase II: Survey Activities: This phase consisted of site visits, verification of documents,<br />
conducting consultations with stakeholders. Site visits carried out to assess its location and<br />
proximity to habitations, and record the land use around the substations. The verification<br />
process involved validation of information as on ground. In the case of the said substations, as<br />
there is no loss of land to any individual, the socio-economic survey using the questionnaire<br />
was not carried out. However, consultations were held with the concerned village panchayat<br />
representatives to document their views. The consultations included FGD with various<br />
groups, knowledgeable persons, village heads and women. It sought to elicit their<br />
expectations and suggestions, willingness to contribute, their perception of the project and<br />
likely benefits that are to accrue to them.<br />
Phase III: Post Survey Activities – Analysis and <strong>Report</strong>s<br />
The information collected through consultations, FGDs, secondary sources and documents<br />
was cross-validated, processed and analyzed. Wherever required, the observations are<br />
supported from the information collected through desk research.<br />
1.8 Structure of the <strong>Report</strong><br />
The Chapterisation plan for this <strong>RRAP</strong> is given in the table below:<br />
Chapters Title of Chapter Brief Description of Contents<br />
1 Introduction and Methodology Project description, details on land and methodology<br />
adopted<br />
2 Profile of Project Area Districts profiles of Sirsa and Faridabad (inclusive of<br />
Population, social composition, Education, work force<br />
Page 10
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Chapters Title of Chapter Brief Description of Contents<br />
etc.)<br />
Impacted villages and their socio-economic profile<br />
covering Population, gender, workers, poverty,<br />
literacy, unemployment<br />
3 Land Acquisition and Analysis of<br />
Alternatives<br />
Land use<br />
Adverse/positive Impacts on land/private<br />
properties/common property resource; Alternatives<br />
Landholding size<br />
4 Impact Assessment Social impact assessment of the affected villages<br />
5 Community Consultations<br />
Details on the community consultation (consultations<br />
with women and other groups)<br />
6 Resettlement Policy and Legal<br />
Framework<br />
7 Compensation and Assistance<br />
8 Institutional Arrangements &<br />
Grievance Redress Mechanisms<br />
9 Budget Estimates<br />
<strong>HVPNL</strong> policy and entitlements and its applicability<br />
Adverse impacts and mitigation measures as per<br />
entitlements/Land transfer/Lease etc.<br />
Mechanisms<br />
redressal<br />
for implementation and grievance<br />
Budget Estimate for implementation of <strong>RRAP</strong><br />
10 Implementation Schedule Time duration for implementation of <strong>RRAP</strong><br />
Annexures<br />
Annexure -1A: Photographs and Layout Map of proposed site for Sub-Station at Nevada.<br />
Annexure -1B: Details of Land Transfer of proposed site for Sub-Station at Nevada.<br />
Annexure -1C: Details of Stakeholder Consultations for Sub-Station at Nevada.<br />
Annexure -2A: Layout Map and Photographs of proposed site for Sub-Station at Nuhianwali<br />
Annexure -2B: Details of Land Transfer of proposed site for Sub-Station at Nuhianwali.<br />
Annexure -2C: Details of Stakeholder Consultations for Sub-Station at Nuhianwali.<br />
Annexure - 3: Consultation Checklist<br />
Annexure - 4: Census/Socio Economic Survey Questionnaire<br />
Page 11
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER -2: PROFILE OF THE PROJECT AREA<br />
2.1 Introduction<br />
This chapter provides an overview of the two districts – Faridabad and Sirsa and particulars<br />
on specific project area impacted by the two sub-stations under Package G-1 i.e. 400 KV<br />
Sub-stations at Nevada Tigaon and Nuhianwali.<br />
2.2 Profile of Faridabad and Sirsa District<br />
Faridabad district came on the map of Haryana on 15th August, 1979 as the 12th District<br />
of the state. The new<br />
District was carved out<br />
from erstwhile Gurgaon<br />
District. It is bounded by<br />
Union Territory of Delhi<br />
(National Capital) on its<br />
north, Gurgaon District on<br />
the west and State of Uttar<br />
Pradesh on its east & south,<br />
as shown in Figure 2.1. The<br />
river Yamuna separates the<br />
District Boundary on<br />
eastern side with UP State.<br />
Delhi-Agra National<br />
Highway No.2 (Shershah<br />
Suri Marg) passes through<br />
Figure 2.1 – Map of Faridabad District in Haryana<br />
centre of District. Total area of the district is 2151.00 Km.<br />
Page 12
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Sirsa district, which isone of<br />
the oldest districts of Haryana.<br />
The derivation of name Sirsa, is<br />
attributed to the abundance of<br />
siris trees. The entire area of<br />
the district was included in the<br />
new state of Haryana on<br />
November 1, 1966. It has a<br />
total area of 4277 sq.km, 7<br />
blocks and 325 villages As<br />
shown in Figure 2.2, the district<br />
borders the state of Punjab in<br />
north and north-east.<br />
Table 2.1 provides a comparison of the profiles of the two districts in terms of the sex ratio,<br />
literacy rate, proportion of main workers, percentage of urban population to the overall<br />
population. It is clear from the table that Faridabad district is ahead in terms of literacy and<br />
urbanization, while in terms of percentage of main workers, Sirsa is ahead.<br />
District<br />
Name<br />
Table 2.1 – Population profile of Faridabad and Sirsa District<br />
Population Sex Ratio<br />
(Females<br />
per 1000<br />
males)<br />
Figure 2.2 – Map of Sirsa District in Haryana<br />
Literacy<br />
Rate (%)<br />
Main<br />
Workers<br />
(%)<br />
Non-<br />
Workers<br />
(%)<br />
Proportion<br />
of Urban<br />
population<br />
(%)<br />
Faridabad 2194586 839 70 27.8 64.2 55.7<br />
Sirsa 1116649 882 60.6 32.5 57.4 26.3<br />
Source: Census of India, 2001<br />
2.3 Socio-economic Profile of the Affected Villages<br />
400 KV Substations have been proposed at the villages of Nevada Tigaon and Nuhianwali. A<br />
brief description of the socio-economic profile of both the villages is given below.<br />
Nevada Tigaon: The village falls in the Ballabgarh sub-district of Faridabad district. As per<br />
Census, 2001, it has a total of 383 households and a total population of 2538 persons. The<br />
household size in the village is 7 members. The sex ratio in the village is 880 females per one<br />
thousand males. Males constitute 53% and females constitute the balance 47% of the total<br />
population. The village has no SC population. Literacy rate of the village is 68.9%. Work<br />
Page 13
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
participation rate of the village is 38.1% with 32.6% being the main workers. Of the total<br />
workers, 17.6% are cultivators and 1.6% being agricultural laborers.<br />
Nuhianwali: The village falls in the Dabwali sub-district of Sirsa district. As per Census,<br />
2001, it has a total of 675 households and a total population of 3898 persons. The household<br />
size in the village is 6 members. The sex ratio in the village is 898 females per one thousand<br />
males. Males constitute 52% and females constitute the balance 48% of the total population.<br />
Scheduled Caste population of the village is 15.2%. Literacy rate of the village is 58.2%.<br />
Work participation rate of the village is 52.3% with 46.4% being the main workers. Of the<br />
total workers, 60.1% are cultivators and 17.1% being agricultural laborers.<br />
Page 14
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER -3: LAND ACQUISITION AND ANALYSIS OF ALTERNATIVES<br />
3.1 Introduction<br />
<strong>HVPNL</strong>’s ESPP indicates that on the basis of data for various parameters considered during<br />
selection process, a comprehensive analysis for each alternative site is carried out. Weightage<br />
is given to various parameters for finalizing alternative sites which are often site specific. Due<br />
consideration is given to availability of infrastructure facilities such as access roads, railheads<br />
etc. type of land viz. government, revenue, private, agriculture. In addition, social impacts<br />
such as number of families affected as well as cost of compensation and rehabilitation are<br />
considered as well.<br />
This chapter deals with the land acquisition, details of the land transfer based on discussions<br />
with officials, villagers and review of resolutions and documents provided. It also provides a<br />
comparison of sites identified based on the selection criteria as stated above.<br />
3.1.1 400 KV Sub-station at village – Nevada Tigaon village, Faridabad district<br />
The proposed 400 KV Sub-station is located at Nevada Tigaon village in Faridabad district. It<br />
is a critical sub-station that shall meet the fast growing demands of industrial Faridabad. The<br />
proposed site is adjacent to another power utility – NTPC gas-based plant, besides many other<br />
existing 66 KV, 132 KV and 220 KV lines. The site is approximately 2-3 km from the main<br />
road and has a village road leading to it.<br />
The village has 250 acres of cultivable, besides 200 acres of uncultivable panchayat land.<br />
The land use is predominantly agricultural. While the average landholding is 3-4 acres per<br />
household, some of the well-off villagers reportedly have more than 10 acres of land.<br />
3.1.2 Analysis of Alternatives<br />
<strong>HVPNL</strong> in its attempt to locate an ideal site for the sub-station had approached the district<br />
revenue authorities and sought their help to identify a suitable piece of land. Preference was<br />
indicated for a piece of land that was in close proximity to existing transmission lines and<br />
meeting other engineering factors such as load factor, avoidance of fertile agricultural lands<br />
etc. The district authorities responded with this piece of land that had been barren and<br />
uncultivable. Table 3.1 below indicates the criteria adopted for selection of site.<br />
Page 15
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Table 3.1 – Criteria for selection of Nevada Tigaon village site<br />
Selection criteria Followed in<br />
finalized Option<br />
Remarks<br />
Availability of infrastructure facilities such as<br />
Y Dusty, village roads lead to<br />
access roads, railheads, etc.<br />
the site<br />
Type of land viz government, revenue, private,<br />
Y Panchayat land and un-<br />
agriculture<br />
cultivable<br />
Number of families affected Y no displacement<br />
Cost of compensation and rehabilitation Y Compensation as per policy<br />
Other criteria (Water logging, etc)<br />
Y- Yes, N- No<br />
N<br />
It is located near a village road, which is motorable (see layout map of proposed site given in<br />
Map No.1, Annexure-1 A). This piece of land is one of the few patches of barren<br />
uncultivable land amidst other fertile land in its vicinity. Crop such as Mustard, besides other<br />
vegetables are grown. Verification process revealed that the land has no productive use for a<br />
long period of time. No group in this village or adjoining village has had any use for it. Its<br />
use as grazing area for cattle too had been discontinued long ago. Water supply too is not a<br />
constraint and both the sub-station and the village shall continued to well-served on this<br />
