GANGOTRI H.E. PROJECT 55 (1X55) MW - Ministry of Power
GANGOTRI H.E. PROJECT 55 (1X55) MW - Ministry of Power
GANGOTRI H.E. PROJECT 55 (1X55) MW - Ministry of Power
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
CHAPTERS<br />
<strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
<strong>55</strong> (1X<strong>55</strong>) <strong>MW</strong><br />
CONTENTS<br />
PFR STUDIES OF <strong>GANGOTRI</strong> HE <strong>PROJECT</strong><br />
NAME Page No.<br />
Salient Features …………………………. i-iv<br />
I Executive Summary……………………… 1-1 to 1-5<br />
II Background Information…………………. 2-1 to 2-6<br />
III The Project Area…………………………. 3-1 to 3-3<br />
IV Topography and Geotechnical Aspects…… 4-1 to 4-9<br />
V Hydrology………………………………… 5-1 to 5-7<br />
VI Conceptual Layout and Planning…………. 6-1 to 6-12<br />
VII <strong>Power</strong> Potential Studies…………………… 7-1 to 7-4<br />
VIII <strong>Power</strong> Evacuation …………………………. 8-1 to 8-2<br />
IX Initial Environment Studies………………… 9-1 to 9-20<br />
X Infrastructure Facilities…………………….. 10-1 to 10-4<br />
XI Construction Planning & Schedule………… 11-1 to 11-5<br />
XII Cost Estimate………………………………. 12-1 to 12-2<br />
XIII Economic Evaluation……………………… 13-1 to 13-3<br />
1
APPENDICES<br />
1.1<br />
Observation <strong>of</strong> CWC on Hydrological<br />
Studies<br />
1.2 Replies on Observations<br />
1.3 Compliance <strong>of</strong> Hydrological Studies<br />
2.0 Drawings<br />
PFR STUDIES OF <strong>GANGOTRI</strong> HE <strong>PROJECT</strong><br />
2
LOCATION<br />
<strong>GANGOTRI</strong> HE <strong>PROJECT</strong> (1x<strong>55</strong>=<strong>55</strong> <strong>MW</strong>)<br />
SALIENT FEATURES<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
State Uttaranchal<br />
District Uttarkashi<br />
River Bhagirathi<br />
Dam site<br />
Location About 2.5km d/s <strong>of</strong> Gangotri Shrine.<br />
Latitude 30 o 59’ 54” N<br />
Longitude 78 o <strong>55</strong>’ 03” E<br />
Nearest Airport Dehradun<br />
Nearest rail head Rishikesh/Dehradun<br />
HYDROLOGY<br />
Catchment area at dam site 944 sq. km<br />
Maximum average discharge at dam site 94.2 cumec<br />
Minimum average discharge at dam site 4.7 cumec<br />
RESERVOIR<br />
Full Reservoir Level (FRL) El 2989.0 m<br />
Minimum Drawdown Level (MDDL) El 2984.0 m<br />
Gross storage at FRL 4.370 M cum<br />
Live storage 0.91 M cum<br />
Area under submergence at FRL 24.96 ha<br />
DIVERSION TUNNEL<br />
Number 1<br />
Size 4 m dia<br />
Length 400 m<br />
Diversion discharge (assumed) 50 cumecs<br />
i
DAM<br />
Type Concrete gravity<br />
Top elevation <strong>of</strong> dam El 2991.0m<br />
Height <strong>of</strong> dam above<br />
river bed level 26.0 m<br />
Length <strong>of</strong> dam at top 110.0 m<br />
River bed level El 2965.0<br />
SPILLWAY<br />
Design flood 2500 cumecs<br />
Type Ogee<br />
Crest elevation El 2975.0<br />
Number & Size 3 <strong>of</strong> 12.5 m x 14.0 m<br />
Length <strong>of</strong> spillway 49.5 m<br />
Energy dissipation Stilling basin<br />
INTAKE<br />
Size 2.75 m ф D-shaped<br />
Invert level El 2977.0 m<br />
Number 1<br />
Size <strong>of</strong> gate opening 3.0 m x 3.0 m<br />
Design discharge 21.83 Cumecs<br />
DESILTING CHAMBER<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Number 1 no<br />
Size 110.0 m x 8.0 m x 9.0 m<br />
Design discharge 21.83 cumecs<br />
Particle size to be removed 0.2 mm & above<br />
ii
HEAD RACE TUNNEL<br />
Number 1<br />
Size 2.5 m<br />
Shape D-shaped<br />
Length 5.2 km<br />
Rated Discharge 18.19 Cumecs<br />
SURGE SHAFT<br />
Number 1<br />
Size 6.0 m dia<br />
Height 92.0 m<br />
PRESSURE SHAFT<br />
Numbers 1 No.<br />
Size 2.0 m<br />
Length 315.0 m<br />
POWER HOUSE<br />
Type Underground<br />
Installed capacity <strong>55</strong> <strong>MW</strong><br />
Number <strong>of</strong> units 1<br />
<strong>Power</strong> house cavern size 40 mx20.5mx30m<br />
Type <strong>of</strong> turbine Vertical Francis<br />
C.L. <strong>of</strong> turbine El 2634.50<br />
Rated Head El 336.33 m<br />
TAIL RACE<br />
Size 3.0 m<br />
Type D-Shape<br />
Length 450.0 m<br />
Design Discharge 18.19 cumecs<br />
River Bed Level El 2638.0 m<br />
Normal TWL El 2642.0 m<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
iii
SWITCHYARD<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Size Gas Insulated Switchyard (GIS) on<br />
the floor above the transformer/s in P/H<br />
cavern<br />
POWER GENERATION<br />
Installed capacity <strong>55</strong> <strong>MW</strong><br />
Annual energy generation<br />
i) 90% dependable year 264.76 GWh<br />
ii) Energy in 90% year 256.64 GWh<br />
on 95% availability<br />
COST ESTIMATES & FINANCIAL ASPECT (Rs. Crores)<br />
Civil Works 148.46<br />
Electro Mechanical Works 63.18<br />
Sub Total 211.64<br />
Interest During Construction 33.47<br />
Total (Generation) 245.11<br />
Transmission works 7.50<br />
Grand Total 252.61<br />
Tariff for first year Rs 1.62 Rs./kWh<br />
Levellised Tariff Rs 1.42 Rs/kWh<br />
CONSTRUCTION PERIOD 5 years<br />
iv
1.1 INTRODUCTION<br />
CHAPTER - I<br />
EXECUTIVE SUMMARY<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The Gangotri Hydroelectric Project located in Uttarkashi district <strong>of</strong><br />
Uttaranchal envisages utilization <strong>of</strong> the waters <strong>of</strong> the river Bhagirathi river for<br />
power generation on a run <strong>of</strong> river type development, harnessing a head <strong>of</strong><br />
about 347 m.<br />
The project with a proposed installation <strong>of</strong> 1 x <strong>55</strong> <strong>MW</strong> ( <strong>55</strong> <strong>MW</strong>) would afford<br />
an annual energy generation <strong>of</strong> 264.76 GWh in a 90% dependable year. The<br />
tariff from the project at present day cost would be Rs.1.42 kWh (levellised).<br />
The diversion site is located at Latitude 30 o 59’ 54”, Longitude 78 o <strong>55</strong>’ 03” E.<br />
The dam site is approachable from Rishikesh/Dehradun road (via Tehri-<br />
Uttarkashi-Gangotri highway) at a distance <strong>of</strong> 267 km upto Bhaironghati and<br />
further 9 km from Bhaironghati to diversion site. The nearest rail head is<br />
located at Rishikesh and Dehradun nearest airport is located at Dehradun.<br />
1.2 SCOPE OF WORKS<br />
The Gangotri HE project envisages construction <strong>of</strong> :<br />
• a 26 m high concrete gravity dam across river Bhagirathi to provide a<br />
live storage <strong>of</strong> 0.91 M cum with FRL at El 2989 m and MDDL at El<br />
2984 m.<br />
• 1 no desilting chamber <strong>of</strong> length 110.0 (L) and size 8.0 m (W) 9 .0 m<br />
(H) to remove silt particles <strong>of</strong> size 0.2 mm and above;<br />
1-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
• a 5.20 km long and 2.5 m dia head race tunnel terminating in a surge<br />
shaft<br />
• a 92.0 m high, 6.0 m dia surge shaft<br />
• 315 m long, 2.0 m dia pressure shaft<br />
• an underground power house having an installation <strong>of</strong> one Francis<br />
turbine driven generating unit <strong>of</strong> <strong>55</strong> <strong>MW</strong> operating under a rated<br />
head <strong>of</strong> 336.33 m; and<br />
• 450 m long tail race tunnel to carry the power houses release back to<br />
the river.<br />
1.3 HYDROLOGY<br />
The river Gangotri drains a catchment area <strong>of</strong> about 944 sq km at the<br />
proposed dam site. The water availability for the project i.e. the dependable<br />
flows both for 90% and 50% dependable year have been assessed, based on<br />
Regional model incorporating glacial cover, snow and forest cover and<br />
incorporating data <strong>of</strong> 17 Gauge Discharge sites (13 CWC sites and 4 state<br />
Govt. sites) in the region utilising the available data for the period 1975-76 to<br />
2001-2002 for many <strong>of</strong> the sites. The computed inflow series worked out has<br />
been utilized for <strong>Power</strong> Potential Studies. The design flood has been<br />
assessed as 2500 cumecs (SPF).<br />
1.4 POWER POTENTIAL STUDIES<br />
The available data <strong>of</strong> water flows on 10 daily basis has been analysed. Water<br />
flows determined on 90% dependable year, have been utilised for computing<br />
power benefits. An installation <strong>of</strong> <strong>55</strong> <strong>MW</strong> comprising 1 generating units <strong>of</strong> <strong>55</strong><br />
<strong>MW</strong> has been proposed. The energy availability from the project in a 90%<br />
dependable year has been summarized below :<br />
1-2
Annual Energy Generation<br />
Annual Energy Generation (GWh) : 264.76<br />
Annual Load Factor (%) : 54.95<br />
Generation during Lean Flow Season<br />
Energy Output (<strong>MW</strong>c) : 10.28<br />
Load Factor (%) : 18.69<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The design energy for tariff at 95% availability in a 90% dependable year has<br />
been worked out as 256.64 GWh.<br />
A pondage <strong>of</strong> 0.910 Mcum has been provided in the diversion dam which<br />
would enable the station to operate as peaking station. The pondage is<br />
equivalent to 764.215 <strong>MW</strong>h which is sufficient to operate the station for 13.89<br />
hours.<br />
1.5 POWER EVACUATION ASPECTS<br />
The <strong>55</strong> <strong>MW</strong> power generated at 11 kV at Gangotri HEP will be stepped upto<br />
220 kV by unit step-transformers. The power would be transmitted to nearby<br />
Bhaironghati HEP.<br />
1.6 ENVIRONMENTAL ASPECTS<br />
The project site is located on river Bhagirathi. The submergence area is 24.96<br />
ha, <strong>of</strong> which 14.90 ha <strong>of</strong> land falls under the category <strong>of</strong> reserve forest area<br />
1-3
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
About 1.89 ha <strong>of</strong> barren land is coming under reservoir submergence. In<br />
addition, land will also be required for other project appurtenances. Based on<br />
assessment <strong>of</strong> environmental impacts, management plans have to be<br />
formulated for acquisition <strong>of</strong> forest land, wildlife conservation, muck disposal,<br />
quarry stabilization, and other environmental issues. These issues would be<br />
addressed during the investigation for DPR.<br />
1.7 ESTIMATES OF THE COST<br />
The project is estimated to cost Rs. 245.11 Crores including IDC at June,2003<br />
price level. The preliminary cost estimate <strong>of</strong> the project has been prepared as<br />
per guidelines <strong>of</strong> CEA/CWC. The break up <strong>of</strong> the cost estimates is given<br />
below :<br />
Particulars Rs. (in Crores)<br />
Civil Works : 148.46<br />
Electro Mechanical Works : 63.18<br />
Sub Total : 211.64<br />
Interest During Construction : 33.47<br />
Total (Generation) : 245.11<br />
Transmission Works : 7.50<br />
Grand Total : 252.61<br />
1.8 FINANCIAL ASPECTS<br />
As indicated above, the Gangotri HE Project, with an estimated cost<br />
(Generation only) <strong>of</strong> Rs. 245.11 Crores (including IDC <strong>of</strong> Rs. 33.47 Crores)<br />
and design energy <strong>of</strong> 256.64 GWh in a 90% dependable year is proposed to<br />
1-4
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
be completed in a period <strong>of</strong> 5 years. The tariff has been worked out<br />
