Volume 2 Series NG 900<br />
Notes for Guidance on the Specification for Road Works Road Pavements <strong>–</strong> Bituminous Bound Materials<br />
4 On particularly large or critical projects it<br />
may be appropriate to monitor resistance to<br />
permanent deformation in the permanent<br />
works. If required, this should be clearly<br />
indicated in Appendix 7/1 along with the site<br />
classification.<br />
5 When specifying resistance to permanent<br />
deformation, it will be necessary to take into<br />
account the transitional problems brought<br />
about by the change in the wheel tracking test<br />
method from BS 598 part 110 to IS EN 12697-<br />
22, which uses similar equipment but<br />
different duration and loading. Further<br />
information is given in the note to SR28 Table<br />
4. Work is in hand to establish criteria for the<br />
new method, but in the interim, requirements<br />
should be based on the BS 598 test but with<br />
data provided to show the values for the same<br />
mix tested to the IS EN 12697 method.<br />
Declared Declared Specifications<br />
Specifications<br />
6 The following table provides an example of a<br />
declared specification derived from the target<br />
composition criteria set out in the<br />
specification.<br />
NG NG 938 938 Porous Course Course<br />
Course<br />
Asphalt Surface<br />
1 Porous asphalt is not intended for use without<br />
prior design approval by the National Roads<br />
Authority Standards Section. Guidance to the<br />
requirements specified in Clause 938 is<br />
contained in HD 27 (DMRB 7.2.4). The use of<br />
Porous Asphalt is restricted in accordance<br />
with HD36.<br />
2 Clause 938 contains requirements for porous<br />
asphalt. The binder shall be preblended<br />
polymer modified bitumen.<br />
3 The type of binder permitted, requirements<br />
for the physical and geometrical properties of<br />
the coarse aggregate and the traffic category<br />
should be stated in Appendix 7/1. The<br />
specification of specific proprietary modifiers<br />
in Appendix 7/1 is not permitted.<br />
4 Before use of a modifier or modified binder the<br />
Contractor should provide all necessary<br />
information to enable evaluation of the<br />
modifier to be carried out and suitable<br />
specification clauses for its use to be prepared.<br />
5 Landscaping operations should preferably be<br />
completed before laying porous asphalt<br />
surface course, to avoid contamination of the<br />
surface.<br />
6 Porous asphalt shall be designed to finish on a<br />
level grade or on an up-grade and shall not<br />
finish or commence at a junction.<br />
January 2010 29 29