account. This finalized site is consistent with <strong>HVPNL</strong>’s ESPP that lays emphasis on<br />
avoidance, mitigation and alleviation. As it also met the engineering/power transmission<br />
considerations no other site was requested or identified for comparison.<br />
3.1.3 Transaction Details<br />
Panchayat vide a resolution passed has agreed to give 33 acres land (see Annexure 1-b for<br />
copies of resolutions passed by the Panchayat). There are two resolutions to this effect, one<br />
is dated 6 th November, 2007 and another 6 th September 2008 and both have certain key pre-<br />
conditions as described below.<br />
The resolution dated 6 th November 2007clearly mentions unanimous agreement to donate the<br />
said land to the <strong>HVPNL</strong>, village provided its development needs are met. These needs as<br />
mentioned are:<br />
24 hours electricity supply to the village Nevada Tigaon either free of cost or at lower<br />
rate;<br />
� Employment should be provided to the villagers in this subproject as per their<br />
capabilities<br />
� Compensation should be given for land as per market rate.<br />
The resolution dated 6 th September 2008 has dropped some pre-conditions while others have<br />
been retained. Conditions that have been retained are:<br />
� 24 hours power supply be provided to the village;<br />
Page 16
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
� compensation for land should be given as per circle rate<br />
The following conditions have been deleted are:<br />
� provision of power at no cost or at lower rates; and<br />
� provision of employment to the villagers as per capabilities.<br />
During the consultations, the villagers were informed that the compensation would be as per<br />
policy applicable of government of Haryana. It is expected that upon completing of<br />
processing of land transfer documents, the final document would indicate the agreed terms<br />
and conditions and would therefore be key in the smooth implementation of the project.<br />
3.2 400 KV Sub-station at the village – Nuhianwali<br />
The proposed 400 KV Sub-station at the village Nuhianwali is a key substation as it is the<br />
starting point for 2 transmission lines – a 46.5 km line from Nuhianwali to Masoodpur and<br />
another 34.6 km line from Nuhianwali to Kirori in Fatehabad, and would serve Sirsa district.<br />
The land use in the village is predominantly agricultural. The village has 6500 acres and in<br />
addition to which it has 350 acres of panchayat. While, the average landholding is 2-3 acres<br />
per household, nearly 10% of the households have lands with better off villagers having 10-12<br />
acres.<br />
3.2.1 Analysis of Alternatives<br />
<strong>HVPNL</strong> in its attempt to locate an ideal site for of the sub-station based on its principle of<br />
avoidance, identified this piece of Panchayat land at Nuhianwali village. Table 3.2 indicates<br />
the criteria adopted for selecting this site.<br />
Table 3.2 - Criteria for selection of Nuhianwali village site<br />
Selection criteria Followed in<br />
finalized Option<br />
Remarks<br />
availability of infrastructure facilities such as Y Connectivity is fine as there is a<br />
access roads, railheads, etc.<br />
national highway from Sirsa-Dabwali<br />
adjacent to the site. Also there is a<br />
tank for storage of rain water<br />
type of land viz government, revenue, private,<br />
agriculture<br />
Y un-cultivable Panchayat land<br />
number of families affected Y no displacement<br />
cost of compensation and rehabilitation Y Compensation as per policy<br />
Other criteria (Water logging, etc)<br />
Y- Yes, N- No<br />
Y No other criteria<br />
In its attempt to avoid fertile cultivable land, <strong>HVPNL</strong> identified this piece of land in<br />
Nuhianwali village. Verification process on ground confirmed that the identified site is barren<br />
uncultivable land Road connectivity a key selection criterion is very well met as the site is<br />
Page 17
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
adjacent to Sirsa-Dabliwali national highway (see layout map of proposed site given in Map<br />
No.1, Annexure-2A). Also the key requirement of water supply is ensured by the presence of<br />
a water tank, adjacent to the site.<br />
As it met the key selection criteria and was consistent with the principles enshrined in ESPP,<br />
no other option was considered.<br />
3.2.2 Transaction Details<br />
The Panchayat vide a resolution passed in December 2007 had agreed to give 52.425 acres of<br />
land. (See Annexure- 2 B for copy of resolution passed by the Panchayat). The resolution that<br />
has been passed unanimously states that:<br />
� Panchayat is willing to give 52.425 acres of land on the condition that the electricity<br />
supply provided to the village for domestic and agriculture purpose, shall be<br />
equivalent to the supply provided in towns; and<br />
� for this purpose, land is being given as a gift.<br />
During the consultations, the villagers were informed that the compensation would be as per<br />
policy applicable of government of Haryana. In context of project implementation, the key<br />
issue is with regard to the condition stated in the resolution, i.e. power supply similar to what<br />
is being provided to those living in towns. Upon processing, the final transfer document<br />
would indicate all such details and would therefore be a key aspect to the smooth<br />
implementation of the project.<br />
Page 18
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER – 4: IMPACT ASSESSMENT<br />
4.1 Introduction<br />
The ESPP as well as past experiences indicate that the social issues normally associated with<br />
siting of sub-stations are:<br />
� Loss of land<br />
� Loss of house/structures (although so far structure has been acquired by <strong>HVPNL</strong> for<br />
its transmission projects).<br />
� Loss of livelihood due to acquisition of private agricultural land<br />
� Loss of common property resources due to acquisition of revenue land.<br />
In case of both the substations, loss of Panchayat land is the only impact. The Consultants<br />
verified that these sites are barren and that there shall be no displacement of any person(s).<br />
Further, there is no adverse impact on vulnerable group of persons, or loss of livelihood or<br />
common property resource at both sites. The indirect impacts as felt by the village<br />
community have been recorded in the next chapter on Community Consultations.<br />
4.2 Impact on Village Nevada Tigaon<br />
Nevada Tigaon village, in the vicinity of Faridabad town is a reasonably developed village.<br />
The village is well served in terms of facilities for education, medical needs and other training<br />
requirements. Though the main occupation of the village is agriculture, youths (including<br />
girls) have taken employment outside the village, in the nearby town. Villagers informed that<br />
the land that had been agreed upon for giving to <strong>HVPNL</strong> was not being put for any productive<br />
use and therefore its loss was unlikely to adversely impact their village.<br />
The verification process and interaction with villagers revealed that they were fully aware of<br />
the loss and transaction process and would be happy to receive benefits from the project.<br />
Fringe benefits such as shops in the periphery of the sub-station and improvement to the<br />
village road that leads to the site, are likely too.<br />
Positive gender impact is likely in view of the fact that better power supply shall enable<br />
women to use electronic appliance for certain domestic chores (for FGD with women groups<br />
see Annexure 4). Discussions with women groups revealed household chores such as ironing,<br />
churning of butter from milk, threshing etc suffer as a result of poor power supply.<br />
Page 19
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
It can be safely concluded that the proposed sub-station will have no negative impact on the<br />
population of this village or of the adjoining villages.<br />
4.3 Impact on Village Nuhianwali<br />
The piece of land finalized for the substation site is a barren and uncultivable land, which the<br />
village Panchayat has agreed to give to <strong>HVPNL</strong>. The site enjoys good location in terms of its<br />
proximity to the road and water storage facility. During the course of social assessment, it<br />
emerged that there are similar pieces of land in the area and the village could have given more<br />
land if so required. Its loss, therefore, is unlikely to have any negative impacts. The proposed<br />
sub-station of 400 KV has many positive benefits for the village as a whole in addition to the<br />
area of Sirsa.<br />
In this context, it would be appropriate to state the due to the substations only positive impacts<br />
and potential benefits are envisaged in the following areas:<br />
� agricultural productivity of the village would increase manifold as reliable supply of<br />
electricity would help improve the irrigation and increase productivity;<br />
� education of children that currently suffers due to poor supply would receive a major<br />
boost;<br />
� better supply is likely to open the possibility of diversifying and moving beyond<br />
agriculture and enable them to start household industries, besides generating employment;<br />
� help reduce pollution of environment as the current poor supply results in excessive use of<br />
diesel gensets;<br />
� reduced expense on diesel genset would positively impact household incomes and in turn<br />
increase purchasing power;<br />
� discussions with women indicated that household works like ironing, refrigeration would<br />
be greatly facilitated;<br />
� the sub-station is likely to spin-off certain benefits that would contribute to development.<br />
Over the long run, these might lead to increase in land value of adjacent tracts of land.<br />
Page 20
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER – 5: COMMUNITY CONSULTATIONS<br />
5.1 Introduction<br />
Consultation refers to the two-way transfer of information or joint discussion between project<br />
proponent and the community in concern. It helps build a rapport with the community and<br />
also helps to provide certain details on the area that planners cannot often foresee. It helps<br />
identify impacts, the vulnerable groups, their source of vulnerabilities and the people and<br />
groups that are likely to be affected. Besides information provided during such consultations<br />
help allay fears and builds trust – a key aspect to the successful implementation of any<br />
project.<br />
This chapter provides details on the community consultations held and their outcomes with<br />
respect to the villages where the two sub-stations are sited. These consultations covered a<br />
host of issues, such as current land holding, BPL status, land provided for sub-station,<br />
education, health and sanitation facilities prevalent, crops cultivated, employment<br />
opportunities likely, etc. Also, attempt was made to understand the status of power supply,<br />
on-going development schemes of government in the village or its vicinity.<br />
5.2 Perceptions towards the project at Nevada Tigaon<br />
Villagers in general, elderly members and women in particular, were consulted to ascertain<br />
their views on the project, besides, which to elicit their views on what are likely to be positive<br />
and negative impacts. Another objective to see if any improvements could be made based on<br />