considering a debt-equity ratio <strong>of</strong> 70:30, 16% return on equity and annual<br />
interest rate on loan at 10%. The tariff for first year and levellised tariff (at<br />
power house bus bar) have been worked out as Rs.1.62 /kWh & Rs.<br />
1.42/kWh respectively.<br />
1.9 CONCLUSIONS<br />
Gangotri HE Project involves simple civil works and could be completed in 5<br />
years. The project would afford a design energy <strong>of</strong> 256.64 GWh in a 90%<br />
dependable year. The cost per <strong>MW</strong> installed works out to Rs. 3.85 Crores.<br />
The Preliminary Feasibility Report indicates that the scheme merits<br />
consideration for taking up Survey & Investigation and preparation <strong>of</strong> DPR.<br />
1-5
2.1 GENERAL<br />
CHAPTER – II<br />
BACKGROUND INFORMATION<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
In Nov.2000, Uttaranchal State was carved out <strong>of</strong> thirteen hill districts <strong>of</strong><br />
Northern U.P. The state borders with Nepal and Tibet on the east, Central<br />
Himalayas on the north, Haryana and Himachal Pradesh on the west and<br />
northwest respectively.<br />
Geophysically the state has four Mountain Zones namely Foot hills, Lesser<br />
Himalayas, Greater Himalayas and Trans-Himalayas. The mountains are<br />
covered with perpetual snow and glaciers and has gifted the north India a<br />
perennial river system <strong>of</strong> the Ganga and its tributaries. The tributaries <strong>of</strong><br />
Ganga, namely Alaknanda, Bhagirathi, Yamuna and Sarda originate from<br />
the foothills <strong>of</strong> snow capped peaks and glaciers in the Central Himalayas and<br />
incise their respective courses through the rugged terrain, splash and surge<br />
the steep gradients and most <strong>of</strong> the streams <strong>of</strong>fer excellent potential for<br />
Hydro power development.<br />
The region is blessed with magnificent glaciers, majestic rivers, gigantic snow<br />
capped peaks, Valley <strong>of</strong> flowers, natural beauty and rich flora and fauna.<br />
Many holy shrines have blessed the state spiritually and given the name <strong>of</strong><br />
“Dev Bhoomi” or “Land <strong>of</strong> Gods”. The seasonal influx <strong>of</strong> tourists, the seekers<br />
<strong>of</strong> peace for visit to the holy shrines and lovers <strong>of</strong> nature contribute to the<br />
state income.<br />
The state is divided into Kumaon and Garhwal Divisions with 13 districts,<br />
42 tehsils, 95 blocks, and 15689 inhabited villages and 73 towns. The<br />
2-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
State has a geographical area <strong>of</strong> 53119 sq. km which is 1.62% <strong>of</strong> the total<br />
area <strong>of</strong> the country and supports 84.8 lakh population which is 0.83% <strong>of</strong><br />
the total population <strong>of</strong> India. The percentage <strong>of</strong> villages having population<br />
more than 500 is about 11.4% (1991 Census). The existing majority <strong>of</strong><br />
smaller settlements <strong>of</strong> Uttaranchal poses a serious challenge for the<br />
economic, infrastructure and lack <strong>of</strong> services to the far flung places in the<br />
hilly terrain makes Uttaranchal as one <strong>of</strong> the extremely backward states <strong>of</strong><br />
India.<br />
It has 76.1% electrified villages as compared to 75.3% <strong>of</strong> villages <strong>of</strong> U.P.<br />
The average per capita consumption <strong>of</strong> electricity is 245.57 kWh whereas<br />
Dehradun and Nainital consume 480.81 and 447.33 kWh respectively<br />
with a minimum consumption <strong>of</strong> 43.7 kwh in Uttarkashi.<br />
2.2 POWER SCENARIO IN NORTHERN REGION<br />
2.2.1 Present Status<br />
Most <strong>of</strong> the states in the Northern Region have been experiencing energy<br />
shortage as well as shortage <strong>of</strong> Peak <strong>Power</strong> <strong>of</strong> varying degree. Actual <strong>Power</strong><br />
supply position in the Northern Region during the year 2001-2002 has been<br />
as under:<br />
Energy (in MU), year 2001-2002<br />
State Require- Availability Shortage(-)/ %age<br />
ment<br />
Surplus (+)<br />
Chandigarh 1110 1108 (-) 2 0.2<br />
Delhi 19350 18741 (-)609 3.1<br />
Haryana 18138 17839 (-)299 1.6<br />
Himachal Pradesh 3293 3206 (+) 87 2.6<br />
Jammu & Kashmir 6635 5899 (-) 736 11.1<br />
2-2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
State Require- Availability Shortage(-)/ %age<br />
ment<br />
Surplus (+)<br />
Punjab 28780 27577 (-)1203 4.2<br />
Rajasthan 24745 24495 (-)250 1.0<br />
Uttaranchal-U.P 48332 43545 (-)4787 9.9<br />
Northern Region 150383 142410 (-)7973 5.3<br />
2.2.2 Peak <strong>Power</strong> (in <strong>MW</strong>), year 2001-2002<br />
State Peak Peak Met Shortage(-)/ %age<br />
Demand<br />
Surplus (+)<br />
Chandigarh 180 180 0 0.0<br />
Delhi 3118 2879 (-)239 7.7<br />
Haryana 3000 2900 (-)100 1.6<br />
Himachal Pradesh 562 562 0 0.0<br />
Jammu & Kashmir 1209 999 (-) 210 17.4<br />
Punjab 5420 4936 (-)484 8.9<br />
Rajasthan 3700 3657 (-)43 1.2<br />
Uttaranchal-U.P 7584 6887 (-)607 9.2<br />
Northern Region 24773 23000 (-)1773 7.2<br />
2.3 NECESSITY OF HYDRO POWER DEVELOPMENT IN UTTARANCHAL<br />
2.3.1 Hydro and Thermal <strong>Power</strong> Mix<br />
The main resources for generating electricity are by utilising the hydro<br />
potential available along the river drops besides the use <strong>of</strong> fossil fuel.<br />
Presently the ratio <strong>of</strong> thermal generation and Hydro-electric generation in<br />
Uttaranchal <strong>Power</strong> grid, is quite disproportionate. With the diminishing coal<br />
resources and difficult oil position all over the world, it is necessary that<br />
electric generation be aimed to achieve the economic balance <strong>of</strong> 40:60<br />
2-3
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
between the hydro and thermal generation <strong>of</strong> power, as against the existing<br />
25:75 ratio.<br />
2.4 BRIDGING THE GAP OF HYDRO POWER GENERATION<br />
The requirement <strong>of</strong> power in Uttranchal is very fluctuating because <strong>of</strong> many<br />
seasonal and other similar demands <strong>of</strong> industries. To improve the share <strong>of</strong><br />
hydro-power generation it is essential to develop the hydroelectric power<br />
potential <strong>of</strong> state which is about 15110 <strong>MW</strong>, <strong>of</strong> which so far only 8% has been<br />
developed.<br />
The existing installed generating capacity in the<br />
State is about 1286 <strong>MW</strong> ( 2003 fig) and the whole is contributed by hydro<br />
generation. There is no thermal power generation in the state . The major<br />
hydro power stations under construction in the state are (i) Maneri Bhali,<br />
Stage-II (304 <strong>MW</strong>), (ii) Lakhawar Vyasi, Stage-I (300 <strong>MW</strong>), (iii) Lakhwari<br />
Vyasi, Stage-II (120 <strong>MW</strong>), (iv) Srinagar H.E. Project (330 <strong>MW</strong>), (v)<br />
Vishnuprayag Scheme (400 <strong>MW</strong>), (vi) Tehri Dam Project, Stage-I (1000 <strong>MW</strong>),<br />
(vii) Tehri Dam Project, Stage-II (1000 <strong>MW</strong>), (viii) Koteshwar Dam Project<br />
(400 <strong>MW</strong>), and (ix) Dhauliganga H.E. Project, Stage-I (280 <strong>MW</strong>).<br />
With rising hydro power generation and improving efficiencies in distribution<br />
<strong>of</strong> electricity, Uttaranchal hopes to <strong>of</strong>fer energy at stable prices for ec<strong>of</strong>riendly<br />
industrial development. Though the state is more or less sufficient<br />
in its energy generation to meet its own requirement, there is an urgent need<br />
to develop its huge untapped hydro power potential in an early and efficient<br />
manner, manage efficiently the hydro generation capacity <strong>of</strong> existing power<br />
stations and to develop and promote new Hydro projects with the purpose<br />
<strong>of</strong> harnessing hydropower resources in the state for economic well being and<br />
growth <strong>of</strong> the people in the whole region.<br />
2-4
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
In order to meet the load demand satisfactorily, it is considered essential to<br />
maintain a minimum gross margin <strong>of</strong> about 30 per cent over the projected<br />
peak demand while planning for expansion <strong>of</strong> power supply facilities.<br />
To bridge the gap between the demand for power and the availability <strong>of</strong><br />
power, some <strong>of</strong> the major hydro-electric schemes identified in Ganga Valley<br />
for development are indicated below :<br />
i Tapovan<br />
(360 <strong>MW</strong>)<br />
Vishnugad<br />
ii Bowala<br />
(132 <strong>MW</strong>)<br />
Nandprayag<br />
viii Karanprayag Dam (252 <strong>MW</strong>)<br />
ix Lata Tapovan (108 <strong>MW</strong>)<br />
iii Kishau Dam (600 <strong>MW</strong>) x Vishnugad Pipalkoti (340 <strong>MW</strong>)<br />
iv Pala Maneri (416 <strong>MW</strong>) xi Pancheshwar Dam<br />
v Loharinag<br />
<strong>MW</strong>)<br />
Pala (520<br />
xii Chamgad Dam (400 <strong>MW</strong>)<br />
vi Koth Bhel (1000 <strong>MW</strong>) xiii Dhauliganga, Stage-II<br />
vii Utyasu Dam (1000 <strong>MW</strong>)<br />
The location <strong>of</strong> H.E. Schemes are indicated in Plate-1 enclosed.<br />
2.5 PRESENT STUDIES<br />
2.5.1 With a view to prioritize the large number <strong>of</strong> identified schemes to harness<br />
vast untapped hydro resources in the order <strong>of</strong> their attractiveness for<br />
implementation, Ranking studies were carried out by CEA. Subsequently,<br />
after consultation process initiated by <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong> with various state<br />
agencies, CPSUs etc., it was considered appropriate that Preliminary<br />
2-5
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Feasibility Report (PFRs) <strong>of</strong> selected hydroelectric projects be taken up so<br />
that feasibility <strong>of</strong> the scheme considered in ranking studies could be<br />
established.<br />
2.5.2 In order to achieve the above objective the present preliminary feasibility<br />
stage report presents the Gangotri H.E Project located in Uttarkashi district,<br />
as detailed in the subsequent Chapters.<br />
2-6
3.1 GENERAL<br />
CHAPTER – III<br />
THE <strong>PROJECT</strong> AREA<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The Gangotri H.E. Project is located on Bhagirathi river, a tributory <strong>of</strong> the<br />
Ganga. The Ganga in this region has two major tributaries viz Bhagirathi and<br />
Alaknanda with their confluence at Dev Prayag. Bhagirathi originates at<br />
Gangotri glaciers and flows west wards.. It passes through the rugged terrain,<br />
incise its course through steep gradients. The Gangotri H.E. Project is the first<br />
H.E. project located on the Bhagirathi river for its development for hydro<br />
power in the cascade development. Immediately after Gangotri, Bhaironghati<br />
H.E. Project is envisaged after joining <strong>of</strong> the Jadhganga river. Gangotri<br />
