1.0 GENERAL<br />

1.1 This document describes in detail the <strong>scope</strong> <strong>of</strong> <strong>work</strong>, supply and responsibilities <strong>of</strong> bidder for procurement<br />

<strong>of</strong> natural gas metering skid <strong>of</strong> different capacities for inventory creation and for various consumers. These<br />

skids will be installed at different <strong>GAIL</strong> sites as and when required. In this contract Ultrasonic Meter based<br />

metering skid is envisaged;<br />

Ultrasonic Meter based metering skids are for Gas despatch stations for Gas consumers consisting <strong>of</strong> skid<br />

mounted Gas filtration, Pressure Let down, and Gas Metering (Ultrasonic meters) with Gas chromatograph<br />

and with control panel installed in the control room. Metering supervisory system is also envisaged to be<br />

mounted in Control Panel.<br />

1.2 The description and requirements contained in this <strong>specification</strong> are concise by necessity and cannot<br />

include all details. However, it is the responsibility <strong>of</strong> the bidder to execute the job on a turnkey basis in<br />

accordance with the <strong>specification</strong>s and internationally recognized good engineering practices .<br />

1.3 Any activity specifically not listed in this document, does not absolve the bidder <strong>of</strong> their responsibility to<br />

include such activities in their <strong>scope</strong> <strong>of</strong> <strong>work</strong> and supply, which otherwise is necessary, to complete<br />

instrumentation <strong>work</strong> for the project. All such activities shall be carried out by the bidder without any<br />

implication.<br />

1.4 In the event <strong>of</strong> any conflict between these <strong>specification</strong>s, related standards and codes, any other<br />

attachment to this package, the bidder shall follow the following documents in the order <strong>of</strong> their<br />

priority:<br />

a) Job Specification for gas metering package<br />

b) Data Sheets, Typical P&ID' s<br />

c) Standard <strong>specification</strong>s and standards<br />

In case <strong>of</strong> any conflict in various documents, same shall be referred to <strong>GAIL</strong> for clarification. Bidder shall<br />

not proceed without getting written approval in such a case<br />

2.0 SCOPE OF WORK & RESPONSIBILITY<br />

2.1 SCOPE OF WORK<br />

2.1.1 Bidder shall be responsible for execution <strong>of</strong> the package on turnkey basis with <strong>scope</strong> <strong>of</strong> <strong>work</strong> as listed<br />

below but not limited to the following :-<br />

i) Design and Engineering<br />

ii) Procurement/Supply, Inspection, Factory testing and Acceptance<br />

iii) Supervision for Installation, field calibration/testing and commissioning.<br />

2.1.2 Design and Engineering<br />

(a) Owner shall provide the bidder with this bid package consisting <strong>of</strong> typical Piping & Instrumentation<br />

Diagrams and process data sheets. The bidder shall be responsible to carryout the design and<br />

detailed engineering based on the data provided in the bid package and in line with other technical<br />

requirements specified elsewhere in this document. Scope shall also include sizing and sizing<br />

verification for all items including where data is dependent upon detailed engineering, detailing <strong>of</strong><br />

basic engineering designs, preparation <strong>of</strong> data sheets, coordination drawings for instruments and<br />

system oriented items, engineering drawings etc.<br />

(b) Residual Engineering<br />

The bidder shall also be responsible for carrying out any residual basic engineering necessary for<br />

proceeding with detailed engineering like instrument sizing, utility consumption, specifying derived<br />

data in process data sheets, type and material selection <strong>of</strong> instruments wherever required.<br />

c) Control Room Engineering<br />

For Supervisory monitoring and control a SCADA system is envisaged to ensure effective and reliable<br />

control, management and supervision <strong>of</strong> the consumers from centralized location. The SCADA<br />

system along with RTUs shall be provided by M/S <strong>GAIL</strong> through their separate Bidder and is not in<br />

the <strong>scope</strong> <strong>of</strong> supply <strong>of</strong> the bidder. However the bidder shall be responsible for configuring their<br />

systems and.providing all the necessary details <strong>of</strong> their systems to the SCADA vendor. All the skid<br />

data (like flow, pressure, temperature, Diff Pressure, valve position etc.) <strong>of</strong> the supplied skid shall be<br />

accessible from <strong>GAIL</strong>’s SCADA .through <strong>GAIL</strong>’s RTU and GSM modem supplied with the control<br />

panel by the bidder.