their suggestions that would i) possibly enhance the overall aesthetics in the vicinity of the<br />
sub-station and ii) bring development to the village as a whole.<br />
Consultation with villagers: Consultations began by gathering information on the overall<br />
socio-economic condition of the village and by providing information on issues as indicated<br />
in the attached checklist (see Annexure - 1c). These issues included: details of proposed Sub-<br />
station (KV, coverage of area), duration of construction, etc. In response to the query on<br />
status of power supply, they indicated that supply is available for around 12-14 hours in a day<br />
spread across day and night. Power shortages for about 10-12 hours occur in the early<br />
morning as well as in the evenings.<br />
Page 21
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Discussions on the current land use and occupation brought out that land is mainly used for<br />
agriculture and crops such as Mustard, Wheat and Paddy are grown. Also vegetables such as<br />
Tomato, Raddish are grown, besides, sugarcane. Majority of the villagers are engaged in<br />
cultivation. Though more than one hundred are reportedly unemployed they are unwilling to<br />
work in their village when opportunities arise out of government schemes such as NREGA.<br />
Literacy is high with many girls in the village being educated and employed in adjacent towns<br />
of Faridabad and Gurgaon.<br />
In this context, topic of provision of land for Sub-station was discussed. The villagers<br />
indicated that this piece of land had been barren for a long period of time. The Sarpanch<br />
added, in the past too, that they had provided barren panchayat land for other development<br />
purposes. It provided 113 acres of land to a technology institute besides another 33 acres for<br />
some other purpose. In response to query on what their expectations were in return for the<br />
land provided, they responded that better power supply to the village would be big plus as its<br />
shortage was impacting education, irrigation and also carrying out of domestic chores.<br />
The accompanying officials were requested to inform the villagers on safety norms<br />
applicable. They informed the villagers that sub-station would not be a thoroughfare and have<br />
restricted entry. It would be surrounded by a boundary wall. The villagers understood the<br />
impending restrictions and indicated that they are aware of such issues as they have seen<br />
NTPC Gas power plant that is a distance of 5-6 km from the village.<br />
The issue of enhancement of features of the area around the sub-station was also discussed.<br />
They were informed that there might be temporary loss of land and other disturbance during<br />
construction period of 1-1/2 years. The villagers understood that it would take place, but<br />
subsequently this would also lead to improvement of the approach road that would benefit<br />
both the sub-station staff and villagers.<br />
On mitigation measures relating to the loss of land, discussions indicated that the villagers<br />
that they had laid conditions such as free (or discounted) 24 hours power and also provision of<br />
employment. However, subsequent discussions have resulted in the recent resolution that<br />
mentions the condition of 24 hours of power supply. They were aware that the compensation<br />
would be payable, though the exact amount was still not known to the villagers. Assistance in<br />
terms of employment opportunities was requested.<br />
Page 22
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Overall expectations from the project were high as it would help address one of the key and<br />
basic requirements of the village.<br />
Consultations with vulnerable group – women: Women constitute a vulnerable group<br />
because they may be excluded from participation and because they are often exposed to<br />
greater risk of impoverishment. It is a good practice to reach out such vulnerable groups in a<br />
consultative process, as they may not always participate in public forums. They were<br />
consulted to:<br />
o provide information on the proposed sub-stations; and<br />
o to record their views and perceptions on benefits from the better power supply<br />
Discussions began with issue of education of females in the village and how they might<br />
benefit from this project. Women responded that while some of them are educated, nearly all<br />
of their female children are going to school. In addition, some of the girls of the village are<br />
employed in government service in nearby towns of Sohna and Gurgaon. They indicated that<br />
the current education scheme wherein books, and tuition fees is provided free of cost, is a<br />
good scheme but only available to the female children of BPL families and not for all.<br />
Women in this village as in any other, have an important role in household management and<br />
in economically productive activities, especially by making non-wage contributions to<br />
household subsistence. Informal contributions to household subsistence include subsistence<br />
agriculture and collection of fuel and water, not to mention cooking, cleaning, and child-care.<br />
They provide support to their men-folk in the fields as well as carry out chores at home.<br />
Women members indicated that while the supply is available for a period of 10-12 hours in a<br />
day, they feel it is necessary for a few more hours, particularly during day time. They<br />
reasoned that during this period of day, they are required to do certain tasks like threshing etc,<br />
which in absence of power has be done manually. They indicated that doing these chores<br />
manually is very time-consuming and tiring. Besides as a few other women in the village are<br />
reportedly employed in government jobs. Some of the women members conveyed that they<br />
would wish to pursue certain courses such as beauty and sewing courses that are being offered<br />
by nearby training institutes. They felt that, if chores such as threshing would get simplified<br />
by power supply, they would have spare time to pursue such courses as per their wish. Some<br />
of them, however, were also reluctant to let their men-folk know of such keen interests.<br />
Page 23
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Overall expectations of development as a result of the sub-station were high with the potential<br />
for positive gender impact on women as a consequence.<br />
5.3 Perceptions towards the project at Nuhianwali<br />
Consultations were held with the Panchayat member, villagers – general community to<br />
understand their views on the project and the benefits that they are likely to receive. Attempt<br />
was made to get the feedback from the stakeholders on the positive and negative impacts of<br />
the project. Also the consultations were aimed to get an views on aesthetics appeal of the area<br />
around their land in view of construction of sub-stations. Apart from these, the Consultations<br />
covered a host of issues, such as current power supply situation, land holding, BPL status,<br />
land given to <strong>HVPNL</strong> for substation, education, health, prevalent sanitation facilities,<br />
cropping pattern, employment opportunities, etc. Also, attempt was made to understand on-<br />
going development work in the village and its vicinity.<br />
Project information and safety issues: During the Consultations the villagers were explained<br />
the importance of safety measures in and around the sub-station including fencing and the<br />
restrictions on land use and activities. The villagers understood and accepted the restrictions.<br />
The villagers in fact came forward to part with more land for such activities, in case the need<br />
arises.<br />
Social impacts: The scenario of temporary loss of access to road does not arise as the site is<br />
adjacent to a major road which is accessible through out the year and any such activity would<br />
not affect the movement on the road. Villagers stated that in order to overcome shortage in<br />
power supply there have been many cases of installation of gensets. While this increases the<br />
household expenditure on diesel, it is also polluting the environment. This pollution, in the<br />
long run is bound to increase at a much faster rate if the power supply continues to be is<br />
inadequate as both usage of gensets and population using it are increasing.<br />
Education for children is much encouraged by all households in the village. Though there are<br />
no constraints in terms of schools and other facilities required for education, the lack of<br />
reliable and adequate supply is causing children to lose vital hours of studies. This was a<br />
major cause of worry for parents and in particular for the females members consulted.<br />
Currently there is a vast focus on the agriculture, due to availability of huge chunks of land,<br />
however the villagers are also involved in small scale and household industries as well.<br />
Page 24
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
However, viable commercial operations are not possible without regular un-interrupted power<br />
supply. Creation of power grid and sub-stations is likely to give an impetus to promotion of<br />
small scale and household industries.<br />
A major concern for women was provision of water supply and the hardship caused in its<br />
absence. In absence of regular power supply, the water supply has remained erratic in the<br />
villages.<br />
Enhancements: The area is already fairly developed and consistent power supply would lead<br />
to increased industrial and agricultural production thereby resulting in increased employment<br />
opportunities and overall economic development. Majority of the consulted stakeholders<br />
including the sarpanch perceived that the project would have positive impact on the village.<br />
They added the major enhancement would be to the agricultural potential which is currently<br />
hampered due to poor power supply.<br />
Temporary or permanent employment opportunities: The issue of provision of temporary (or<br />
permanent) employment opportunities, if any was discussed. During construction of sub-<br />
station and staff quarters, labour force (both skilled and unskilled) would be required.<br />
Villagers stated that some of their youths had undergone ITI training and this project can<br />
provide them suitable employment opportunities during construction as well as operational<br />
phase.<br />
Page 25
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 26
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER – 6: RESETTLEMENT POLICY AND LEGAL FRAMEWORK<br />
6.1 Policy, Legal and Regulatory Framework<br />
This section presents the legal requirements of Land Acquisition Policy and the Resettlement<br />
and Rehabilitation Policy and entitlements for affected families. The legal framework for any<br />
project includes process of land acquisition and measures to mitigate adverse impacts.<br />
Haryana government had published its R&R policy in December 2007. As a result <strong>HVPNL</strong><br />
has joined a list of entities in power transmission business to have an Environment, Social<br />
Policy and Procedures document. The features of the R&R Policy are indicative of the kind of<br />
impacts that have been felt by such companies over many years.<br />
<strong>HVPNL</strong> undertakes its transmission activities within purview of Indian laws keeping in mind<br />
appropriate obligations and guidelines of statutory and funding agencies. Power transmission<br />