H.E.Project utilise the river bedfall <strong>of</strong> about 327.0 m with the diversion<br />
structure located at bed level <strong>of</strong> 2965.0 m.<br />
Immediately down stream <strong>of</strong> Gangotri H.E. Project, another project<br />
Bhaironghati H.E. Project is proposed which utilises the river bed fall <strong>of</strong> about<br />
100.0 m. The Gangotri H.E. Project is a Run-<strong>of</strong>f-the-River scheme. With the<br />
arrangement <strong>of</strong> dam and gates, a small diurnal storage is created. It is<br />
proposed to locate the diversion dam at bed level EL 2965 m which is about<br />
2.5 km downstream <strong>of</strong> Gangotri shrine where by Kedar Ganga river joins<br />
Bhagirathi river from the south in Uttarkashi District. The project intake is<br />
approached by railway upto Rishikesh further 267 km by road upto<br />
Bhaironghati via Tehri-Uttarkashi-Gangotri highway and further 9 km by road<br />
to Gangotri H.E. Project diversion site. The ratio discharge <strong>of</strong> about 18.19<br />
cumecs passes through a tunnel <strong>of</strong> 5.20 km length and 2.50 m dia (D-shaped)<br />
lead the discharge to the under ground power station proposed to be located<br />
at Lat 31 0 01’ 29” N and Long 78 0 52’ 17.5” E. The tail race lead the<br />
3-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
discharge back to the river. The power station utilises an average hydraulic<br />
head <strong>of</strong> about 347.0 m.<br />
3.2 CLIMATE<br />
The available IMD observatory is at Dehradun which hardly represents the<br />
Uttarkashi climate. However at Dehradun peak winter extend from Dec. to<br />
Jan. months where the temperature remains at 2 0 C and during May- June<br />
months the maximum temperature is around 40 0 C. Rainfall during monsoon<br />
period (June to Sept.) is about 2770 mm. Large climatic variations are<br />
experienced in the intra-sub basin <strong>of</strong> the tributaries <strong>of</strong> Ganga. Gangotri<br />
project is located in Bhagirathi basin the climate <strong>of</strong> which could be considered<br />
more synonymous to Badrinath Met-station (IMD). Here substantial snowfall<br />
occurs during winter months ( Dec.-April) with average seasonal snowfall is<br />
about 4600 mm. Although some snowfall is experienced in other months<br />
also except during June and July months.<br />
3.3 SOCIO ECONOMIC PROFILE<br />
The entire state has undulating topography with l<strong>of</strong>ty mountains jutting out<br />
and create the rugged terrain with steep valleys. The geology, soil texture and<br />
climate are highly variable including the habitation pattern. It has sparse and<br />
scanty population, small sized villages, scattered on the hilly land scape.<br />
Out migration <strong>of</strong> able bodied person is common, subsistance level agriculture<br />
based economy mostly prevails with marginal holdings, the infrastructural<br />
development becomes very costly.<br />
Uttarkashi District has an area <strong>of</strong> 15.8% and supports 4% population as<br />
compared to the state. It has lowest density <strong>of</strong> population <strong>of</strong> about 30<br />
persons per sq. km. as against that <strong>of</strong> 116 persons per sqkm <strong>of</strong> the state.<br />
3-2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The litracy rate both among total and female is lowest in the district standing<br />
at 47.2% and 23.6% as against state average <strong>of</strong> 59.6 and 42.9% respectively.<br />
It has largest population <strong>of</strong> schedule casts <strong>of</strong> about 22.8% against state<br />
average <strong>of</strong> 16.7%.<br />
The main work force <strong>of</strong> about 75% are engaged in primary and secondary<br />
sectors and balance in allied sectors. As regards land use pattern about 70%<br />
<strong>of</strong> land is under forest and barran lands.<br />
About 64% <strong>of</strong> the inhabited villages are connected with road and the<br />
remaining villages suffer because <strong>of</strong> remoteness and higher altitudes.<br />
As regard rural electrification Uttaranchal has 76.1% electrified villages and<br />
the per capita consumption <strong>of</strong> electricity <strong>of</strong> the state is about 245.6 Kwh.<br />
However, Dehradun and Naintal have much higher consumption where as<br />
Uttarkashi has the least <strong>of</strong> 43.7 kwh consumption.<br />
3-3
CHAPTER - IV<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
TOPOGRAPHY AND GEOTECHNICAL ASPECTS<br />
4.1 TOPOGRAPHY AND PHYSIOGRAPHY<br />
The terrain is highly undulating with jutting peaks, steep valleys the rivulets<br />
and tributaries cut across and negotiate the mountains with rapids and<br />
steep gradients. The major tributaries <strong>of</strong> Bhagirathi, Alakananda,<br />
Yamuna, Tons originate from the foot <strong>of</strong> glaciers and snow capped<br />
peaks. The pucca road network cover only 64% <strong>of</strong> the inhabitated<br />
villages and rest <strong>of</strong> the villages are not be covered by roads due to<br />
higher altitude and remoteness. Bhagirathi river on which Gangotri H.E.<br />
Project is located originates at the foot <strong>of</strong> the Gangotri glaciers and<br />
flow westwards further Jadhganga joins Bhagirathi from the north down<br />
stream <strong>of</strong> Gangotri H.E. Project.<br />
Present PFR studies do not envisage topographical surveys and hence<br />
this write up is confined to physiographical aspects only.<br />
4.2 REGIONAL GEOLOGY<br />
The topography <strong>of</strong> the area around the proposed scheme is located in inner<br />
parts <strong>of</strong> Lesser Himalayas and outer parts <strong>of</strong> Central Himalayan is extremely<br />
rugged. In Central Himalayan portion the E-W trending strike ridges are<br />
characterised by steep northerly dip slopes and southerly consequent<br />
escarpments. In the inner parts <strong>of</strong> Lesser Himalayan Zones, the trend <strong>of</strong><br />
ridges has been modified and controlled by the folding <strong>of</strong> rocks. The main<br />
drainage <strong>of</strong> the area is Bhagirathi River which originates form Gangotri<br />
Glacier at Gaumukh. In the upper reach, the river is fed by numerous streams<br />
such as Jadhganga, Jalandra Gad and Siam Gad. These streams appear to<br />
4 -1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
be subsequence to joints in granite. The drainage pattern in Central<br />
Crystalline country is rectangular. In the rock <strong>of</strong> Garhwal Group, the tributary<br />
streams are mainly transversal.<br />
The Bhagirathi Valley is characterized glacial and U shaped upstream <strong>of</strong><br />
Sukhi Gaumukh. A rapid down cutting by the river has formed a deep narrow<br />
gorge between Gangotri & Jangal Bridge. Downstream <strong>of</strong> Jangla, up to<br />
Jhala Bridge, the narrow gorge has been filled by sand and gravel due to<br />
the silting connected with the damming <strong>of</strong> river at Sukhi by a landslide.<br />
Further downstream <strong>of</strong> Suklhi, the true pr<strong>of</strong>ile <strong>of</strong> valley has been masked as a<br />
result <strong>of</strong> massive landslides. The rock <strong>of</strong> the area have been grouped in to<br />
Garhwal Group, Central Crystalline and the meta sedimentaries, possibly<br />
equivalent to Martloi Formation by Kumar, Agarwal and Mukerjee (1969-79).<br />
The tectonic sequence observed in the area is as follows:<br />
NORTH<br />
Meta-sedimentaaries Black slates, garnet mica schist, quartz-biotite<br />
schist, garnet-mica schist, banded augen gneiss<br />
(Martoli Formation)<br />
------------------- FAULT-------------<br />
Central Crystallines Kyanite-garnet-mica<br />
schist and inter bedded augen and porphyritic<br />
gneiss, banded augen gneiss and garnet mica<br />
schist containing tourmaline, migmatite zone <strong>of</strong><br />
mica schist gneiss, granite, amphibolite and<br />
marble/calc-silicate.<br />
4 -2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
- - - - - - - - - - - -MAIN CENTRAL THRUST (MCT)- - - - - - - - - - - - -<br />
Garhwal Group Upper massive quartzite, white to light grey and<br />
green coloured, fine grained to gritty, occasionally<br />
schistose, current and graded bedded.<br />
Metavolcanics- occasionally with pillow lava<br />
structure, lenticular limestone/dolomitewith slate<br />
and minor quartzite; Lower quartzite and slate.<br />
4.3 GEOLOGICAL FEATURES OF THE <strong>PROJECT</strong> COMPONENTS<br />
The Gangotri Hydro-electric scheme envisages utilisation <strong>of</strong> 18.19 cumec<br />
rated discharge and 327 m river bed drop available in the river Bhagirathi,<br />
downstream <strong>of</strong> the Gangotri shrine and a power house at a place near the<br />
confluence <strong>of</strong> Jadhganga. For this, it is proposed to construct a diversion<br />
dam <strong>of</strong> low height at a location about 2.5 Km downstream <strong>of</strong> the Gangotri<br />
shrine. For diverting water into a 5.20 Km long tunnel on the right bank <strong>of</strong><br />
river Bhagirathi and a power house also on the same bank <strong>of</strong> the river, just<br />
upstream <strong>of</strong> the place near the confluence.<br />
At the proposed diversion site, located just about a Km downstream <strong>of</strong> the<br />
confluence <strong>of</strong> the Rudugaira gad, the river Bhagirathi flows in the direction<br />
from S 65 0 E to N 65 0 W direction through a very tight nearly “U”-<br />
Shaped gorge, carved through tourmaline granite traversed by pegmatite<br />
veins which is designated as Gangotri granite. The granite is generally white<br />
in colour with dark-coloured laths and specks <strong>of</strong> tourmaline seen very<br />
prominently. The granite are intruded into the granite gneiss <strong>of</strong> the Central<br />
Crystalline Group which is the country rock in the area. The contact<br />
between the two types <strong>of</strong> rock occurring in the area, i.e., the tourmaline<br />
4 -3
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
granite and the gneiss occurs downstream <strong>of</strong> the Jangla bridge about 10-12<br />
Km downstream <strong>of</strong> the proposed dam site. The diversion structure is located<br />
at bed level <strong>of</strong> EL 2965 m and , consequently may face problems <strong>of</strong> snow ice<br />
cover and avalanches during the winter months.<br />
The base width <strong>of</strong> the gorge <strong>of</strong> the river Bhagirathi at the proposed diversion<br />
site, which may be <strong>of</strong> the order <strong>of</strong> 30-40 m only is completely occupied by<br />
the river water and both the banks <strong>of</strong> the gorge rise very steeply upto about<br />
50-60m on the right bank and upto a little farther higher elevation on the left<br />
bank. Thereafter, both the banks are for some distance much gentler and<br />
occupied by detached/transported blocks <strong>of</strong> rocks mixed with soil and<br />
support a dense forest which continues farther higher up. This flatish break<br />
in the pr<strong>of</strong>ile on the banks <strong>of</strong> the gorge appears to mark the pavement (floor)<br />
