As with the starter strip panels, installation must start at the left side of the roof. If working left to<br />
right out of a valley, place the top left portion of the panel in the valley such that the diagonal cut<br />
down, 4 inches out from the centerline of the valley, from left to right cuts through the entire<br />
panel. The overlap on each piece is fitted into the overlap of the preceding one. At the ends of the<br />
courses trim panels (using a power saw or knife), to be flush with the edge.<br />
Panels are installed using eight (8) 1 ¾” galvanized roofing nails (see illustration above and in<br />
“Fastening” section). This will ensure that there are ten (16) attachment points in each panel as the<br />
fasteners will go through the top portion of the panel below.<br />
ROOF JACKS<br />
Roof Jacks may be fitted and removed in the same manner as with asphalt shingles.<br />