projects are not included in schedule-I of Environment Impact Assessment-1994, hence<br />
environment clearances are not required for power transmission projects and would require<br />
limited environmental analysis and Environmental Management Plan (EMP) only.<br />
As per provision contained in Haryana Electricity Reforms Act 1997 & Electricity Act, 2003<br />
Acts, <strong>HVPNL</strong> has authority to install transmission towers in any kind of land. Electricity Act,<br />
2003 seeks to create a framework for the power sector development by measures conducive to<br />
the industry. Power transmission schemes are planned in such a way that the power of<br />
eminent domain is exercised responsibly. Mandatory environment requirements for <strong>HVPNL</strong><br />
transmission works include: Mandatory social requirements for <strong>HVPNL</strong> transmission works<br />
includes Land Acquisition Act 1894, Haryana Government Rehabilitation & Resettlement<br />
Policy for land acquisition Oustees and funding agencies requirement like WB OP 4.12<br />
involuntary resettlement, WB OP 4.10 Indigenous People. National Rehabilitation and<br />
Resettlement Policy 2007 has also been consulted while framing the ESPP.<br />
6.2 Procedure for Land Acquisition<br />
All land acquisition for any public purpose in the state is governed by the Land Acquisition<br />
Act 1894 as amended from time to time by the State Government. This empowers the<br />
government to acquire compulsorily any land not owned by it which is required for a public<br />
purpose. The definition of land includes benefits to arise out of land & things attached to earth<br />
Page 27
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
or permanently fastened to anything attached to the earth. This act applies to those with legal<br />
entitlements to land and structures thereon.<br />
(i) For any LA the Act under section (u/s)-4(1) stipulates publication of a notification to<br />
that effect in the official Gazette and in 2 daily newspapers circulated in the locality, at<br />
least, one shall be in the regional language. Such a publication authorizes an<br />
authorized officer to enter upon such a land make a preliminary survey ascertain its<br />
suitability and determine the exact position of land to be acquired. However, person<br />
can enter into any building or any enclosure attached to a dwelling house either by<br />
giving notice of seven days to the occupant or with the consent of occupant. The<br />
substance of this notification is given as public notice at a convenient place in the<br />
locality in which the land to be acquired is located, such a notification provides an<br />
opportunity to the parties interested in the land to file objections if any, u/s-5A to the<br />
proposed acquisition.<br />
(ii) In order to proceed with the acquisition of the land (as notified u/s-4) it is followed by<br />
declaration u/s 6 of the ibid Act specifying that land is required for public purpose.<br />
Every declaration is published in the official Gazette and in two daily newspapers with<br />
circulation in the local area, thereafter revenue Department issues direction to the<br />
Collector u/s-7 of the Act to take order for the acquisition of notified land to be<br />
marked out, measured land/or other immovable properties, which is done under the<br />
provision of Sec.8 of the act in question. Thereafter under the provisions contained in<br />
Sec.-9 notices are served to the concerned persons stating the intention of the<br />
Government to take possession of the land and that any claims for compensation<br />
should be made to the Collector, Finally, the award of compensation is made by the<br />
collector u/s-11 of the Act after inquiring into objections(if any) in pursuance of the<br />
notice given u/s-9 to the measurements made u/s-8 and into the value of the land on<br />
the date of publication of the notification/s4(1). The award u/s-11 is made within two<br />
years from the date of publication of the declaration and if no award is made within<br />
this period, the entire proceedings of the LA is lapsed and fresh notification u/s-(4)<br />
needs to be initiated. Once the award is passed, the collector takes possession of the<br />
land which there upon vests absolutely in the Government free from all encumbrances.<br />
However, in case of urgency Section-17 of the Act empowers the Collector to take<br />
possession of the land even though no award has been made. Such land thereupon<br />
vests with the Government free from all encumbrances.<br />
Page 28
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
However, this Act further provides remedy for seeking enhancement of compensation by the<br />
person to seek enhancement of compensation in lieu of acquired as per provisions contained<br />
in Sec.18 of ibid Act.<br />
This act was further amended in 1984 with respect to sections 4,23,28 and 34 which deal with<br />
publication of primary notification determination of compensation; power of the court in<br />
determining the amount of compensation; interest on compensation and payment of interest<br />
respectively. To sum up the amended provisions have resulted in the following:-<br />
� The publication of the primary notification, apart from the Official Gazette, has to be<br />
made in two daily newspapers circulated in that locality of which at least one shall be<br />
in the regional language.<br />
� In addition to the market value of the land the court is to award a sum of thirty percent<br />
as solarium on such market value in consideration of the compulsory nature of the<br />
acquisition.<br />
� The amount of compensation awarded by the court is not to be lower than the amount<br />
awarded by the collector.<br />
� The interest of excess compensation has been enhanced from 9 per cent to 15 per cent<br />
after the date of expiry of a period of one year from the date on which possession has<br />
been taken.<br />
<strong>HVPNL</strong> strictly follows procedures laid down under the Land Acquisition Act (LA Act),<br />
1894, when land is acquired for sub-stations. Once the award is passed, the collector takes<br />
possession of the land which there upon vests absolutely in the Government free from all<br />
encumbrances. These are further reinforced taking into consideration <strong>HVPNL</strong>’s entitlement<br />
framework and public consultation process apart from inbuilt consultation process of LA Act,<br />
public consultation/information by <strong>HVPNL</strong> is an integral part of the project implementation.<br />
Public is informed about the project at every stage of execution by Press Notes and media etc.<br />
During socio-economic survey taken up in parallel with land acquisition process, <strong>HVPNL</strong>’s<br />
site officials meet people and inform them about the Land acquisition details, proposed R&R<br />
measures and compensation packages.<br />
6.3 World Bank Operational Policy on Involuntary Resettlement (OP 4.12)<br />
The objectives of the Bank’s Operational Policy (OP 4.12) on Involuntary Resettlement are as<br />
follows:<br />
Page 29
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
� Involuntary resettlement should be avoided where feasible, or minimized, exploring<br />
all viable alternative project designs.<br />
� Where it is not feasible to avoid resettlement, resettlement activities should be<br />
conceived and executed as sustainable development programs. Providing sufficient<br />
investment resources to enable the persons displaced by the project to share in project<br />
benefits.<br />
� Displaced persons should be meaningfully consulted and should have opportunities to<br />
participate in planning and implementing resettlement programs.<br />
� Displaced persons should be assisted in their efforts to improve their livelihoods and<br />
standards of living or at least to restore them, in real terms, to pre-displacement levels<br />
or to levels prevailing prior to the beginning of project implementation whichever is<br />
higher<br />
6.4 <strong>HVPNL</strong> Environment and Social Policy and Procedures<br />
The ESPP of the company has been developed following consideration of all the mandatory<br />
requirements of the national and state policies and acts and also the guidelines of funding<br />
agencies in addressing the social and environmental issues arising out of its activities. The<br />
company is committed to identify, assess, and manage environmental and social concerns at<br />
both organization and project levels by strictly following the basic principals of avoidance,<br />
minimization and mitigation of environmental & social impacts with the improvement of<br />
Management Systems and introduction of State of the Art and proven technologies.<br />
The key principles of <strong>HVPNL</strong>’s social policy are:<br />
� Avoid any disruption of socially sensitive areas with regard to human habitation and<br />
areas of cultural significance;<br />
� Wherever losses are suffered, assistance will be provided to the affected persons to<br />
improve or at least regain their living standards;<br />
� Consultations will be held among local population regarding finalization of proposed<br />
route of the transmission lines and sub-stations;<br />
� Ensure in delivering R&R entitlements and compensation for lost assets based on<br />
<strong>HVPNL</strong>’s entitlement framework;<br />
� Involuntary resettlement will be avoided or minimized by exploring all viable<br />
alternative project designs;<br />
� All adversely affected persons including those without title to land will be provided<br />
Page 30
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
assistance to improve or regain their living standards to the pre project levels;<br />
� Special attention will be paid for the improvement of living standards of marginalized<br />
and vulnerable groups;<br />
� If any person’s remaining land holding becomes operationally non viable, the entire<br />
holding will be acquired and compensated accordingly, if the Affected Family (AF)<br />
desires. A similar approach will be adopted for structures affected partially;<br />
� Physical works will not commence on any portion of land before compensation and<br />
assistance to the affected population have been provided in accordance with the policy<br />
framework.<br />
6.5 Social Entitlement framework<br />
The prescriptive social entitlement framework derives from the aforementioned constitutional<br />
directives national R&R Policy, State R&R Policy and relevant policies. Physical<br />
displacement of people is not, and will not be, a major consequence of the company’s projects<br />
as has been the experience in the case with the other transmission companies. Regardless of<br />
displacement occurs, the entitlement framework will be a base for all its management<br />
procedures. The objective of the <strong>HVPNL</strong>’s framework is to ensure realistic rehabilitation and<br />
compensation of the acquired assets of the AFs covers categories such as Loss of Land<br />
(Homestead land, agriculture land, tenants, lease holders, encroachers/ squatters etc), Loss of<br />
structure ( with valid title, tenants, lease holders, squatters, cattle sheds, workshop sheds etc.),<br />
loss of livelihood, loss of standing crops/ trees, loss of access to Common Property Resources<br />
(CPR) and facilities, losses to host communities, Panchayat land and additional benefits for<br />
vulnerable person.<br />
For this package, entitlement provision applicable would be as per Clause 7 of the ESPP as<br />