<strong>of</strong> the Gangotri glacier, which now terminates at Gaumukh, around 19 Km<br />
upstream <strong>of</strong> the proposed diversion site, but is believed to have extended in<br />
the past geological times to many kilometers downstream <strong>of</strong> the proposed<br />
barrage site. The pavement <strong>of</strong> the erstwhile glacier is clearly and<br />
continuously seen down to the Jangla bridge, 5-6 Km farther downstream<br />
<strong>of</strong> Bhaironghati.<br />
The granite occurring at the proposed diversion site is pr<strong>of</strong>usely jointed and<br />
many <strong>of</strong> the joints are distinctly open. In regard to the depth <strong>of</strong> overburden is<br />
the river section at the proposed dam site, it is very difficult to guess a<br />
hazard. Nevertheless, in view <strong>of</strong> the well-known past glacial history <strong>of</strong> the<br />
river, the depth <strong>of</strong> overburden therein may be considerable. It is suggested<br />
that for the present, especially for the purpose <strong>of</strong> the PFR studies, the depth<br />
<strong>of</strong> overburden in the river bed at the dam site may be assumed to be <strong>of</strong><br />
the order <strong>of</strong> over 10-15 m.<br />
4 -4
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The steep gorge <strong>of</strong> the river at the diversion site is being continuously<br />
undercut by the river Bhagirathi. Cutting/erosion at the toe <strong>of</strong> the gorge<br />
results is gravitational adjustments along divisional planes in the rocks on<br />
the banks. This phenomenon is commonly referred to as slumping. It is<br />
feared that on both the banks <strong>of</strong> the river at the diversion site, The extent <strong>of</strong><br />
slumping would be considerable, as is also indicated by the presence <strong>of</strong><br />
open joints on the banks.<br />
In order to tie the diversion structure on to the firm rock, the slumped<br />
rock on both the banks would have to be stripped. The stripping may be <strong>of</strong><br />
the order <strong>of</strong> 10-15 m at the HFL <strong>of</strong> the river and around 25-30 m at the<br />
crest level <strong>of</strong> the spillway. This operation would have to be undertaken with<br />
simultaneous planning for stabilization <strong>of</strong> bank above the stripped section.<br />
The stripping <strong>of</strong> the banks <strong>of</strong> the river in the gorge would, no doubt, increase<br />
its width and provide some additional space at the base <strong>of</strong> the gorge.<br />
However, it would still remain quite narrow and may not permit the<br />
sedimentation / de-silting structure to be located on the surface. Therefore,<br />
the structure may have to be located underground on the right bank. The<br />
highly jointed nature <strong>of</strong> the granite would necessitate consolidation as well<br />
as certain grouting in the bed and banks <strong>of</strong> the river for controlling<br />
foundation and abutment leakage.<br />
The 5.20 Km long HRT from the diversion structure to the surge shaftpower<br />
house is aligned in the direction S60 0 E - N60 0 W direction. It is likely<br />
to be driven through the highly jointed Gangotri granite in its entire length.<br />
It is hoped that the granite occurring at the tunnel – grade would have lesser<br />
number <strong>of</strong> joints that are seen on the surface. Further evaluation <strong>of</strong> likely<br />
rock condition along the proposed tunnel would have to be undertaken<br />
during the next stage <strong>of</strong> the project planning.<br />
4 -5
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The power house <strong>of</strong> the scheme is proposed to be located on the right bank <strong>of</strong><br />
river Bhagirathi, just upstream <strong>of</strong> the Jadhganga confluence. At the<br />
proposed location gorges <strong>of</strong> both the rivers Bhagirathi and Jadhganga are<br />
very narrow and steep. Consequently, there is no space for locating the<br />
power house on the surface. Therefore, the structure would have to be<br />
located underground in the Gangotri granites, which occurs in the area.<br />
The granite is traversed by several well-developed joints. The orientation <strong>of</strong><br />
the joints will have to be studied in detail and a suitable orientation for<br />
locating the power house cavity would have to decided. The orientation <strong>of</strong><br />
the tail race tunnel from the power house would also have to be decided in a<br />
similar fashion. On the basis <strong>of</strong> a preliminary evaluation <strong>of</strong> the joints is the<br />
granite, it appears that a NE – SW Orientations <strong>of</strong> the power house and the<br />
tail race channel would be a favorable direction with respect, to the joints is<br />
the granite. However, this would have to be confirmed/revised on the basis<br />
<strong>of</strong> joints actually encountered in an exploratory drift which could be made at<br />
the power house site during the next stage <strong>of</strong> studies for the scheme.<br />
4.4 GEOTECHNICAL APPRAISAL<br />
The head on Bhagirathi up to its confluence with Jadhganga is proposed to be<br />
utilized through the proposed Gangotri Hydroelectric project which is<br />
upstream most project on Bhagirathi River, followed by Bhairoghati and<br />
Harsil projects. The project envisages construction <strong>of</strong> diversion structure<br />
across Bhagirathi just downstream <strong>of</strong> confluence <strong>of</strong> Bhagirathi and Rudiguira<br />
Gad. The river in this reach flows through granitic rock which have intruded in<br />
to Martoli and Ralen Formations. The river has cut a deep gorge in this reach.<br />
The valley widens near Jangla, probably due to change in lithology. The<br />
granite is mainly biotite granite and tourmaline granite. These - have been<br />
correlated with Tourmaline Granite <strong>of</strong> Badrinath. The granites are jointed and<br />
intruded by pegmatite, aplite and quartz veins. The valley is narrow and<br />
4 -6
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
typical V-shaped near the diversion site. The thickness <strong>of</strong> overburden in the<br />
river bed and stability <strong>of</strong> abutment may be assessed before finally locating the<br />
diversion site. The water conductor system envisages the construction <strong>of</strong><br />
5.20 km long head race tunnel. It is expected to be excavated through biotite<br />
granite which is intruded by aplite, pegmatite and silica veins. The biotite<br />
granite is expected to provide fair to good tunneling media in general except<br />
for reaches where joints are closely spaced and shear and local faults are<br />
encountered. The problem may be become more acute if these zones are<br />
water charged. The powerhouse is proposed to be located near the<br />
confluence. It is suggested that the structure be located in the area where<br />
adequate space for locating the structure and its appurtenance is available<br />
otherwise it may be designed as an underground structure. This geotechnical<br />
appraisal is based on the regional geological set up.<br />
4.5 SEISMOTECTONICS AND SEISMICITY<br />
Seismotectonically, the project are is located in Main Himalayan 'Seismic<br />
Zone demarcate by the Main Boundary Thrust (MBT) in south and downdip<br />
influence zone <strong>of</strong> the Main Central Thrust (MCT) in north, demonstrating<br />
predominantly thrust type <strong>of</strong> fault plane mechanism. It has been interpreted by<br />
Narula (1991) that the strain buildup in different sectors in this, domains takes<br />
place at different locales and in Utarkashi-Kumaon sector, this is concentrated<br />
around the MCT as evidenced by the clustering <strong>of</strong> the seismic events in this<br />
subdomain to be around this structural dislocation. The seismic status <strong>of</strong> MCT<br />
has been a subject <strong>of</strong> interest for quite some time, though direct geological<br />
evidences <strong>of</strong> neotectonic activity have not been recorded in the area.<br />
According to Narula (1991), the project area falls in Garhwal Seismic Block<br />
which, is constrained by Alaknanda tectonic flux fault in the east and Kautir or<br />
Kinnaur Faults in west. This domain contains another tectonic flux fault which<br />
is located in the project area.<br />
4 -7
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
MBT & MCT are the two major dislocation features <strong>of</strong> significance in the<br />
project area located about 20 km to 35 km in the southern direction.<br />
Seismically the project area traverses through highly active Himalayan<br />
seismic belt and falls in seismic zone V <strong>of</strong> the seismic zoning map <strong>of</strong><br />
India [ IS 1893 (Part-I): 2002]. Therefore, a suitable seismic factor would<br />
have to be adopted for designing the structures in the area.<br />
4.6 SEISMIC REFRACTION SURVEY<br />
The seismic refraction survey was conducted along the dam axis to ascertain<br />
thickness <strong>of</strong> overburden and quality <strong>of</strong> bedrock. The both the Banks are<br />
massive rock in nature and almost as a vertical cliff. To investigate the<br />
overburden in river portion, as per the requirements <strong>of</strong> the investigations, it<br />
was considered mandatory to carry out one seismic spread along the river, to<br />
have maximum depth penetration. Due to massive rock and high slopes, and<br />
an extremely narrow width <strong>of</strong> river, the normal spreads fails to provide<br />
adequate penetration below riverbed.<br />
The seismograph used was Model BISON, GALILEO with liquid crystal<br />
display, graphic plotter, 3.5 inch disk drive, 486 CPU, IFP amplifiers and 16 bit<br />
A/D converters and RS – 232 interface. Moving-coil type digital grade vertical<br />
geophones, natural frequency 14 Hertz were used as sensors.<br />
The processing involves picking the first arrivals, input <strong>of</strong> data with geophone<br />
elevations and first arrivals, and final interpretation for velocity model. Latest<br />
sodtware SeisOptPocket was used for picking the first arrivals. Latest<br />
advanced s<strong>of</strong>tware has been used for interpretation and velocity model<br />
computation <strong>of</strong> data obtained.<br />
4 -8
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The velocity model has been developed using information from both the<br />
spreads and velocity measurements carried out on the rock face. The findings<br />
duly interpreted from velocity model are given as section.<br />
Seismic Refraction Survey conducted at Gangotri site depicts the presence<br />
<strong>of</strong> rock line at shallow depth near the banks but the rock line goes below<br />
upto 5-10 meters from the river bed.<br />
Based on velocity model three broad layers can be classified, a thick<br />
alluvium, an intermediate layer and rock with different units <strong>of</strong> subsurface<br />
layers (Plate-4.1).<br />
4 -9
5.1 GENERAL<br />
CHAPTER - V<br />
HYDROLOGY<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The Ganga river is one <strong>of</strong> the holiest rivers in India and many temples and<br />
