As with the starter strip panels, installation must start at the left side of the roof. If working left to<br />

right out of a valley, place the top left portion of the panel in the valley such that the diagonal cut<br />

down, 4 inches out from the centerline of the valley, from left to right cuts through the entire<br />

panel. The overlap on each piece is fitted into the overlap of the preceding one. At the ends of the<br />

courses trim panels (using a power saw or knife), to be flush with the edge. Care should be taken<br />

to keep the cuts straight.<br />

Panels are installed using five (7) 1 ¾” galvanized roofing nails (see illustration above and in<br />

“Fastening” section). This will ensure that there are ten (14) attachment points in each panel as the<br />

fasteners will go through the top portion of the panel below.<br />

ROOF JACKS<br />

Roof Jacks may be fitted and removed in the same manner as with asphalt shingles.<br />

Upon reaching the peak of the roof, the last row of panels may have to be trimmed along the upper<br />

edge, flush with the ridge.<br />

<strong>Euroshield</strong>® <strong>Installation</strong> Guide – EUROLITE SHAKE® November 2012<br />