per <strong>HVPNL</strong>’s social entitlement framework (see Table 6.1). In accordance with policy,<br />
compensation amounts have been computed at circle rates prevalent and are presented under<br />
Chapter 9 on Budget Estimates.<br />
Page 31
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Table 6.1 - <strong>HVPNL</strong>'s Social Entitlement Framework<br />
Sr.<br />
No.<br />
Type of Loss/ Impact Entitled Person/s Entitlement<br />
1. Loss of Land<br />
a) Homestead land with valid<br />
title, or customary or<br />
usufruct rights<br />
Titleholders<br />
i) Cash compensation as per LA Act<br />
1894<br />
ii) Actual registration charges for<br />
purchase of alternate land for<br />
maximum of compensation amount<br />
within one year as per proof of<br />
purchased land.<br />
iii) The land owners will be<br />
paid annuity for 33 years over and<br />
above the usual land compensation.<br />
The amount of annuity will be Rs.<br />
15,000/-per acre per annum on<br />
prorata basis. Annuity of Rs.<br />
15,000/- will be increased by a fixed<br />
sum of Rs.500/- every year as per<br />
State Government Policy.<br />
Vulnerable person Titleholders One time additional compensation of<br />
Rs.5000 per acre on prorate basis will be<br />
paid in addition to above entitlements.<br />
b) Agricultural Land<br />
(i) With valid title Titleholders i) Cash compensation as per LA Act<br />
1894<br />
ii) Actual registration charges for<br />
purchase of alternate land for<br />
maximum of compensation amount<br />
within one year as per proof of<br />
purchased land.<br />
The land owners will be paid annuity for<br />
33 years over and above the usual land<br />
compensation. The amount of annuity will<br />
be Rs. 15,000/-per acre per annum on<br />
prorata basis. Annuity of Rs. 15,000/-<br />
will be increased by a fixed sum of<br />
Rs.500/- every year as per State<br />
Government Policy.<br />
Vulnerable person Titleholders One time additional compensation of<br />
Rs.5000 per acre on prorate basis will be<br />
paid in addition to above entitlements.<br />
(ii) tenants, sharecroppers,<br />
leaseholder including the<br />
commercial and other<br />
establishments<br />
Individual with<br />
proof of<br />
tenancy/share<br />
cropping/leasing<br />
Vulnerable person Individual with<br />
proof of<br />
Reimbursement for unexpired<br />
tenancy/share cropping/lease period.<br />
Note: This amount will be deducted from<br />
the compensation payable to land owners.<br />
One time additional compensation of<br />
Rs.5000 will be paid in addition to above<br />
Page 32
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Sr.<br />
No.<br />
Type of Loss/ Impact Entitled Person/s Entitlement<br />
tenancy/share<br />
cropping/leasing<br />
entitlements.<br />
(iii) Encroacher/Squatters Occupant Assistance to be provided for inclusion in<br />
various Government Schemes.<br />
2. Loss of structure<br />
(i) with valid title, Structure owner<br />
Vulnerable person Structure owner<br />
(ii) Tenant, leaseholder<br />
(who have created the<br />
structure)<br />
Vulnerable person<br />
(who have created the<br />
structure)<br />
(iii) Tenant, leaseholder<br />
(Who have not created the<br />
structure)<br />
Vulnerable person<br />
(Who have not created the<br />
structure)<br />
Individuals/ Party<br />
with proof of<br />
tenancy/leasing<br />
Individuals/ Party<br />
with proof of<br />
tenancy/leasing<br />
Individuals/ Party<br />
with proof of<br />
tenancy/leasing<br />
Individuals/ Party<br />
with proof of<br />
tenancy/leasing<br />
i) Compensation as per Haryana PWD<br />
scheduled rates<br />
ii) One time financial assistance of<br />
Rs.10,000/- for shifting of family,<br />
building material, belongings and<br />
cattle etc.<br />
Affected Families will be allowed to<br />
dismantle structure and carry salvage<br />
whatever they can.<br />
One time additional compensation of<br />
Rs.5000 will be paid in addition to above<br />
entitlements.<br />
i.) Compensation as per Haryana<br />
PWD scheduled rates.<br />
ii) One time financial assistance of<br />
Rs.10,000/- for shifting of family,<br />
building material, belongings and cattles<br />
etc.<br />
iii) Affected Families will be<br />
allowed to dismantle structure and carry<br />
salvage whatever they can.<br />
iv) Reimbursement for unexpired<br />
tenancy/ lease period.<br />
Note: The amount at iv) will be deducted<br />
from the compensation payable to land<br />
owners.<br />
One time additional compensation of<br />
Rs.5000 will be paid in addition to above<br />
entitlements.<br />
Reimbursement for unexpired tenancy/<br />
lease period.<br />
Note: This amount will be deducted from<br />
the compensation payable to land owners.<br />
Additional compensation of Rs.2000 will<br />
be paid in addition to above entitlements.<br />
Page 33
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Sr.<br />
No.<br />
Type of Loss/ Impact Entitled Person/s Entitlement<br />
(iv) Squatters Structure<br />
(v) Cattle shed<br />
Owner/Family<br />
Vulnerable person Owner/Family<br />
(vi) Workshop sheds Owner/Family<br />
Vulnerable person Owner/Family<br />
3 Loss of livelihood<br />
i) Wage /Self employment<br />
(both agriculture and Non<br />
Agriculture)<br />
4 Loss of standing crops/ trees<br />
i) a) Crops<br />
b) Trees<br />
Each adult<br />
earning member<br />
(both men &<br />
women)<br />
Cultivator title<br />
holders<br />
5 Loss of access to Common Property Resources (CPR) and facilities<br />
i) Common property resources<br />
/ Civic amenities.<br />
6 Losses to host communities<br />
I. Compensation as per Haryana PWD<br />
scheduled rates.<br />
II. Assistance in shifting by providing<br />
transport charges to actual or<br />
Rs.10,000/- maximum.<br />
III. Affected Families will be allowed to<br />
dismantle structure and carry salvage<br />
whatever they can.<br />
Cash compensation of Rs. 15000/- for reconstruction<br />
of cattle shed.<br />
Additional compensation of Rs.1000 will<br />
be paid to head of family in addition to<br />
above entitlements.<br />
Cash compensation of Rs. 25000/- for reconstruction<br />
of workshop shed.<br />
Additional compensation of Rs.2000 will<br />
be paid to head of family in addition to<br />
above entitlements.<br />
Assistance to be provided for inclusion in<br />
various State Government Schemes for<br />
self-employment.<br />
In either category compensation for the<br />
total loss of crop/tree as per LA Act<br />
during construction as well as during<br />
O&M**.<br />
Community Replacement of CPRs/Civic amenities to<br />
ensure equivalent community resources<br />
and amenities or provisions of functional<br />
equivalence.<br />
i) CPR and Civic amenities Community Augmentation of resources of host<br />
community to sustain pressure of AFs.<br />
Page 34
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Sr.<br />
No.<br />
Type of Loss/ Impact Entitled Person/s Entitlement<br />
7 Panchayat land Village<br />
Panchayat<br />
8. Other Impacts related to loss<br />
of assets/ livelihood not<br />
identified.<br />
9. Title holders affected by<br />
Transmission towers In<br />
urban/ rural areas<br />
Compensation as per State Government<br />
Policy.<br />
AFs Unforeseen impacts should be<br />
documented and mitigative measures have<br />
to be proposed with in the overall<br />
principles & provisions of ESPP.<br />
Title holders Compensation as per “Works of licensees<br />
Rules 2006” notified by GoI on dated<br />
18.4.2006.<br />
Note: *Vulnerable person means the people below poverty level, widow, physically handicap and SC/ ST.<br />
** compensation of damage to crops/trees during O&M would be paid within one month<br />
Cut Off dates<br />
For the non-titleholders the cut-off date will be the date of census survey conducted as part of<br />
the socio-economic survey and for titleholders it will be the date of issuance of Section 4 (1)<br />
notice under the LA Act.<br />
Public Disclosure, Consultation, and Participation<br />
Public consultation has been incorporated as an integral part of the process throughout the<br />
planning and execution of project. The Environment and Social Management Team (ESMT)<br />
will interact closely with PAPs, host communities, project personnel, government<br />
departments, NGOs right from the early stages of the project preparation on regular basis for<br />
developing and implementing the RAP and EMP.<br />
During implementation the public contact drives have been envisaged by bringing in active<br />
NGOs in the affected area. The first step of public awareness program is the publication of the<br />
public notification in the local newspapers as per the Section 29 of the Electricity (Supply)<br />
Act, 1948 in which details of the proposed project are given. The objections are to be filed<br />
within a period of 60 days from the date of publication of notification. The next step of the<br />
program is holding of the meetings and discussions with the public during the reconnaissance<br />
survey and again during the detailed survey/tower spotting.<br />
Page 35
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER – 7: COMPENSATION AND ASSISTANCE<br />
7.1 Introduction<br />
This chapter deals with the mitigation measures commensurate to the loss of the property.<br />
Besides, it elaborates on any assistance that could be provided to the affected village.<br />
7.2 Compensation and assistance for Nevada Tigaon<br />
The impact of the project resulting in loss of land has no adverse impact on the village. On<br />
the contrary, as details in the previous chapters show that this transaction would actually help<br />
the village economy. In other words, impact is entirely positive.<br />
As per the resolution passed by Nevada Tigaon village, land shall be provided at circle rates.<br />
compensation for panchayat land shall be as per clause 7 of ESPP. As confirmed by the<br />
district officials, the circle rate for land in Faridabad district is Rs. 12.5 lakhs/acre. This shall<br />
form basis for calculation of the compensation amount for the 33 acres of land at Nevada<br />
Tigaon village.<br />
7.3 Compensation and assistance for Nuhianwali<br />
The land transaction details indicate that land has been donated with the expectation of better<br />
power supply and no preconditions are attached. Interactions with Officials indicate that the<br />
land was donated via resolution passed – on 29 th December 2007 and currently the papers are<br />
being processed.<br />
As per the resolution passed by Nevada Tigaon village, land shall be provided at circle rates.<br />
Compensation for panchayat land shall be as per clause 7 of ESPP. As confirmed by the<br />
district officials, the circle rate for land in Sirsa district is Rs. 3.5 lakhs/acre. This shall form<br />
basis for calculation of the compensation amount for the 52.425 acres of land at Nuhianwali<br />
village.<br />
In this context, it is to be noted that any conditions laid down by the panchayat such as<br />
provision of power supply equivalent to supply in towns, etc., must be recorded in the<br />
contract agreement with <strong>HVPNL</strong>.<br />
Page 36
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER – 8: INSTITUTIONAL ARRANGEMENTS AND GRIEVANCE<br />
REDRESSAL MECHANISMS<br />
8.1 Introduction<br />
This section deals with the institutional arrangement and grievance redressal mechanisms as<br />
enunciated in the ESPP of <strong>HVPNL</strong>. These would be applicable to all the sub-stations and<br />