religious places are situated on its banks right from its origin to its confluence<br />
near Sagar Island with Bay <strong>of</strong> Bengal. It drains an area <strong>of</strong> 8.61 lakh sq km<br />
and the basin is one <strong>of</strong> the most fertile basins <strong>of</strong> the country.<br />
Bhagirathi and Alaknanda are the two major tributaries <strong>of</strong> Ganga which<br />
originates from Gangotri and Kamet glaciers in Uttarkashi and Chamoli<br />
districts respectively <strong>of</strong> Uttaranchal state. Bhagirathi originates at an<br />
elevation <strong>of</strong> 7010 m while Alaknanda rises at an elevation 7800m. Both the<br />
Bhagirathi and Alaknanda rivers join at Deoprayag and thereafter it is known<br />
as Ganga. Jadhganga is the first major tributary <strong>of</strong> Bhagirathi originating<br />
near Tagala at an elevation 5300m and joins Bhagirathi at Bhaironghati. The<br />
river has very steep slopes in upper reaches and most <strong>of</strong> the area is covered<br />
by permanent snow and glaciers. Due to steep slopes and area covered by<br />
snow, there exists considerable quantity <strong>of</strong> perennial flow and as such have a<br />
large potential for hydropower development, though irrigation may not be<br />
feasible due to non existence <strong>of</strong> command area. CEA had identified several<br />
hydro electric sites in the basin. The Gangotri Hydro-Electric Project<br />
(CA=944sq km) is the first project identified on Bhagirathi river. The<br />
catchment area map <strong>of</strong> the project is shown in Plate No. 5.1<br />
This report contains the results <strong>of</strong> the Hydrological studies made for Gangotri<br />
H.E. scheme. The detailed studies in respect <strong>of</strong> water availability and Design<br />
5-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
flood are available in the report “ Hydrological studies – volume I, Ganga<br />
basin” September, 2003.<br />
5.2 HYDROMETEOROLOGICAL DATA<br />
No rainfall and discharge data at Gangotri site is available. However,<br />
observed discharges from 1971 – 72 at Uttarkashi (CA=4504 sq km) are<br />
available. The site is maintained by CWC. Discharge data for longer periods<br />
are available at 17 G&D sites (13 CWC sites and 4 States Governments) in<br />
the region, which are much downstream <strong>of</strong> Gangotri site. The data availability<br />
is given as under which has been utilised for developing the Regional Model.<br />
Table -1<br />
Sl. Name <strong>of</strong> River Organisation Period<br />
No Station<br />
1 Tehri Bilanganga CWC 1975-76 to 2001-02<br />
2 Joshimath Alakananda CWC 1975-76 to 2001-02<br />
3 Tehri Bhagirathi CWC 1975-76 to 2001-02<br />
4 Deoprayag Ganga CWC 1975-76 to 2001-02<br />
5 Maror Nayar CWC 1975-76 to 2001-02<br />
6 Deoprayag Bhagirathi CWC 1975-76 to 2001-02<br />
7 Rudraprayag Mandakini CWC 1975-76 to 2001-02<br />
8 Rishikesh Ganga CWC 1975-76 to 2001-02<br />
9 Rudraprayag Alakananda CWC 1975-76 to 2001-02<br />
10 Nandkesri Pinder CWC 1994-95 to 2001-02<br />
11 Chandrapuri Mandakini CWC 1976-77 to 2001-02<br />
12. Karnprayag Pindar CWC 1976-77 to 2001-02<br />
5-2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Sl. Name <strong>of</strong> River Organisation Period<br />
No Station<br />
13 Uttarkashi Bhagirathi CWC 1971-72 to 2001-02<br />
14 Raiwala Ganga State Govt. 1946-47 to 1983-84<br />
15 Maneri Bhagirathi State Govt. 1964-65 to 1984-85<br />
16 Lambagarh Alakananda State Govt. 1969-70 to 1990-91<br />
17 Tapovan Alakananda State Govt. 1973-74 to 1981-82<br />
Long term flood peaks are available at Raiwala on Ganga (1901 to 1992),<br />
Tehri on Bhagirathi (!963 to 1978), Maneri at Bhagirathi (1964 to 84) besides<br />
at G&D sites on Alaknanda, Sarda, Tons and Yamuna rivers.<br />
5.3 ESTIMATION OF WATER AVAILABILITY<br />
5.3.1 Regional Model<br />
The proposed Gangotri site is in high altitude area whose major portion <strong>of</strong> the<br />
catchment (a small fraction <strong>of</strong> the nearest observed G&D catchment area)<br />
area is covered by snow and glaciers. As such the traditional method <strong>of</strong><br />
rainfall run <strong>of</strong>f or run <strong>of</strong>f-run <strong>of</strong>f model may not be feasible due to non<br />
availability <strong>of</strong> requisite data. A regional model has been developed on 10 daily<br />
basis utilising the 10 daily flows <strong>of</strong> each 17 G&D sites (CWC and State<br />
Government) together with the mean annual catchment rainfall and the<br />
percentage <strong>of</strong> area intercepted by glacier, snow and forest. The general<br />
format <strong>of</strong> the linear model for the G&D site is as under:<br />
q = K + a * s + b * g + c * f + d * (RF)<br />
or Q = K * (CA) + a * (SA) + b * (GA) + c * (FA) + d * (RF) * (CA)<br />
Where, q = Average specific yield <strong>of</strong> G&D site<br />
5-3
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Q = Average yield <strong>of</strong> G&D site<br />
CA = Total catchment area in sq. km<br />
GA = Total area under glacier in sq.km<br />
SA = Intermediate area between glacier and permanent<br />
snow line in sq.km<br />
FA = Total forest area in sq.km<br />
RF = Mean annual catchment rainfall in mm<br />
K, a, b, c, d = Constant <strong>of</strong> the model<br />
s = percentage <strong>of</strong> net snow area to total catchment<br />
area<br />
g = percentage <strong>of</strong> glacier area to total catchment area<br />
f = percentage <strong>of</strong> forest area to total catchment area<br />
The linear regional model was developed for Bhagirathi and Alaknanda basin.<br />
After studying the physical parameters responsible for run <strong>of</strong>f for each<br />
catchment upto G&D site, the one parameter, two parameter, three parameter<br />
and four parameter linear models have been developed for each 10 daily<br />
block period. The one parameter model considers the specific yield <strong>of</strong> G&D<br />
sites Vs catchment area, whereas the remaining models consider the<br />
catchment area, glacier area, forest area, net snow area, mean annual<br />
catchment rainfall and the specific yield. After attempting the various<br />
permutations and combinations, the model which gives the maximum<br />
correlation coefficient was selected for estimating the dependable flows at<br />
Gangotri site.<br />
5.3.2 Dependable flows<br />
Using the most suitable regional model developed for each 10 daily block, the<br />
90%, 50% dependable flows and the average flows have been computed for<br />
the Gangotri project site (CA=944 sq. km) as under:<br />
5-4
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Units:m 3 Items June I June II<br />
/sec<br />
June III July I July II July III Aug I Aug II Aug III<br />
90% 25.2 33.0 42.6 38.6 46.3 46.2 35.8 34.9 38.7<br />
50% 47.7 62.3 75.8 73.1 91.5 68.8 66.6 57.6 63.6<br />
Average 51.7 63.7 80.6 80.3 94.2 72.0 67.1 58.2 64.9<br />
Sep I Sep II Sep III Oct I Oct II Oct III Nov I Nov II Nov III<br />
90% 27.9 21.9 14.3 12.1 7.9 8.0 6.4 5.9 5.3<br />
50% 52.1 40.3 23.2 18.7 13.1 12.7 10.7 9.5 8.2<br />
Average 54.7 42.2 24.9 19.7 14.6 13.7 11.6 10.0 8.8<br />
Dec I Dec II Dec III Jan I Jan II Jan III Feb I Feb II Feb III<br />
90% 4.8 4.5 3.4 4.2 3.7 3.4 3.2 2.8 2.6<br />
50% 7.9 7.5 6.5 6.3 6.0 5.3 4.9 4.6 4.6<br />
Average 8.4 8.1 7.1 6.5 6.1 5.4 5.2 4.7 4.7<br />
Mar I Mar II Mar III Apr I Apr II Apr III May I May II May III<br />
90% 3.6 3.4 3.7 3.5 3.5 6.1 10.6 12.9 18.7<br />
50% 6.0 6.2 6.7 6.2 7.6 12.4 18.6 25.1 33.4<br />
Average 6.4 6.7 7.0 6.5 7.9 13.3 19.9 27.4 35.1<br />
5.4 ESTIMATION OF DESIGN FLOOD<br />
Since the continuous discharge data for rainy season and concurrent rainfall<br />
is not available, it is not possible to estimate the design flood by unit<br />
Hydrograph method.<br />
The peak flood discharge at Gangotri site has been estimated based on the<br />
methodology indicated in the Flood Estimation Report for Western Himalayas,<br />
Zone 7 <strong>of</strong> CWC and Regional Frequency analysis (based on 5 and 10 G&D<br />
sites) and Synthetic unit hydrograph approach based on Snyder’s method.<br />
The results <strong>of</strong> the study are as under:<br />
5-5
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Methodology Return Period<br />
100 years/ SPF<br />
(m 3 /Sec)<br />
i) Flood Estimation Report, CWC<br />
2452<br />
ii) Regional Frequent Analysis (5 G&D sites).<br />
Iii) Regional Frequency Analysis (10 G&D sites).<br />
iv) Snyder’s Method<br />
v) Recommended Design flood value.<br />
1824<br />
2280<br />
1592<br />
2500<br />
As furnished above design flood (SPF) <strong>of</strong> 2500 m 3 /sec is recommended for<br />
studies.<br />
5.5 SEDIMENTATION<br />
Since Gangotri site HE scheme is identified as run <strong>of</strong> the river scheme, the<br />
sedimentation studies are not considered necessary as in the case <strong>of</strong> storage<br />
structures. However, based on the experience gained at various <strong>Power</strong><br />
Stations in that valley, it is proposed to exclude silt particles <strong>of</strong> size 0.20 mm<br />
and above from the water before it enters the power house. This aspect will<br />
be considered while designing the civil structures.<br />
5-6
5.6 Observations <strong>of</strong> CWC<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The draft report <strong>of</strong> this project was submitted to CEA for perusal during<br />
October 03. The observations received from CWC on the Hydrological studies<br />
<strong>of</strong> this project and the replies for above observations, submitted by WAPCOS<br />
are enclosed as Appendices 1.1 and 1.3.<br />
5-7
6.1 INTRODUCTION<br />
CHAPTER – VI<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
CONCEPTUAL LAYOUT AND PLANNING<br />
Gangotri H.E. Project is proposed as Run-<strong>of</strong>f-the river scheme on the river<br />
Bhagirathi to tap its hydropower potential. The diversion structure is located<br />
1.0 km downstream <strong>of</strong> confluence <strong>of</strong> Rudugar Gad from the left bank or 2.5<br />
km before the holy Gangotri shrine in Uttarkashi district. The project<br />
envisages to divert the water <strong>of</strong> Bhagirathi into water conductor system by<br />
means <strong>of</strong> a diversion structure (a concrete gravity dam) across the river. The<br />
water conductor system comprises <strong>of</strong> an intake, underground desilting<br />
chambers followed by a 5.2 km long head race tunnel <strong>of</strong> 2.5 m diameter<br />
(D-shaped), a surge shaft <strong>of</strong> 6 m diameter, a pressure shaft <strong>of</strong> 2.0 m dia to<br />
feed one unit <strong>of</strong> <strong>55</strong> <strong>MW</strong> housed in an underground power house. A 450 m<br />
long tail race tunnel discharges the water back into the river Bhagirathi just<br />
upstream <strong>of</strong> another proposed Bhaironghati H.E. scheme head works.<br />
6.2 LAYOUT STUDIES<br />
6.2.1 The Bhagirathi river rises at EL 7010 m and falls steeply untill Gaumukh at EL<br />
4000 m to Gangotri, the river bed fall is about 1000 m in 50 km stretch.<br />
