Dimensionare tehnica <strong>AQUAmax</strong> Professional <strong>XL</strong> - bazine dreptunghiulare<br />
Dimensionare pentru epurare completa cu nitrificare si <strong>de</strong>nitrificare<br />
<strong>AQUAmax</strong> <strong>PROFESSIONAL</strong> <strong>XL</strong>1<br />
Baza <strong>de</strong> calcul <strong>XL</strong>1 <strong>XL</strong>1 <strong>XL</strong>1 <strong>XL</strong>1 <strong>XL</strong>1 <strong>XL</strong>1 <strong>XL</strong>1 <strong>XL</strong>1 <strong>XL</strong>1<br />
Persoane racordate 60 75 100 125 150 175 200 225 250 PE<br />
Cantitate specifica <strong>de</strong> apa pe persona si zi 150 150 150 150 150 150 150 150 150 ltr/(PE x d)<br />
Incarcatura specifica CBO5 60 60 60 60 60 60 60 60 60 g/(PE x d)<br />
Concentratie CBO5 400,0 400,0 400,0 400,0 400,0 400,0 400,0 400,0 400,0 mg/l<br />
Concentratie CCO 800,0 800,0 800,0 800,0 800,0 800,0 800,0 800,0 800,0 mg/l<br />
Substante filtrabile 350,0 350,0 350,0 350,0 350,0 350,0 350,0 350,0 350,0 mg/l<br />
Incarcatura specifica NH4-N 6,4 6,4 6,4 6,4 6,4 6,4 6,4 6,4 6,4 g/(PE x d)<br />
Concentratie NH4-N 42,7 42,7 42,7 42,7 42,7 42,7 42,7 42,7 42,7 mg/l<br />
Incarcatura specifica TKN 11,0 11,0 11,0 11,0 11,0 11,0 11,0 11,0 11,0 g/(PE x d)<br />
Concentratie TKN 73,3 73,3 73,3 73,3 73,3 73,3 73,3 73,3 73,3 mg/l<br />
Incarcatura specifica P 1,8 1,8 1,8 1,8 1,8 1,8 1,8 1,8 1,8 g/(PE x d)<br />
Concentratie P 12,0 12,0 12,0 12,0 12,0 12,0 12,0 12,0 12,0 mg/l<br />
Valoare pH la admisie (6.5 - 8.0) 7,0 7,0 7,0 7,0 7,0 7,0 7,0 7,0 7,0<br />
Temperatura in reactorul SBR (12 - 30°C) 20,0 20,0 20,0 20,0 20,0 20,0 20,0 20,0 20,0 °C<br />
Cantitatea totala <strong>de</strong> apa Qd [m³/d] 9,00 11,25 15,00 18,75 22,50 26,25 30,00 33,75 37,50 m³/d<br />
Incarcatura totala zilnica CBO5 3,60 4,50 6,00 7,50 9,00 10,50 12,00 13,50 15,00 kg/d<br />
Incarcatura totala zilnica NH4-N 0,38 0,48 0,64 0,80 0,96 1,12 1,28 1,44 1,60 kg/d<br />
Incarcatura totala zilnica TKN 0,66 0,83 1,10 1,38 1,65 1,93 2,20 2,48 2,75 kg/d<br />
Incarcatura totala zilnica P 0,11 0,14 0,18 0,23 0,27 0,32 0,36 0,41 0,45 kg/d<br />
Ape din alte surse [%] [fara ape pluviale] 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 %<br />
Debit zilnic <strong>de</strong> apa Qd [m³/d] 9,00 11,25 15,00 18,75 22,50 26,25 30,00 33,75 37,50 m³/d<br />
Debit maximal Q10 [m³/h] 0,90 1,13 1,50 1,88 2,25 2,63 3,00 3,38 3,75 m³/h<br />
Valori la evacuare<br />
CCO < 90 < 90 < 90 < 90 < 90 < 90 < 90 < 90 < 90 mg/l<br />
CBO5 < 25 < 25 < 25 < 25 < 25 < 25 < 25 < 25 < 25 mg/l<br />
SS < 60 < 60 < 60 < 60 < 60 < 60 < 60 < 60 < 60 mg/l<br />
Ntotal anorg. < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 < 20 mg/l<br />
Gratar mecanic / Sita rotativa nu nu nu nu nu nu nu nu nu da / nu<br />
Cantitate materii soli<strong>de</strong> pe locuitor si an [l/PE/y] 15,0 15,0 15,0 15,0 15,0 15,0 15,0 15,0 15,0 l/PEy<br />
Volum anual [m³/y] 0,9 1,1 1,5 1,9 2,3 2,6 3,0 3,4 3,8 m³/y<br />
Volum materii soli<strong>de</strong> retinut zilnic [m³/d] 2,47 3,08 4,11 5,14 6,16 7,19 8,22 9,25 10,27 l/d<br />
Reducere CBO5 dupa sitare RedS 0 0 0 0 0 0 0 0 0 %<br />
Incarcatura dupa sitare Bd,S = Bd - RedS x Bd [kg/d] 3,60 4,50 6,00 7,50 9,00 10,50 12,00 13,50 15,00 kg/d<br />
Preepurare<br />
Dim. minima a preepurarii la un timp <strong>de</strong> stationare > 1,5 h: VGF = Q10 x 1,5h [m³] 1,4 1,7 2,3 2,8 3,4 3,9 4,5 5,1 5,6 m³<br />