transmission lines that get funded under this proposed World Bank project.<br />
8.2 Institutional Framework<br />
The company will have three levels of Institutional bodies to oversee and implement ESPP.<br />
The bodies are constituted at Head Quarter level; Zonal level; and Divisional Level.<br />
At Head Quarter Level: Environment, Resettlement and Rehabilitation Committee (ER&R)<br />
under the chairmanship of the Director Technical includes the concerned Chief Engineer/TS<br />
and CE/P&D HVPN, Panchkula and Deputy Secretary/Projects as the Committee members.<br />
Deputy Secretary/Projects will be the Member Secretary of the R&R committee.<br />
At Zonal Level: The Environment and Social Monitoring Committee (ESMC) constitute of<br />
concerned Chief Engineer/TS , concerned Superintendent Engineer/TS, concerned Executive<br />
Engineer/TS, Land Acquisition officer and two representatives of the AFs and ESMC would<br />
report to Director Technical, <strong>HVPNL</strong>, Panchkula.<br />
At Divisional Level: In addition to above, Environment and Social Implementation unit<br />
(ESIU) will be there consisting of Executive Engineer/TS and SSE/SDO/Construction of<br />
concerned place.<br />
The role and functions of the ER&R, ESMC and ESIU include but are not limited to:<br />
� Coordinate among the various agencies involved in implementation of the ESPP<br />
programs<br />
� Monitor and review implementation of the ESPP plans<br />
� Function as a grievance redressal body; and<br />
� Provide overall guidance and leadership for smooth implementation of the<br />
resettlement and rehabilitation plans<br />
Page 37
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
To ensure effective implementation of ESPP, <strong>HVPNL</strong> focuses on<br />
1. strengthening the implementation of the ESPP by redeployment of appropriately<br />
trained persons at key levels;<br />
2. reinforcing in house capabilities by working with specialized external agencies; and<br />
3. reviewing progress of the ESPP internally or through external agencies<br />
8.3 Social Procedures<br />
<strong>HVPNL</strong> has developed comprehensive Environmental and Social (E&S) Management<br />
Procedures and incorporated them to its project cycle, to ensure that its operation eliminates<br />
or minimizes adverse environmental and social impacts. The E&S management procedures<br />
identifies the relevant issues at early stages of project cycle and follow the basic philosophy of<br />
sustainable development through Avoidance, Minimization and Alleviation.<br />
<strong>HVPNL</strong>’s project cycle forms the operational framework and background through which the<br />
environment & social issues are addressed. Key milestones in <strong>HVPNL</strong>’s transmission projects<br />
include project conceptualization; planning; approval; design; tendering; implementation and<br />
operation; and maintenance.<br />
8.3.1 Project Conceptualization<br />
During project conceptualization, <strong>HVPNL</strong> identifies the project. Identification of a power<br />
transmission project is on the basis of demand and supply in regions and links between new<br />
power generating projects and availability of state’s quota of power from the POWERGRID.<br />
<strong>HVPNL</strong> carries out feasibility studies encompassing demand for energy, prioritizing for<br />
different sectors and regions, environmental and social impact assessment; economic and<br />
financial analysis; and an implementation schedule. During feasibility studies, <strong>HVPNL</strong><br />
identifies and weight various line options on a survey map such that there is shortest distance<br />
between origin of the proposed transmission line and the substations sites. At all times, while<br />
considering line options, <strong>HVPNL</strong> keeps in view its policy of avoidance of socially (including<br />
environmentally) sensitive areas.<br />
8.3.2 Project Planning<br />
During project planning, <strong>HVPNL</strong> carries out a Reconnaissance survey. A number of<br />
alternatives are studied to minimize possible social impacts of transmission line. The planning<br />
exercise also ensures that the route does not involve human habitation and areas of cultural<br />
importance. Field officers verify critical issues e.g. river, hill, railway crossings; power and<br />
Page 38
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
telephone lines etc. and finalize the optimal route on the map. Once the route is finalized,<br />
<strong>HVPNL</strong>, will carry out a Environment & Social Assessment with its own field staff and<br />
prepare a Environment & Social Impact Assessment. Based on the assessment and the<br />
provisions under ESPP, <strong>HVPNL</strong> will formulate an EMP (Environment Management Plan &<br />
Resettlement Action Plan (RAP) in consultation with AFs.<br />
<strong>HVPNL</strong> considers various sites for substations. On the basis of data for various parameters<br />
considered during selection process, a comprehensive analysis for each alternative site will be<br />
carried out. Weightage will be given to various parameters for finalizing alternative sites<br />
which are often site specific. Due consideration is given to availability of infrastructure<br />
facilities such as access roads, railheads etc. type of land viz. government, revenue, private,<br />
agriculture, environment and social impacts such as number of families affected as well as<br />
cost of compensation and rehabilitation.<br />
8.3.3 Operation and Maintenance<br />
<strong>HVPNL</strong> continuously monitors the transmission lines and substations. The lines are patrolled<br />
regularly to identify any defects in the components. Monitoring of the line is carried out by<br />
the respective <strong>HVPNL</strong> field offices.<br />
8.3.4 Project Review<br />
The social components of the project will be reviewed by the ESMU of <strong>HVPNL</strong> on regaular<br />
basis.<br />
8.4 Capacity Building<br />
Training and development of employees is integral to implementation of ESPP. In the<br />
beginning, training would be imparted to the executive/non-executive from NPTI/PGCIL so<br />
as to enable them to understand the ESPP document, to take necessary steps in right time to<br />
implement.<br />
It is recommended that the <strong>HVPNL</strong> carries out periodic orientation and refresher courses that<br />
comprise of social and environmental issues applicable to such projects. Content of these<br />
courses should also comprise of the mitigation measures that are required to be adopted in the<br />
case of sub-stations and transmission line projects.<br />
Page 39
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
8.5 Grievance Redress Mechanism<br />
It is expected that through a participatory process and good compensation and support<br />
mechanisms, acceptance of the project will be enhanced and complaints reduced. In case of<br />
issues related to land acquisition, the LA Act provides adequate provisions at different stages<br />
of the LA process for the AFs to object to the proposed acquisition of land and other<br />
properties, compensation rates, etc. The LA Act also allows the affected persons to receive<br />
the compensation under protest and then refer the case to the court for settlements. However<br />
ESMC at the Zonal Level will hear complaints and facilitate solutions. If the grievance is not<br />
redressed at zonal level, the affected person can appeal to the Environment R&R committee at<br />
Corporate level. He/she can further appeal to the court if his/her grievance is not redressed at<br />
either zonal or corporate level.<br />
In addition to the proposed grievance redressal under the ESPP, it is recommended that<br />
another level of grievance redressal be added at the Division level to help record complaints.<br />
The advantage of such a mechanism would be receive, and forward it to the ESMC at Zonal<br />
level for redressal. Past experiences in other such and other infrastructure projects too<br />
indicate handling of issues at lowest possible level have proved more effective than if they are<br />
let to scale up.<br />
Page 40
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Organizational Structure for ESPP<br />
C<br />
NGO contract (only a Nevada)<br />
Lump<br />
sum<br />
Sub Total<br />
Contingency<br />
Contingency SE/ TS<br />
XEN/ TS<br />
amount @ 10 % of total<br />
amount Concerned<br />
Concerned<br />
Sub Total<br />
Grand Total (A+B+C)<br />
CE/ TS Concerned<br />
Member<br />
ER&R High Powered Committee at HQ level<br />
Director/ Technical<br />
Chairman<br />
Deputy Secy/ Projects<br />
Member Secy.<br />
(Nodal Officer)<br />
Environment Social management Committee (ESMC) at Zonal level<br />
CE/ TS Concerned<br />
Chairman<br />
LAO Two<br />
representatives<br />
AFs<br />
Environment & Social Implementation Committee (ESIU) at Division level<br />
XEn/ TS<br />
Concerned<br />
CE/ P&D Member<br />
SSE/ SDO<br />
construction<br />
concerned<br />
Complaint<br />
recorded at<br />
this level<br />
Page 41
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER – 9: BUDGET ESTIMATES<br />
9.1 Introduction<br />
This chapter presents the budget estimates for this package. The costs used for the budget are<br />
based on information collected during the site from the revenue department. The budget is<br />
based on the entitlement matrix as given in the ESPP.<br />
9.2 Budget and Costs (Nevada Tigaon and Nuhianwali)<br />
Since this package involves land acquisition for both the substations, the land rates have been<br />
taken as prevalent in respective tehsils where the substations are located i.e. circle rate. Land<br />
rates as obtained are given in Table 9.1. (See Annexure<br />
Name of the Village Nature of Land/ Barren Per acre costs<br />
Nevada Tigaon Barren land 12.5 lacs/acre<br />
Nuhianwali Barren land 3.5 lacs/acre<br />
Separate budgets for the <strong>RRAP</strong> of the two sub-stations are presented in Table 9.2 and 9.3<br />
below. This includes cost of land for both substations and contingency for any unforeseen<br />
situations.<br />
Sl.<br />
No.<br />
Table 9.2 : Estimated Budget for Nevada Tigaon Sub-station<br />
Item Unit Quantity<br />
(in<br />
acres)<br />
Compensation for land<br />
Cost/unit<br />
(In Rs.)<br />
A Panchayat land<br />
Acre 33 12.5 lakhs<br />
(Nevada Tigaon)<br />
per acre<br />
B Contingency amount @ 5 % of total amount<br />
Grand Total (A+B)<br />
Financed by<br />
World<br />
Bank<br />
(Rs)<br />
Rupees Four Crores Thirty Three Lakhs Twelve Thousand Five Hundred only<br />
<strong>HVPNL</strong>(Rs)<br />
41250000<br />
2062500<br />
43312500<br />
Page 42
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Sl.<br />
No.<br />
Table 9.3 : Estimated Budget for Nuhianwali Sub-station<br />
Item Unit Quantity<br />
(in<br />
acres)<br />
Compensation for land<br />
A Panchayat land<br />
(Nuhianwala)<br />
B<br />
Contingency amount @ 5 % of total amount<br />
Cost/ unit<br />
(In Rs.)<br />
Acre 52.425 3.5 lakhs<br />
per acre<br />
Financed by<br />
World<br />
Bank<br />
(Rs)<br />
<strong>HVPNL</strong>(Rs)<br />
18348750<br />
917437.50<br />
Total (A+B) 19266188<br />
Rupees One Crore Ninety Two Lakhs Sixty Six Thousand One Hundred and Eighty Eight<br />
Only<br />
The total budget for both sub-stations under Package G-1, is Rs. 6,25,78,687 (Rupees Six<br />
Crores Twenty Five Lakhs Seventy Eight Thousand Six Hundred and Eighty Seven<br />
only)<br />
However, the resolution passed by the Nevada Panchayat states that the Panchayat will give<br />