Thereafter, it runs in a gentle to steep slopes in various stretches and is joined<br />
by Jadhganga at EL 2625.0 m.<br />
As per CEA re-assessment studies the hydro-potential <strong>of</strong> river Bhagirathi is<br />
proposed to be exploited by potential schemes in a cascade development and<br />
the projects serially planned are Gangotri, Bharion Ghati and Harsil Schemes<br />
now proposed for PFR studies.<br />
6-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
6.2.2 The entire stretch <strong>of</strong> river between proposed diversion site <strong>of</strong> Gangotri<br />
scheme to power house site was inspected and it was observed that both the<br />
banks <strong>of</strong> Bhagirathi at a reach 2.5 kms d/s <strong>of</strong> the Gangotri shrine are occupied<br />
by massive steep rocky slopes. The pondage created at this site selected<br />
shall be within safe levels at the Gangorti Shrine.<br />
6.2.3 As per CEA proposal, the diversion site for Gangotri H.E. scheme is proposed<br />
about 2.5 km d/s <strong>of</strong> Gangotri shrine at bed level 2960.0 m. After inspection<br />
the site for diversion site was planned to be shifted upstream as much as<br />
possible so that additional head could be utilized for power generation without<br />
effecting the Gangotri Shrine. The site selected was at river bed level EL<br />
2965.0 and 50 m further up stream <strong>of</strong> the earlier CEA site.<br />
6.3 RIVER DIVERSION WORK<br />
6.3.1 The aspect <strong>of</strong> isolating the site for construction activity in the deep river valley<br />
portion was examined for two scenarios i.e. with and without the provision <strong>of</strong><br />
diversion tunnel through abutment. As the diversion site is located in a<br />
narrow valley it was not found practical to isolate the construction area without<br />
the provision <strong>of</strong> diversion tunnel.<br />
6.3.2 A diversion tunnel <strong>of</strong> 4m diameter circular and 400 m long is proposed along<br />
right bank to divert flood <strong>of</strong> 50 cumecs for the construction <strong>of</strong> dam &<br />
appurtenant works. However, during monsoon season, excess discharges<br />
beyond the capacity <strong>of</strong> diversion tunnel is expected to pass over the c<strong>of</strong>fer<br />
dam and the constructed portion <strong>of</strong> the dam. The tunnel inlet is proposed to<br />
be provided with a gate <strong>of</strong> size 4.50 m x 4.50 m which will be operated by<br />
means <strong>of</strong> a rope drum hoist at the time <strong>of</strong> plugging the diversion tunnel.<br />
Suitable c<strong>of</strong>fer dams located approximately 100 m u/s & 150 m d/s <strong>of</strong> the<br />
dam axis are proposed. The u/s c<strong>of</strong>fer dam will be 7 m high with 7.0 m base<br />
6-2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
width while the d/s c<strong>of</strong>fer dam will be 6 high with base width <strong>of</strong> 6.0 m. These<br />
structures are proposed <strong>of</strong> masonry type with colcrete.<br />
6.4 DIVERSION DAM<br />
6.4.1 The type <strong>of</strong> dam to be adopted i.e Earth dam or concrete dam is governed by<br />
the topographical, geotechnical and availability <strong>of</strong> construction materials<br />
considerations. The requisite construction materials for Earth dam alternative<br />
are not expected to be available in the vicinity <strong>of</strong> project area and also not<br />
possible for the narrow gorge. In view <strong>of</strong> the rock exposures along steep<br />
valley on both the banks <strong>of</strong> the river and shallow thickness <strong>of</strong> overburden in<br />
the river bed are anticipated. Accordingly a concrete gravity structure with a<br />
spillway in the deeper gorge portion is proposed at this site. Concrete dam,<br />
26 m high above the deepest river bed (El 2965.0 m) 110.0 m long comprises<br />
<strong>of</strong> 7 blocks. Three overflow blocks in the deeper gorge portion are provided to<br />
pass the design flood. A foundation gallery running all along the abutment is<br />
also proposed from drainage, grouting and maintenance considerations. A<br />
downstream slope <strong>of</strong> 0.8:1 is proposed for the dam section keeping in view<br />
the seismicity <strong>of</strong> the area (zone V, as per BIS 1893)<br />
6.4.2 Reservoir<br />
Keeping in view the storage characteristics <strong>of</strong> the valley upstream, the crest <strong>of</strong><br />
spillway is proposed at El 2975.0 m. The crest <strong>of</strong> power intakes are kept 7.0<br />
m lower then the MDDL <strong>of</strong> El 2984.0 m. This is to ensure minimum water<br />
cushion requirements above the intake tunnels from air entrainment<br />
considerations. Storage to meet the diurnal peaking requirements has been<br />
provided between MDDL and FRL as it is a Run-<strong>of</strong>f the River type<br />
development. Accordingly, MDDL and FRL are proposed at El 2984.0, and El<br />
2989.0 m respectively which provide live storage <strong>of</strong> around 0.91 M cum.<br />
6-3
6.4.3 Spillway & Energy Dissipation<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
An ogee spillway with radial gates and breast wall is proposed to pass the<br />
design flood <strong>of</strong> 2500 cumecs corresponding to SPF. Three bays, each with<br />
clear opening <strong>of</strong> size 12.5 m x 14.0 m (height) are proposed to cater to design<br />
flood discharge which is inclusive <strong>of</strong> one gate for additional factor <strong>of</strong> safety in<br />
consideration <strong>of</strong> 10% <strong>of</strong> gates inoperative as per codal requirement. Radial<br />
gates will be operated by means <strong>of</strong> hydraulic hoists. Provision <strong>of</strong> stoplog<br />
gates with gantry crane is also made.<br />
Since this project is located in high altitude area (about EL 3000 m above<br />
MSL) and most <strong>of</strong> the time the reservoir water surface will be under sub zero<br />
temperature. To generate power for maximum period and for smooth running<br />
<strong>of</strong> the power plant, de-iceing arrangements are proposed to be provided.<br />
Energy dissipation is proposed through stilling basin <strong>of</strong> 35 m length.<br />
Protection works in the form <strong>of</strong> stone pitching are provided immediately<br />
downstream <strong>of</strong> stilling basin from considerations <strong>of</strong> scour and water depth.<br />
The Layout details <strong>of</strong> Dam and Spillway are shown in Drg<br />
No.WAP/PFR/<strong>GANGOTRI</strong>/1003 (R1) &1004 (R1).<br />
6.5 INTAKE AND DESILTING CHAMBER<br />
6.5.1 One intake structure is proposed on the right bank <strong>of</strong> the river upstream <strong>of</strong><br />
the Diversion structure with its invert at El 2977.0 m i.e. 2.0 m above the<br />
spillway crest level to avoid entry <strong>of</strong> rolling debris into the water conductor<br />
system during floods. One no. intake tunnel, 2.75 m dia (D-shaped) is<br />
proposed on the right bank to carry design discharge <strong>of</strong> 21.83 cumec<br />
(including 20% flushing discharge). A trashrack is proposed at the entry so<br />
6-4
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
that debris /particles exceeding 75 mm do not enter the water conductor<br />
system.<br />
6.5.2 One underground desilting chamber is provided about 120.0 metre<br />
downstream <strong>of</strong> intake structure to remove particles <strong>of</strong> size 0.2 mm and above<br />
to protect the turbine parts against erosion. The chamber proposed is <strong>of</strong> size<br />
110 m x 8 m x 9 m (depth) and is designed to achieve 90% efficiency for silt<br />
removal. The chamber is designed to pass design discharge <strong>of</strong> 21.38 cumec<br />
and is provided with a gate on downstream end to isolate for routine<br />
maintenance. The bed <strong>of</strong> the trough is provided with a longitudinal duct <strong>of</strong> 2.0<br />
m dia to remove the silt laden water through a silt flushing tunnel to the river<br />
downstream.<br />
6.6 HEADRACE TUNNEL<br />
6.6.1 The design discharge <strong>of</strong> 18.19 cumecs is carried downstream <strong>of</strong> desilting<br />
chamber through 2.5 m dia D-shaped headrace tunnel, 5.20 km long to<br />
meet the surge shaft. The alignment <strong>of</strong> the tunnel has been optimally fixed to<br />
provide adequate rock cover below the nallah crossings.<br />
6.6.2 The excavated tunnel section is proposed to be provided with suitable support<br />
system depending upon the type <strong>of</strong> rock strata met. Accordingly, the entire<br />
tunnel reach has been tentatively divided into 4 categories depending upon<br />
the type <strong>of</strong> rock i.e. Good, Fair, Poor and Very Poor. It is presumed that 20%<br />
<strong>of</strong> the tunnel reach encounters poor/very poor rock conditions while in<br />
remaining reach Good/Fair rock conditions are met. A 300 mm thick PCC<br />
lining <strong>of</strong> M20 grade concrete is proposed for the headrace tunnel. Provision<br />
for contact grouting & consolidation grouting has also been made.<br />
6-5
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The details <strong>of</strong> the Rock support system are shown in Drg. No<br />
WAP/PFR/<strong>GANGOTRI</strong>/1005 (R1).<br />
6.7 SURGE SHAFT & PRESSURE SHAFT<br />
6.7.1 An 6.0 m dia and 92.0 m high simple surge tank is proposed at the end <strong>of</strong><br />
headrace tunnel to release the effect <strong>of</strong> mass oscillations in the tunnel and to<br />
provide immediate storage requirement near the power house in case <strong>of</strong><br />
sudden acceptance <strong>of</strong> load. The bottom elevation <strong>of</strong> surge tank has been so<br />
fixed as to provide adequate water cushion below the minimum down surge<br />
level. Similarly, it is ensured that maximum upsurge level is contained within<br />
the surge shaft.<br />
The surge shaft is likely to be excavated in tourmaline granite rock formations.<br />
It is proposed to provide 75 mm thick shotcrete with 4m long rock bolt at<br />
suitable intervals. Reinforced concrete lining (M25 grade) 1.0m thick, is<br />
proposed in the deeper reaches reducing to 0.6 m thickness in the upper<br />
portion. Provision for consolidation grouting & contact grouting is also made<br />
to ensure proper consolidation <strong>of</strong> rockmass around the surge shaft.<br />
6.7.2 A vertical pressure shaft <strong>of</strong> size 2.0 m diameter is proposed downstream <strong>of</strong><br />
surge shaft keeping in view the adequacy <strong>of</strong> horizontal and vertical rock cover<br />
as per codal requirement. Pressure shaft drops from El 2928.0 m to<br />
El 2634.50 m in line with the center line <strong>of</strong> distributor. The horizontal portion<br />
<strong>of</strong> pressure shaft is to feed to 1 unit <strong>of</strong> <strong>55</strong> <strong>MW</strong>.<br />
The pressure shaft liner is designed taking into account 30% rock participation<br />
and 40% as water hammer head. High tensile steel <strong>of</strong> grade A-517 is<br />
proposed for liner so as to restrict the liner thickness to reasonable limits to<br />
6-6
