Layout 1 (Page 1) - Peterborough Court
Layout 1 (Page 1) - Peterborough Court
Layout 1 (Page 1) - Peterborough Court
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
44<br />
PETERBOROUGH COURT & DANIEL HOUSE<br />
133-140 FLEET STREET LONDON EC4<br />
PETERBOROUGH COURT<br />
SPECIFICATION<br />
Goldman Sachs are currently undertaking a<br />
comprehensive internal refurbishment of <strong>Peterborough</strong><br />
<strong>Court</strong>. This involves stripping back the existing<br />
accommodation to shell and core and then refitting to<br />
an enhanced Cat A specification. The project is being<br />
undertaken on a rolling floor-by-floor basis and it is<br />
likely these works will be completed by mid 2012.<br />
As part of this exercise, Goldman Sachs will be<br />
replacing the air-conditioning, WCs and creating new<br />
tea points/break out areas. New glazing panels will<br />
also be inserted between Levels 6-10 on the southern<br />
elevation, further increasing light penetration into the<br />
building.<br />
The base-build specifications for <strong>Peterborough</strong> <strong>Court</strong><br />
includes:<br />
External Envelope<br />
The ground floor storey is clad in hand set granite<br />
providing a base up to the first floor and incorporating<br />
double-glazed stainless steel framed windows,<br />
aluminium grilles and architectural metalwork. From<br />
the first floor upwards cladding is a high quality curtain<br />
walling system using a pre-finished and pre-glazed rain<br />
screen panel system. The structure and cladding allows<br />
for offices to be divided generally on a module of 1.5 m.<br />
At ground level and above, a minimum slab to slab of<br />
4,140 mm varying up to 5,330 mm is provided.<br />
Floor Loadings<br />
The floor slabs are designed to accommodate the<br />
following loads:-<br />
Typical office floors: 4 kN/m2 + 1 kN/m2 extra<br />
for partitions<br />
Loading dock: 12 kN/m2<br />
Parking area: 3 kN/m2<br />
Internal Finishes<br />
The internal specification includes the following:<br />
Fully accessible, suspended white powder coated<br />
perforated pressed metal tiles with sound absorbent<br />
mineral wool padding. The suspension grid is<br />
suitable for partitioning on a 1.5 m x 1.5 m module.<br />
Standard light fittings are incorporated into the<br />
suspended ceilings. The fittings comprise low<br />
brightness louvres providing 500 lux lighting level<br />
at the desk top. There are incandescent light fittings<br />
in the main entrance and lobbies providing 200 lux.<br />
Fully accessible raised metal floors in all office areas<br />
with an average void of 150 mm (inclusive of floor<br />
tile) on typical office floors and 300 mm deep<br />
(inclusive of floor tile) on Levels 1, 2, 3 and 6.<br />
Electrical services provided at 11.0 Kv, 3 Phase,<br />
50 hertz from multiple feeders entering the building<br />
at Shoe Lane.<br />
Finished floor to ceiling height of 2.6 m (8 ft 6 in)<br />
for typical office space, increasing to 3.05 m (10 ft)<br />
for floors 1, 2 and 3 and 2.9 m (9 ft 6 in) on the<br />
6th floor.<br />
Automatic sprinkler system.<br />
Building Management System (BMS).<br />
Emergency generator.