this land as per the circle rate. In addition, the resolution mentions the demand of the<br />
Panchayat for 24 hrs electricity supply to this village. The resolution passed by the<br />
Nuhianwali Panchayat mentions donation of the piece of identified land with a precondition<br />
that the village will get the supply equivalent to that of the town. This clearly indicates their<br />
perception about how they are being deprived of the uninterrupted electricity supply.<br />
Page 43
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
CHAPTER – 10: IMPLEMENTATION SCHEDULE<br />
10.1 Introduction<br />
The outcomes of this <strong>RRAP</strong> depend upon quality of implementation. This chapter deals with<br />
the implementation schedule for the <strong>RRAP</strong> for the proposed sub-stations at the villages of<br />
Nevada Tigaon and Nuhianwala.<br />
10.2 Implementation issues and Schedule<br />
Key issues in implementation are likely to be the following:<br />
(i) Timely processing of resolution/contract agreement between <strong>HVPNL</strong> and village<br />
and transfer of land<br />
(ii) Release of funds as per agreement for the first year and also for subsequent<br />
years.<br />
Another recommended, but not mandatory measure would be for <strong>HVPNL</strong> to hold a<br />
consultation meeting with all the members of the villages following processing of resolution<br />
and prior to commencement of construction works. This meeting could provide information<br />
such as duration of constructions, potential disruptions to access roads, etc. They could take<br />
the opportunity to disseminate information on safety norms applicable and grievance<br />
mechanisms available for recording of complaints, if any. These continued consultations shall<br />
help continue the good rapport built already and also understand and suitably address any<br />
changed perceptions of the people of the affected villages.<br />
The breakdown of each activity according to a specific time frame has been provided in the<br />
Implementation Schedule. Implementation Schedule will require detailed coordination<br />
between the project authority – <strong>HVPNL</strong> and other relevant line departments. Implementation<br />
plan has been spread over a period of two years in respect of these two sub-stations that are<br />
expected to complete in terms of construction and running.<br />
The table below indicates the implementation schedule in case of land being donated by<br />
Panchayat. The total implementation period is likely to be only more than 2 months from the<br />
start date of the project. Employment opportunities, if any are likely shall be on continuous/<br />
continual basis.<br />
Page 44
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Week<br />
Activity<br />
Processing of<br />
Resolution<br />
Transfer of land<br />
Release of funds<br />
Table 10.1 – Implementation Schedule<br />
Wk 1 Wk 2 Wk 3 Wk 4 Wk 5 Wk 6 Wk 7 Wk 8 Wk 9 onwards<br />
Page 45
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure -1A: Photographs and Layout Map of proposed site at NevadaTigaon.<br />
Page 46
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 47
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure -1B: Details of Land Transfer of proposed site at Nevada Tigaon.<br />
Page 48
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 49
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 50
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 51
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure -1C: Details of Stakeholder Consultations for Sub-Station at Nevada Tigaon.<br />
Focus Group Discussion with key members at Nevada Tigaon<br />
Name of the Village Nevada Tigaon<br />
Date December 12, 2008<br />
Venue Sarpanch House<br />
No. of Persons attended: 8 persons<br />
FGD Conducted by Srihari and Neha<br />
Start and End Time 11.00 am - 12.00 noon<br />
Objectives:<br />
� inform villagers about the proposed sub-station<br />
� to understand their overall socio-economic condition<br />
� to elicit their views and perceptions on project<br />
Issues discussed:<br />
Village and household composition: The village has approximately 500 households with a<br />
total population of approximately 3000. In terms of household composition, it is 7-8<br />
members per household. 12-14 BPL households are there<br />
Land donation: The village has a total of 250 acres of village land and another 200 acres of<br />
panchayat uncultivable The panchayat has donated this barren panchayat land of 33 acres for<br />
the sub-station. Besides community land such as the donated piece, the panchayat had another<br />
250 acres, of which it has already donated 113 acres to MIT (a technology institute) and<br />
another 33 acres for other purposes<br />
Land use: Agricultural land on which crops such as mustard, wheat and paddy are grown.<br />
Also vegetables such as Tomato, Raddish are grown, besides, sugarcane. The produce is<br />
marked in the mandis of Ballabgarh<br />
Occupation: Farming is the main occupation. Unemployment is high with more than 100+.<br />
Girls also work in nearby town. Under NREGA work was available though village persons<br />
feel some shame in working in their own village but are okay to work outside in factories.<br />
Free education, free books, lab fees and 2000-3000 rupees are provided under the Haryana<br />
government education scheme. Training centre is available too from NTPC and courses for<br />
beauty parlour, sewing are provided<br />
Electricity status is available for approximately 6 hours during day time and then again from<br />
7.00 pm to 2.00 am, and this meant that total supply during a day is around 10-12 hours a day<br />
Medical facilities: Besides, a dispensary is close by there are doctor and nurses who once or<br />
twice in a week come to the village to attend to their when called.<br />
Education: School upto middle is around in the vicinity of the village. 15-20 people in the<br />
villages are graduates, in addition to 2-4 who are metric and also there are many plus 2<br />
students. Girls of the current generation are all being educated.<br />
Water Supply: Irrigation is an issue, particular when electricity is not available effectively<br />
Page 52
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Water level low, though tubewells are there. Handpumps have been installed in the village<br />
Sanitation: Toilets are there too under different government schemes and nearly all<br />
households have toilets in the vicinity.<br />
Enhancements to the village road are likely once the sub-station comes up. Also facilities like<br />
a couple of shops too shall materialize too.<br />
Outcomes: More reliable power supply is required for the village and for which the land has<br />
been donated. Overall development as a result of the sub-station too is expected in terms of<br />
employment opportunities are expected<br />
Page 53
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Focus Group Discussion with women<br />
Name of the Village Nevada Tigaon<br />
Date December 12, 2008<br />
Venue Sarpanch House<br />
No. of Persons attended: 10 persons<br />
FGD Conducted by Neha<br />
Start and End Time 11.00 am - 12.00 noon<br />
Objectives:<br />
� inform villagers about the proposed sub-station<br />
� to understand their overall socio-economic condition<br />
� to elicit their views and perceptions on benefits from the better power supply<br />
Issues discussed:<br />
Education: Girls of the current young generation are being sent to school while of the older<br />
generation a handful are educated and in fact are employed in government service outside the<br />
village in places like Sohna.<br />
Health: Dispensary is nearby and also lady doctor if required is available.<br />
Employment: all of them do either household work or work in the fields.<br />
Perception on the project: Women members in particular revealed that they would wish to<br />
pursue certain courses such as beauty and sewing courses. However, when they have to<br />
pursue courses such as these, manual labor for their homes such as threshing etc. takes up lot<br />
of their time. Also this in view, causes a lot of hardship. Besides, these few issues there are<br />
not any major issues that they had to report. Overall expectations of development as a result<br />
of the sub-station too were high.<br />
Outcomes: better power supply would help to alleviate some of burden of domestic work and<br />
the project of the proposed sub-station is welcome<br />
Page 54
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 55
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure -2A: Layout Map and Photographs of proposed site at Nuhianwali<br />
Page 56<br />
.
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 57
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure -2B: Details of Land Transfer of proposed site at Nuhianwali.<br />
Page 58
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 59
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 60
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 61
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure -2C: Details of Stakeholder Consultations for Sub-Station at Nuhianwali.<br />
Focus Group Discussion with key members<br />
Name of the Village Nuhianwali<br />
Date December 9, 2008<br />
Venue Sarpanch House<br />
No. of Persons attended: 30 persons<br />
FGD Conducted by Sarika and Chandrani<br />
Start and End Time 11.00 am - 12.00 noon<br />
Objectives:<br />
� inform villagers about the proposed sub-station<br />
� to understand their overall socio-economic condition<br />
� to elicit their views and perceptions on project<br />
Issues discussed:<br />
1. Majority of the consulted stakeholders perceived that the project would have positive<br />
impact on the village<br />
2. The present intermittent supply of electricity is hampering the agricultural productivity<br />
of the region. The consistent supply of electricity would lead to development of new<br />
agricultural technique which in turn would increase the productivity in the village<br />
3. The consistent supply of electricity would have a positive impact on the education of<br />
children which is deprived off in the present situation<br />
4. Small scale and household industries would get a positive impetus for growth which<br />
are presently suffering on account of present electricity situation in the village<br />
5. It was reveled that majority of the villages receive only 5-6 hrs of electricity supply<br />
thus leading to inconsistent and inadequate water supply<br />
6. Household works like ironing, refrigeration etc would also get a positive impact due<br />
the project<br />
7. The intermittent electric supply has led to installation of diesel gensets at major places,<br />
this is not only having a negative impact of the environment but is also hampering the<br />
economics of the village as the cost of power from these diesel genset is much higher<br />
than the normal electric supply<br />
8. Consistent electric supply would lead to increased industrial and agricultural<br />
production thereby leading to increased employment options and overall economic<br />
development.<br />
Outcomes: More reliable power supply is required for the village and for which the land has<br />
been donated. Overall development as a result of the sub-station too is expected in terms of<br />
employment opportunities are expected<br />
Page 62
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 63
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure - 3: Consultation Checklist<br />