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
obviate the need for stress relieving. Liner thickness varies from 8 mm to 20<br />
mm in the pressure shaft reach.<br />
6.8 POWER HOUSE<br />
The underground power house is proposed as the river banks are steep and<br />
there is paucity <strong>of</strong> space for surface power house. The underground power<br />
house complex comprises <strong>of</strong> one cavern <strong>of</strong> 20.5 m width. The machine<br />
cavern is 20.5 m wide, it house 1 unit <strong>of</strong> <strong>55</strong> <strong>MW</strong> along with 15 m long service<br />
bay and 40 m x 6 m auxiliary room. The generator floor level is kept at EL<br />
2642.0 Centre line <strong>of</strong> units is at EL 2634.50 m and invert level <strong>of</strong> draft tubes<br />
kept at EL 2629.50 m. EOT crane <strong>of</strong> 150/20 tonnes capacity shall be<br />
provided at crane beam level at EL 2650.0 m and travel up to service bay end<br />
also. One main inlet valve is also provided. The transformer bay is inside the<br />
power house cavern and is 6 m wide to accommodate transformer and GIS.<br />
A cable carriage is provided from this cavern to the outdoor switchyard at the<br />
ro<strong>of</strong> level. The draft tubes shall be provided with a draft tube gate operated<br />
by a gantry crane installed inside the main power house cavern. The TRT <strong>of</strong><br />
3.0 dia (D-shaped) <strong>of</strong> length 450.0 m shall have reverse slope to meet the<br />
river bed level. The power house cavern shall be approached by a main<br />
access tunnel starting from the main road.<br />
6.9 ELECTRO - MECHANICAL WORKS<br />
6.9.1 General<br />
The installed capacity would be provided by one no. Vertical Axis Francis<br />
turbine driven generating unit <strong>of</strong> <strong>55</strong> <strong>MW</strong>. It is proposed to provide spherical<br />
type Inlet Valve for each turbine, which would be accommodated in the<br />
powerhouse cavern.<br />
6-7
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The generation voltage <strong>of</strong> 11 kV would be stepped up to 220 kV through three<br />
single phase 20 MVA, 11/220 kV ODWF type unit step up transformers<br />
located in powerhouse cavern. The 11 kV phase isolated phase busducts<br />
would connect the 11 kV generator terminals with 11 kV bushings <strong>of</strong> step up<br />
transformer. The 220 kV terminals <strong>of</strong> the transformer would be connected<br />
with 220 kV Gas Insulated Switchgear (GIS) located on a floor above the<br />
transformer in powerhouse cavern.<br />
The arrangement <strong>of</strong> generating equipment, unit step up transformer, etc. is<br />
indicated in Drgs. No. WAP/PFR/<strong>GANGOTRI</strong>/1007 (R1) & 1008 (R1).<br />
The GIS would accommodate 4 bays in which 1 for generator incoming, 2 for<br />
outgoing 220 kV transmission lines and one for step down transformer. The<br />
power generated would thus be evacuated through 2 nos. 220 kV<br />
transmission lines. The single line diagram is shown in Drg. No.<br />
WAP/PFR/<strong>GANGOTRI</strong>/1009 (R1).<br />
6.10 BRIEF PARTICULARS OF EQUIPMENTS<br />
6.10.1 Turbine and Governor<br />
The upstream levels, tailrace levels and heads available for power generation<br />
are indicated below :<br />
i) Upstream Levels<br />
• FRL EL 2989.0 M<br />
• MDDL EL 2984.0 M<br />
ii) Tailrace Levels<br />
• Maximum EL 2643.0 M<br />
• Minimum EL 2641.0 M<br />
6-8
iii) Heads<br />
• Maximum net head 339.00 M<br />
• Minimum net head 332.00 M<br />
• Rated head 336.33 M<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
For this project there is a choice in selection <strong>of</strong> type <strong>of</strong> turbine to be used. The<br />
turbine could be either Francis or Pelton type. One <strong>of</strong> the important aspect<br />
which dictates the choice <strong>of</strong> turbine is the need <strong>of</strong> part load operation <strong>of</strong> the<br />
generating units. In the run <strong>of</strong> the river scheme without any pondage, Pelton<br />
wheel would be preferred as the generating units would need to be operated at<br />
part load operation depending upon the discharge available. This project is run<br />
<strong>of</strong> the river type with pondage for peaking purpose therefore both Pelton and<br />
Francis type turbine are suitable with reference to above aspect. However, based<br />
on the following main advantages, Francis type turbine, is chosen for this project :<br />
1. Francis turbine is cheaper as compared to Pelton wheel because <strong>of</strong> high<br />
speed.<br />
2. Peak efficiency <strong>of</strong> Francis turbine is higher<br />
3. Pelton wheel runner is set 3 to 4 metres above the maximum tail water<br />
level as such there is permanent loss <strong>of</strong> head in power generation.<br />
4. The silt erosion <strong>of</strong> the runner is lesser there by requiring less frequent<br />
maintenance / replacement <strong>of</strong> runner and the repair <strong>of</strong> silt eroded turbine<br />
components is easier in case <strong>of</strong> Francis turbine. This is an important<br />
aspect for the stations located in Himalayas.<br />
The turbine would be suitably rated to provide <strong>55</strong> <strong>MW</strong> at generator terminals<br />
at rated head <strong>of</strong> 336.33 M. The speed <strong>of</strong> turbine has been determined as 600<br />
RPM. The centerline <strong>of</strong> turbine runner has been set at EL 2634.5 M whereas<br />
the minimum TWL is at EL 2641.0. The governor would be electro-hydraulic<br />
6-9
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
digital PID type suitable for fully automatic control. The closing time <strong>of</strong> wicket<br />
gates would be so adjusted so as not to increase the speed rise and pressure<br />
rise more than 45% and 30% respectively under full load throw <strong>of</strong>f condition.<br />
6.10.2 Main Inlet Valve<br />
It is proposed to provide an Inlet Valve <strong>of</strong> spherical type for turbine as second<br />
line <strong>of</strong> defence in stopping the water flow to the turbine when due to governor<br />
malfunctioning, the generating unit may tend to go to runaway speed. During<br />
the time when the generating unit is under standstill condition, it would help in<br />
minimizing the water leakage through the wicket gates <strong>of</strong> the turbine. The<br />
opening <strong>of</strong> the valve would be achieved through pressurized oil servomotor<br />
and closing through counter weight.<br />
6.10.3 Generator and Excitation System<br />
The generator shaft would be directly coupled with the turbine shaft. The<br />
bearing arrangement would be semi-umbrella type with combined thrust and<br />
guide bearings below the rotor and one guide bearing above the rotor. The<br />
generator would be <strong>of</strong> the closed air circuit water-cooled type. The main<br />
parameters <strong>of</strong> the generator would be as indicated below:<br />
i) Rated out put - <strong>55</strong> <strong>MW</strong><br />
ii) <strong>Power</strong> factor - 0.9 lag<br />
iii) Speed - 600 RPM<br />
iv) Class <strong>of</strong> Insulation <strong>of</strong><br />
stator and rotor winding - Class 'F'<br />
v) Generation Voltage - 11 kV<br />
6-10
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The generators would be provided with static excitation equipment and<br />
voltage regulator. Necessary power for excitation would be provided by<br />
tapping the generator terminals.<br />
6.10.4 Unit Step-Up Transformer<br />
Three single phase 20 MVA, 11/ 220 kV transformers, would be provided for<br />
generating unit. This transformer would be located in powerhouse cavern.<br />
The 11 kV bushings <strong>of</strong> the transformer would be connected with 11 kV<br />
terminals <strong>of</strong> generator through 11 kV busduct. The 220 kV bushing would be<br />
connected with 220 kV Gas Insulated Switchgear.<br />
6.10.5 EOT Crane<br />
The heaviest equipment which the powerhouse crane is required to handle<br />
during erection and subsequently during maintenance is the generator rotor.<br />
The weight <strong>of</strong> the generator rotor has been estimated to be about 131.5<br />
tonnes. It is proposed to provide EOT crane <strong>of</strong> 150/ 20 tonnes capacity.<br />
6.10.6 Auxiliary Equipments and Systems For The <strong>Power</strong> House<br />
Following equipments for the auxiliary systems <strong>of</strong> the powerhouse would be<br />
provided:<br />
i) Cooling water system for turbines, generators, unit step up<br />
transformers etc.<br />
ii) Drainage System<br />
iii) Dewatering system<br />
iv) High pressure compressed air equipment for governor and MIV etc.<br />
v) Low pressure compressed air equipment for station services<br />
6-11
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
vi) 415 V LTAC supply system comprising station service transformers,<br />
unit auxiliary transformer, station service board, unit auxiliary boards<br />
etc.<br />
vii) D.C. supply system comprising 220 V DC battery, chargers, DC<br />
distribution boards etc.<br />
viii) Ventilation system for the power house<br />
ix) Air conditioning system for control room, conference room etc.<br />
x) Illumination system<br />
xi) Earthing system<br />
xii) Oil handling system<br />
xiii) <strong>Power</strong> and control cables<br />
xiv) Fire protection system<br />
6.11 220 KV SWITCHYARD<br />
It is proposed to provide 220 kV, Gas Insulated Switchgear located in power<br />
house cavern having 4 bays. 1 bay for generator incoming, 2 bays for 220 kV<br />
transmission lines and 1 bay for step down transformer. Double bus bar<br />
arrangement at 220 kV has been proposed.<br />
6.12 OBSERVATIONS OF CEA & CWC<br />
The Draft Report <strong>of</strong> this project was submitted to CEA for perusal during<br />
October 03. The observations from the various directorates <strong>of</strong> CWC and CEA<br />
on the civil and electrical aspects have been considered and taken care in this<br />
report. The detailing has been kept to the possible extent as the report<br />
pertains to the preliminary feasibility stage studies.<br />
6-12
7.1 GENERAL<br />
CHAPTER-VII<br />
POWER POTENTIAL STUDIES<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The power potential studies have been carried out for Gangotri Hydel<br />
Scheme. The projected power supply position for 11 th Plan also indicated<br />
that there would be shortage <strong>of</strong> peak power in Uttranchal State as well as<br />
in Northern region. The execution <strong>of</strong> this project would help in reducing<br />
the gap between supply and demand <strong>of</strong> power.<br />
This is a Run <strong>of</strong> river type development with diurnal storage for peaking<br />
purpose and would utilize a rated head <strong>of</strong> water <strong>of</strong> 336.33 m. The power<br />
house would be <strong>of</strong> Under ground type.<br />
7.2 Fixation Of FRL/MDDL<br />
The FRL <strong>of</strong> the pondage has been fixed at EL 2989.0 m so as to get<br />
adequate storage capacity for peaking operation <strong>of</strong> the plant during lean<br />
period. The MDDL <strong>of</strong> EL 2984.0 m has been fixed keeping the<br />