Reducere CBO5 dupa grosier/preepurare, timp stationare > 1,5 h RedPE 33 33 33 33 33 33 33 33 33 %<br />
Incarcatura dupa preepurare Bd,PE = Bd,S - RedPE x Bd,S [kg/d] 2,4 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,1 kg/d<br />
Namol primar sedimentat zilnic PS = 0,045 kg/(PE*d)<br />
Bazin <strong>de</strong> stocare / Pompare<br />
2,7 3,4 4,5 5,6 6,8 7,9 9,0 10,1 11,3 kg/d<br />
Volum bazin <strong>de</strong> stocare VP = ((tR/z/n)+tSed+tAb) x Q10 [m³] 4,4 5,5 7,4 9,2 11,0 12,9 14,9 16,8 18,8 m³<br />
Calcul bazin biologic conform ATV-A 131<br />
Incarcatura Bd la admisia in bazinul biologic [kg/d] 2,4 3,0 4,0 5,0 6,0 7,0 8,0 9,0 10,1 kg/d<br />
In<strong>de</strong>x namol ISV [l/kg TS] 100 100 100 100 100 100 100 100 100 l/kg<br />
Continut substanta uscata TSBB [kg TS/m³] 4,0 4,0 4,0 4,0 4,0 4,0 4,0 4,0 4,0 kg/m³<br />
Productie specifica namol in exces ÜS BB [kg TS/kg CBO5] 0,90 0,90 0,90 0,90 0,90 0,90 0,90 0,90 0,90 kg/kg<br />
Cantitatea <strong>de</strong> namol produsa zilnic din CBO5 ÜS d,C = ÜSBB x Bd [kg/d] 2,17 2,71 3,62 4,52 5,43 6,33 7,24 8,14 9,05 kg/d<br />
Varsta namol tTS 11,3 11,3 11,3 11,0 11,3 11,3 11,3 11,3 10,8 d<br />
Volumul bazinului biologic VBB = tTS x ÜSSd / TSR [m³] 6,13 7,67 10,22 12,44 15,33 17,89 20,44 23,00 24,42 m³<br />
Incarcatura volumetrica BR = BdZ / VBB [kg/(m³xd] 0,39 0,39 0,39 0,40 0,39 0,39 0,39 0,39 0,41 kg/m³d<br />
Incarcatura namol BTS = BR / TSR [kg BSB/(kg TS x d)] 0,10 0,10 0,10 0,10 0,10 0,10 0,10 0,10 0,10 kg/kg<br />
Dimensionare bazin <strong>de</strong> tratare (SBR) conform ATV-M 210<br />
Numar bazine <strong>de</strong> tratare SBR n 1 1 1 1 1 1 1 1 1<br />
Numarul ciclelor pe zi mZ [d -1 ] 3 3 3 3 3 3 3 3 3 1/d<br />
Cantitate <strong>de</strong> apa pe ciclu si bazin V z = Qd/mz/n [m³] 3,0 3,8 5,0 6,3 7,5 8,8 10,0 11,3 12,5 m³<br />
Durata unui ciclu tZ [h] 8,0 8,0 8,0 8,0 8,0 8,0 8,0 8,0 8,0 h<br />
Faza <strong>de</strong> sedimentare tSed [h] 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 h<br />
Faza <strong>de</strong> evacuare tAb [h] 0,25 0,31 0,42 0,26 0,31 0,36 0,42 0,47 0,52 h<br />
Timpul <strong>de</strong> reactie tR = z x (tN+tD) = tZ-tSed- tAb [h] 6,3 6,2 6,1 6,2 6,2 6,1 6,1 6,0 6,0 h<br />
Faza <strong>de</strong> nitrificare t N [h] 4,7 4,6 4,6 4,7 4,6 4,6 4,6 4,5 4,5 h<br />
Volumul unui bazin <strong>de</strong> tratare VR = Bd/BRxtZ/tR/n [m³] 7,8 9,9 13,4 15,9 19,8 23,3 26,9 30,5 32,7 m³<br />
Volum min. al unui bazin SBR Vmin = VR - VZ [m³] 4,8 6,2 8,4 9,7 12,3 14,6 16,9 19,3 20,2 m³<br />
Dimensiunile unui bazin SBR dreptunghiular, lungime latura l [m] 2,0 2,0 2,5 2,8 2,5 2,5 2,8 3,0 3,0 m<br />
Dimensiunile unui bazin SBR dreptunghiular, lungime latura b [m] 2,0 2,5 2,5 2,8 4,0 4,5 4,5 4,5 4,5 m<br />
Suprafata unui bazin SBR AR [m²] 4,0 5,0 6,3 7,8 10,0 11,3 12,6 13,5 13,5 m²<br />
Adancime max. apa in bazinul SBR hWmax = VRx4/3,14/dR² [m] 2,0 2,0 2,2 2,0 2,0 2,1 2,1 2,3 2,4 m<br />
Adancime min. apa in bazinul SBR hWmin = Vminx4/3,14/dR² [m] 1,2 1,2 1,4 1,2 1,2 1,3 1,3 1,4 1,5 m<br />
Inaltime strat namol hS = hWxTSRxISV/1000 [m] 0,78 0,79 0,86 0,81 0,79 0,83 0,85 0,90 0,97 m<br />
Factor <strong>de</strong> barbotare fA = (VR - Vmin)/VR [-] 0,38 0,38 0,37 0,39 0,38 0,38 0,37 0,37 0,38<br />
Varsta namol calculata tTS = VRxTSBBxtR/ÜSSd/tZxn [d] 11,3 11,3 11,3 11,0 11,3 11,3 11,3 11,3 10,8 d<br />
<strong>AQUAmax</strong> <strong>PROFESSIONAL</strong> <strong>XL</strong>1 - Dimensionare instalatii cu bazine dreptunghiulare