CONSULTATION CHECKLIST<br />
Name of the Village/Panchayat<br />
Date<br />
Venue<br />
No. of Persons attended:<br />
Start and End Time<br />
Issue Covered<br />
Yes No<br />
Information about the project<br />
Details on the Sub-station (KV, coverage of area)<br />
Duration of construction for Sub-station<br />
Site Specifications of Sub-station (type of land on sub-station is sited)<br />
Safety Issues<br />
Restrictions on land use in and around the sub-station<br />
Social impacts<br />
Loss of land (for substation), structures and other community property resources such as<br />
playground<br />
Temporary Loss of access to road, etc.<br />
Temporary loss of income<br />
Impact on Water situation due to supply for the sub-station<br />
Enhancement (or if any deprivation) of features of the area around sub-station<br />
Page 64
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Mitigation Measures<br />
� Compensation for land (and substation) and structures<br />
� Provision of compensation of lost trees and CPRs<br />
Work Opportunities<br />
� Provision of temporary (or permanent) employment opportunities, if any<br />
Page 65
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure - 4: Census/Socio Economic Survey Questionnaire<br />
Date<br />
Investigator Name Supervisor Name<br />
Type of Household<br />
General<br />
SC<br />
Type of the Use<br />
HARYANA POWER PROJECT<br />
Census/Socio Economic Survey Questionnaire<br />
(Note: Provide a sketch of the property on Page 4 of this questionnaire.)<br />
A. IDENTIFICATION<br />
A.1 General Identification.<br />
A.2 Type of Property<br />
Private<br />
2 0 0<br />
Government<br />
Respondent Name AC/BC<br />
Trust Community Others<br />
1 2 3 4 5<br />
A.3 Ownership<br />
A.3.1 Do you own the structure/ plot/ agriculture land?<br />
Identification Number<br />
ST OBC Women headed<br />
household<br />
1 2 3 4 5 6<br />
/ /<br />
Road No Side Number<br />
BPL* If BPL, card NoBPL*<br />
Residential<br />
Open Land/Plot<br />
School<br />
1<br />
4<br />
7<br />
Commercial<br />
Plantation/ Orchard<br />
PHC/Hosp./Dispensary.<br />
2<br />
5<br />
8<br />
Residential cum Commercial<br />
Graveyard<br />
Industrial<br />
3<br />
6<br />
9<br />
No<br />
Storeys<br />
G<br />
of<br />
1<br />
Mazar 10 Temple 11 Masjid 12 G+1 2<br />
Church 13 Shrine 14 Vill Com/ Panchyat/Government Land 15 G+2 3<br />
Agriculture 33 Waste/ Grazing/ Barren 17 Others (specify) 99<br />
State District<br />
Owner<br />
Block Town//Village<br />
1. Tenant 2. Encroacher 3. Squatter 4. Share Cropper 5<br />
A.3.2 Occupiers Name ___________________________S/o__________________________<br />
A.3.3 Name, Address, Phone Number and LANDMARK __________________________________<br />
_____________________________________________________________________________________<br />
A.3.4 If Tenant, Name and Address and Contact Number of the Owner ____________________<br />
_____________________________________________________________________________________<br />
Page 66
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
A.3.5 Please provide with an ID Proof (Ration card, Voter Id, PAN Card, Driving Licence, any ONE)<br />
Record the details.<br />
_______________________________________________________________________________<br />
A.4 Utilities on the Property<br />
Sl.No Utilities Unit(s) owned Sl.No Live Stock Asset Numbers<br />
1. Trees 1. Cow<br />
2. Dug wells 2. Buffalo<br />
3. Tube wells 3. Sheep<br />
4. Lift Irrigation Points 4. Goat<br />
5. Water Tap 5. Pig<br />
6. Water Tank 6. Poultry<br />
7. Hand Pump 7. Pond Others (Mention)<br />
8. Cattle Shed<br />
9 Water supply<br />
pipeline<br />
10 Boundary wall<br />
11 Barbed wire fence<br />
12 Pond<br />
13 Others (SP)<br />
A.5 Trees that are likely to be affected<br />
Tree type<br />
Height of<br />
tree<br />
Distance<br />
from<br />
tower<br />
base<br />
1. Mango 2. Mulberry, 3. eucalyptus, 4. pine, 5. kikar, 6. shisham and 7. babul<br />
A.6 Typology of the Main Structure<br />
Wall<br />
Roof<br />
Floor Boundary No of Rooms<br />
RCC/RBC 1 Brick 1 Concrete 1 Brick 1<br />
Thatched<br />
2<br />
Wood<br />
Plastic<br />
2<br />
Mud<br />
2<br />
Barbed<br />
Wire<br />
2<br />
Mud 3 Mud 3 Stone 3 Wood 3<br />
GI /<br />
Asbestos<br />
4<br />
Asbestos<br />
4<br />
Others<br />
9<br />
Others<br />
9<br />
Bamboo 5 Others 9<br />
Others 9<br />
B. Structural Details<br />
B.1.1 How old is the structure?<br />
(Mention the Year since you are operating from this structure)<br />
B.1.2. How long are you residing or operating from the structure?<br />
B.1.3 Measurement of the Land (in mts)<br />
Length:<br />
Breadth: Total<br />
Area:<br />
Impacted area Remarks if any<br />
Page 67
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
B.1.4 Measurement of the Structure/Asset<br />
Length: Breadth: Height Total area<br />
of the<br />
structure<br />
Total<br />
Impacted<br />
area of<br />
the<br />
structure<br />
Remarks if any<br />
B.1.5 What type of business are you doing, in case of commercial use?<br />
1. Tea Stall 8. Kabari Shop 15. Motel<br />
2. Grocery/General/KiranaStore 9. Educational institution 33. Butcher/meat<br />
3. Vegetables/ Fruits 10. Hotel/ Restaurant 17. Barber Shop<br />
4. Cloth/Garments 11. Electrical 18. Medicine Shop<br />
5. Tailor shop 12 Furniture 19 Wine Shop<br />
6. Pan/ Cigarette Shop 13 Petrol Pump 20 Phone/Photocopy shop<br />
7. Garage/ Mechanic Shop 14. Lubricant Shop 99. Any other, please specify<br />
B.1.6 Is your business self owned? 1 -Yes / 2 - No<br />
B.1.7 How many people have you employed? (number)<br />
B.1.9 Where would you prefer to move from here ? (Residential and Commercial Both )<br />
S No Place Where (specify) Distance in Kms from current<br />
location<br />
1 Within the Village/ Town<br />
2 Outside the Village / Town<br />
B.1.10 Do you have any alternative land /structure? 1 - Yes / 2 - No<br />
B.1.11 If Yes, where?<br />
Place (specify) Distance in Kms from existing<br />
B.2. Agricultural Details<br />
B.2.1 Do you have agricultural land? 1 - Yes / 2 - No<br />
B.2.2 Type of Land 1. Irrigated 2. Un-irrigated 3. Waste Land 9. Other (Specify)<br />
B.2.3 What Crops you Grow ? 1. Rice 2. Maize 3. Tea 4. Wheat 5. Vegetables 6. Fruits 7. Bamboo<br />
9. Others (Specify)__ ___________________<br />
B.2.4 For how many years the Land being cultivated by you / your ancestors ____<br />
C.1. Household Details<br />
C.1.1. Caste details<br />
C.1.2. Type of Family<br />
C.1.2. No. of Persons in Household.<br />
ST (hills) ST<br />
(Plain<br />
)<br />
SC MOBC OBC General<br />
1 2 3 4 5 6<br />
Others Specify the Caste Group<br />
9<br />
Nuclear Joint Extended Sibling<br />
1 2 3 4<br />
Above 15 yrs Below 15 yrs<br />
Page 68
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Codes for Relationship<br />
1 Head of the House Hold 2 Wife 3 Husband 4 Son<br />
5 Daughter 6 Son-in-law 7 Daughter-in-law 8 Grandfather<br />
9 Grandmother 10 Grandson 11 Grand daughter 12 Grandson-in-law<br />
13 Grand daughter-in-law 14 Brother 15 Sister 33 Brother-in-law<br />
17 Sister-in-law 18 Father 19 Mother 20 Father-in-law<br />
21 Mother-in-law 22 Uncle 23 Aunt 24 Cousin<br />
25 Nephew 26 Niece 27 Any other (specify)<br />
C.2. Family Profile. (Start from Head of the Household)<br />
Member<br />
Number<br />
C.2.1 Name<br />
C.2.2<br />
Relationship<br />
C.2.3 Sex<br />
C.2.4 Age<br />
C.2.5 Marital<br />
Status<br />
C.2.6<br />
Education<br />
C.2.7<br />
Health<br />
1 2 3 4 5 6 7 8 9 10 11 12<br />
Write down the<br />
names of all person<br />
who live and eat<br />
together in this<br />
household starting<br />
with head exclude<br />
persons under the<br />
age of 14 years.<br />
HH<br />
Codes<br />
above<br />
as given<br />
Is the NAME male or female?<br />
1 1 1 1<br />
2 2 2 2<br />
1<br />
2<br />
1<br />
2<br />
1<br />
2<br />
1<br />
2<br />
1<br />
2<br />
1<br />
2<br />
1<br />
2<br />
1<br />
2<br />
Male<br />
Female<br />
How old was NAME on the last birthday?<br />
Record the age on<br />
last birthday<br />
1 1 1 1 1 1 1 1 1 1 1 1 Married<br />
2 2 2 2 2 2 2 2 2 2 2 2 Unmarried<br />
3 3 3 3 3 3 3 3 3 3 3 3 Divorced<br />
4 4 4 4 4 4 4 4 4 4 4 4 Separated<br />
5 5 5 5 5 5 5 5 5 5 5 5 Widow/Widower<br />
The class till which the person has been educated.<br />
1 1 1 1 1 1 1 1 1 1 1 1 Illiterate<br />
2 2 2 2 2 2 2 2 2 2 2 2 Primary (class 4)<br />
3 3 3 3 3 3 3 3 3 3 3 3<br />
Secondary (Class 5<br />
- 10)<br />
4 4 4 4 4 4 4 4 4 4 4 4 Higher (graduate)<br />
5 5 5 5 5 5 5 5 5 5 5 5 Technical<br />
6 6 6 6 6 6 6 6 6 6 6 6 Vocational<br />
1 1 1 1 1 1 1 1 1 1 1 1 Handicap by birth<br />
2 2 2 2 2 2 2 2 2 2 2 2<br />
Handicap due<br />
other reasons<br />
to<br />
3 3 3 3 3 3 3 3 3 3 3 3<br />
Any other chronic<br />
health problems<br />
D.1. Employment Status of the Family Members<br />
D.1<br />
Is the NAME working?<br />
Employment 1 1 1 1 1 1 1 1 1 1 1 1 Yes<br />
Status<br />
2 2 2 2 2 2 2 2 2 2 2 2 No<br />
The occupational activity at the place of job? This may have<br />
multiple entries<br />
1 1 1 1 1 1 1 1 1 1 1 1 Agriculture<br />
2 2 2 2 2 2 2 2 2 2 2 2 Agri Labour<br />
D.2<br />
Occupation<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
3<br />
4<br />
5<br />
Non Agri Labour<br />
Business/Trade<br />
Government<br />
Service<br />
6 6 6 6 6 6 6 6 6 6 6 6 Private Service<br />
7 7 7 7 7 7 7 7 7 7 7 7 Maid Servant<br />
9 9 9 9 9 9 9 9 9 9 9 9 Others<br />
What was the main reason for the NAME not working?<br />
To be<br />
persons<br />
filled<br />
who<br />
for<br />
are<br />
D.3 Non-<br />
not working.<br />
Working 1 1 1 1 1 1 1 1 1 1 1 1 No work available<br />
Status<br />
2 2 2 2 2 2 2 2 2 2 2 2 Seasonal inactivity<br />
3 3 3 3 3 3 3 3 3 3 3 3<br />
Household<br />
duties<br />
family<br />
Page 69
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
D.4 Income<br />
D.5 Skills<br />
D.6 Household Expenditure<br />
4 4 4 4 4 4 4 4 4 4 4 4 Old/young<br />
5 5 5 5 5 5 5 5 5 5 5 5 Handicapped<br />
6 6 6 6 6 6 6 6 6 6 6 6 Student<br />
9 9 9 9 9 9 9 9 9 9 9 9 Others<br />
How much does the NAME earn in a month?<br />
1 1 1 1 1 1 1 1 1 1 1 1 Less than Rs.2000<br />
2 2 2 2 2 2 2 2 2 2 2 2 Rs.2000 – 3000<br />
3 3 3 3 3 3 3 3 3 3 3 3 Rs. 3000 - 4000<br />
4 4 4 4 4 4 4 4 4 4 4 4 Above Rs 4000<br />
What type of skill possessed by the person?<br />
1 1 1 1 1 1 1 1 1 1 1 1 Computer<br />
2 2 2 2 2 2 2 2 2 2 2 2 Weaving<br />
3 3 3 3 3 3 3 3 3 3 3 3 Typing<br />
4 4 4 4 4 4 4 4 4 4 4 4 Mechanic<br />
5 5 5 5 5 5 5 5 5 5 5 5 Driving<br />
6 6 6 6 6 6 6 6 6 6 6 6 Others (specify)<br />
7 7 7 7 7 7 7 7 7 7 7 7 None<br />
Item Amount<br />
1 Food<br />
2 Cooking Fuel<br />
3 Clothing<br />
4 Transport<br />
5 Health Care/Medicines<br />
6 Education<br />
7 Electricity/Utilities<br />
8 Social events<br />
9 Agriculture (Labor/ Tools)<br />
10 Seeds/Fertilizers/Pesticides<br />
11 Water<br />
12 Deisel Generator<br />
13 Others<br />
D.7 Have you availed of benefit under any Government Scheme ? 1. Yes 2. No<br />
Yes Purpose Amount Availed Training<br />
1. JRY/ IJRY<br />
2. DWACRA<br />
3. IPDP<br />
4. PMRY<br />
5. NREGP<br />
6. Others (Specify)<br />
D.8 Site Observations (distance from start point):<br />
Km Observations<br />
Page 70
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure – 5: Notification regarding rate applicable for Nevada Tigaon Sub-station<br />
Page 71
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Annexure - 6: Notification on circle rate applicable for Sirsa District<br />
Page 72
Draft Resettlement and Rehabilitation Action Plan – Package G 1 Substations Haryana Power System Improvement Project<br />
Page 73