3<br />
Achievement against the<br />
approved program plan<br />
At a glance<br />
Key findings<br />
• The original targets for the program have proven to be too ambitious. This has<br />
required the Office of Health Information Systems to revise milestones as the<br />
program proceeds.<br />
• The program’s original completion dates have been extended from four to six<br />
years. However, in our view, the program will not meet this revised delivery date.<br />
• Delivery of the clinical systems, which is central to obtaining the original forecast<br />
benefits of the HealthSMART strategy, is already two years behind the original<br />
schedule, with no firm implementation dates.<br />
• According to the original 2003 timelines approved by government, major acute<br />
hospitals in ten health agencies should by now, be using clinical systems.<br />
• OHIS does not fully account for agency costs in its budgets for the program, nor<br />
does it monitor agency expenses. Therefore, OHIS is not able to robustly<br />
estimate budgets or understand the program’s true cost.<br />
• Although there has been significant activity and effort by OHIS resulting in the<br />
implementation of a number of HealthSMART applications, some 57 per cent of<br />
the original approved budget has been consumed, with 24 per cent of the<br />
expected installations complete, and the shared services environment and<br />
supporting ICT technical infrastructure fully operational.<br />
Key recommendations<br />
The Department of Human Services should:<br />
• identify the agencies expected to implement clinical systems and devise a<br />
realistic schedule, with adequate contingency, to successfully implement the<br />
program<br />
• work with agencies to define a standard method to record agency costs related to<br />
the HealthSMART program<br />
• monitor in collaboration with agencies, agency costs for the HealthSMART<br />
program and report these to the Board of Health Information Systems<br />
• seek authorisation for the various changes it has made to system implementation<br />
and budget targets in the HealthSMART program through the defined central<br />
agency amendment processes.<br />
<strong>Delivering</strong> HealthSMART — Victoria's whole-of-health ICT strategy 19