28.03.2013 Views

Specification 49 Stone Mastic Asphalt for Airfields - Ministry of Defence

Specification 49 Stone Mastic Asphalt for Airfields - Ministry of Defence

Specification 49 Stone Mastic Asphalt for Airfields - Ministry of Defence

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Specification</strong> <strong>49</strong> <strong>Stone</strong> <strong>Mastic</strong> <strong>Asphalt</strong> <strong>for</strong> <strong>Airfields</strong> Appendix B – Straightedge Test<br />

Appendix B – Straightedge Test<br />

B.1 SCOPE<br />

This Appendix shall be followed to determine the<br />

surface accuracy <strong>of</strong> bituminous surfacing layers in<br />

this <strong>Specification</strong>.<br />

B.2 APPARATUS<br />

B.2.1 The straightedge <strong>for</strong> the tests shall be<br />

purpose made and 3 m long. It shall have a flat<br />

square edge <strong>of</strong> metal, at least 75 mm wide, along<br />

the full length <strong>of</strong> its base. The straightedge shall<br />

be fitted with lifting hand grips or handles.<br />

B.2.2 A calibrated wedge may be used to<br />

determine the straightedge clearance. The wedge<br />

should have an angle <strong>of</strong> (5.75 ± 0.05)°, and<br />

engraved at 10 mm intervals across the incline,<br />

starting at the apex, representing clearances<br />

increasing in 1 mm intervals up the incline.<br />

B.3 PROCEDURE<br />

B.3.1 The straightedge shall be placed<br />

unsupported on the surface, anywhere in any<br />

direction, other than across the crown <strong>of</strong> a camber<br />

or across a drainage channel. The location shall<br />

be selected by the Project/Works Services<br />

Manager or his representative, and the tests shall<br />

be carried out in his presence.<br />

B.3.2 Twenty tests shall be made <strong>for</strong> every<br />

1000 m² laid and at least half <strong>of</strong> these tests shall<br />

be across lane joints.<br />

B.3.3 The Contractor shall mark with white paint<br />

all areas which fail to comply with the specified<br />

requirement.<br />