requirement <strong>of</strong> minimum cushion <strong>of</strong> water above the headrace tunnel<br />
(HRT) to rule out the air entrainment into the HRT. The storage at FRL is<br />
computed as 4.370 million cubic metres whereas the storage at MDDL is<br />
estimated as 3.460 million cubic metres, thus making available live storage<br />
<strong>of</strong> 0.910 million cubic metres. The levels v/s capacity characteristics <strong>of</strong> the<br />
pondage are indicated in Annex 7.1.<br />
7.3 FIXATION OF TAIL RACE WATER LEVEL (TWL)<br />
The minimum tail water level which corresponds to discharge <strong>of</strong> one<br />
generating unit at 10% load has been determined as EL 2641 m. The<br />
Maximum TWL at EL 2643 m corresponds to all the generating units<br />
running at full load.<br />
7-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
These levels, however, would need to be verified when it would be possible<br />
to prepare tail rating curve.<br />
7.4 WATER AVAILABILITY<br />
The available data <strong>of</strong> water flows on 10 daily basis has been analysed in<br />
Chapter No. 5 on “hydrology”. Water flows determined in 90% dependable<br />
year and in 50% dependable year, have been utilized for computing power<br />
benefits.<br />
7.5 TYPE OF TURBINE<br />
The specific speed <strong>of</strong> the turbine at the head 336.33 m works out to be 86<br />
which lead to the choice <strong>of</strong> Francis Turbine to be used for this station. The<br />
following efficiencies applicable for Francis turbine driven generating unit<br />
have been considered for power potential studies.<br />
- Efficiency <strong>of</strong> Turbine 93.5%<br />
- Efficiency <strong>of</strong> Generator 98.0%<br />
- Combined efficiency <strong>of</strong> Turbine<br />
and Generator 91.63%<br />
7.6 INSTALLED CAPACITY<br />
7.6.1 The power potential with different installed capacities from 30 <strong>MW</strong> to 80<br />
<strong>MW</strong> in 90% dependable year is indicated in Annex-7.2. The simulation<br />
studies have been carried out with FRL at 2989 m, MDDL at El 2984 m,<br />
losses in water conductor system as 9 m and average TWL at 2642 m. The<br />
study indicated that the firm power is 10.28 <strong>MW</strong> continuous. Considering<br />
four hours peaking, the installed capacity required would be about 61.68<br />
<strong>MW</strong>.<br />
7.6.2 For optimization <strong>of</strong> Installed Capacity, annual energy generation (kWh),<br />
Incremental Energy generation d (kWh), and ratio <strong>of</strong> Incremental energy<br />
and Incremental Installed Capacity d (kWh) /d (kW) have been computed<br />
for 90% dependable year for installed capacity varying from 30 <strong>MW</strong> to 80<br />
7-2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
<strong>MW</strong>. The results are indicated in Annex-7.3. It would be seen there from<br />
that d (kWh) /d (kW) drops steeply for increase in installed capacity from <strong>55</strong><br />
<strong>MW</strong> to 60 <strong>MW</strong>.<br />
7.6.3 Keeping in view the system requirements and analysis <strong>of</strong> Incremental<br />
energy and Incremental installed capacity, the installed capacity <strong>of</strong> <strong>55</strong> <strong>MW</strong><br />
is considered optimum. With installation <strong>of</strong> <strong>55</strong> <strong>MW</strong>, the load factor <strong>of</strong><br />
operation during lean flow period works out to be 18.69 % corresponding to<br />
4.49 hrs <strong>of</strong> peaking.<br />
7.6.4 Three are two options for number <strong>of</strong> generating units to be installed i.e.<br />
1x<strong>55</strong> <strong>MW</strong><br />
2x27.5 <strong>MW</strong><br />
The station is to be connected with large power system <strong>of</strong> Northern region<br />
and therefore outage <strong>of</strong> this station would have negligible effect on the<br />
stability <strong>of</strong> the system. Further as the scheme is provided with durinal<br />
storage, requirement <strong>of</strong> part load operation would be minimum. Further<br />
installation <strong>of</strong> one unit would be more economical as compared to two<br />
units. Considering the above, it is decided to install only one unit <strong>of</strong> <strong>55</strong> <strong>MW</strong>.<br />
The turbine would be suitably rated to provide <strong>55</strong> <strong>MW</strong> at generator terminal<br />
at rated head <strong>of</strong> 336.33 M. The speed <strong>of</strong> the turbine is determined at 600<br />
RPM.<br />
7.7 RESULTS OF STUDIES<br />
Annual energy generation in 90% dependable year (Design energy) and in<br />
50% dependable year have been computed for installed capacity <strong>of</strong> <strong>55</strong> <strong>MW</strong><br />
(1x<strong>55</strong> <strong>MW</strong>) and are indicated in Annexures 7.2 and 7.4 respectively. The<br />
results are also briefly indicated below.<br />
7-3
Particulars 90% dependable<br />
year<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
50% dependable<br />
year<br />
Annual Energy Generation (Gwh) 264.76 327.7<br />
<strong>MW</strong> continuous 10.28 17.0<br />
Average annual load factor 54.95 68.02<br />
Load factor in lean flow months 18.69 % 30.91 %<br />
The design energy computation have been carried out and indicated in<br />
Annexure 7.5. The design energy 256.64 GWh would be considered for<br />
financial evaluation. The live storage available with FRL at EL 2989.0 m and<br />
MDDL at 2984.0 m would be 764.215 <strong>MW</strong>h (0.91 Million cubic meters)<br />
whereas the storage required for peaking operation works out 246.72 <strong>MW</strong>h.<br />
Thus sufficient storage is available for peaking operation <strong>of</strong> the station.<br />
7.8 CONCLUSIONS<br />
The power potential studies carried out indicate that installed capacity <strong>of</strong> <strong>55</strong><br />
<strong>MW</strong> comprising one unit <strong>of</strong> <strong>55</strong> <strong>MW</strong> would be required for this Hydel scheme to<br />
derive optimum power benefits. This station would afford generation <strong>of</strong><br />
264.76 Million units in a 90% dependable year.<br />
7.9 RECOMMENDATIONS FOR FURTHER STUDIES<br />
7.9.1 At DPR stage, based on the data available <strong>of</strong> topographic survey, tail race<br />
rating curve should be evolved so that in energy computations the head<br />
utilized for power generation is corrected with the change in tail race level<br />
corresponding to discharge. In the present study, tailrace level was<br />
considered constant.<br />
7.9.2 The storage at FRL and MDDL should be computed with more accuracy<br />
based on the data <strong>of</strong> topographic survey.<br />
7-4
CHAPTER VIII<br />
POWER EVACUATION<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
8.1 APPRAISAL OF EXISTING POWER EVACUATION FACILITIES<br />
The Project is located at latitude 31-01-29 (D-M-S) North and longitude 78-<br />
52-17.5 (D-M-S) East. The installed capacity <strong>of</strong> Uttaranchal State is 1286.15<br />
<strong>MW</strong> as on March 2003. Its peak demand has been estimated as 771 <strong>MW</strong><br />
whereas the met peak is 705 <strong>MW</strong> in the present scenario. This amounts to<br />
deficit <strong>of</strong> 66 <strong>MW</strong> (8.56%). Accordingly, energy requirement is 3774 MU<br />
against the available energy <strong>of</strong> about 3670 MU. This depicts deficit <strong>of</strong> 104<br />
MU (2.8%). For the purpose <strong>of</strong> evacuation <strong>of</strong> power pooling has been<br />
proposed for various Hydro Electric <strong>Power</strong> Projects. As per the geographical<br />
locations the following proposed Hydel Projects lie between the longitude<br />
78.5 o N to 79.5 o N namely Harsil, Bhaironghati, Gangotri, Jadhganga, Karmoli<br />
Hydro <strong>Power</strong> Projects. The next group <strong>of</strong> Hydro Electric Projects which lie<br />
between longitude 79.3 o N to 80 o N are Badrinath, Gohana Tal, Rishiganga II,<br />
Rishiganga I, Jelum Tamak, Deodi, Devasari Dam and Malari Jelum.<br />
Whereas in the next series the Hydro Electric Projects which lie between<br />
longitude 80 o to 81 o N are Mapang Bogudiyar, Sirkari Bhyol Bogudiyar, Sirkari<br />
Bhytol Rus Bagar, Khasiya Barah, Khartoli Lumti Talli, Kalika Dantu, Garba<br />
Tawaghat, Sobala Jhimrigaon, Sela Urthing, Chhanger Chal, Bokang Beiling.<br />
The power map <strong>of</strong> Uttranchal as on 1/1/2002 is shown at Annex-8.1.<br />
8.2 PROPOSED EVACUATION SYSTEM TO NEAREST FACILITY<br />
A map has already been prepared indicating various proposed Hydro Electric<br />
Projects for the purpose <strong>of</strong> preparation <strong>of</strong> prefeasibility report (PFR) indicating<br />
their locations which may be seen at Annex-8.2.<br />
8-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
8.3 ARRANGEMENT FOR EVACUATION OF POWER FROM <strong>GANGOTRI</strong> HEP<br />
The <strong>55</strong> <strong>MW</strong> power generated at 11 kV at Gangotri HEP will be stepped upto<br />
220 kV by unit step-transformers. The power would be transmitted to nearby<br />
Bhaironghati HEP. Proposed line from Gangotri HEP for evacuation <strong>of</strong> power<br />
is shown at Annexure - 8.3.<br />
8.4 ROUTE LENGTH AND COSTING OF 220 KV TRANSMISSION LINE FOR<br />
EVACUATION OF POWER FROM <strong>GANGOTRI</strong> HEP<br />
The power <strong>of</strong> this project is intended to be evacuated by proposed 220 kV<br />
D/C line to Bhaironghati HEP. The length <strong>of</strong> line has been estimated as 10<br />
km (220 kV D/C line) from Gangotri to Bhaironghati HEP. The cost <strong>of</strong> this line<br />
is estimated as Rs. 7.50 Crores. However it is proposed to keep spare<br />
space/provision for second outgoing 220 kV transmission line but its cost has<br />
not been included in E & M estimates.<br />
8-2
CHAPTER – IX<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
INITIAL ENVIRONMENTAL EXAMINATION STUDIES<br />
9.1 INTRODUCTION<br />
The Initial Environmental Examination <strong>of</strong> the proposed Gangotri hydroelectric<br />
project, has following objectives, which need to be considered during various<br />
phases <strong>of</strong> the development :<br />
• provide information on baseline environmental setting;<br />
• preliminary assessment <strong>of</strong> impacts likely to accrue during construction<br />
and operation phases;<br />
• identify key issues which need to be studied in detail during<br />
subsequent environmental studies<br />
It is essential to ascertain the baseline status <strong>of</strong> relevant environmental<br />
parameters that could be significant changes as a result <strong>of</strong> construction and<br />
operation <strong>of</strong> the project. In an<br />
Initial Environmental Examination (IEE) study, baseline status is ascertained<br />
through review <strong>of</strong> secondary data, reconnaissance survey and interaction with<br />
the locals.<br />
The Preliminary Impact Assessment conducted as a part <strong>of</strong> IEE Study, is<br />
essentially a process to forecast the future environmental scenario <strong>of</strong> the<br />
project area that might be expected to occur as a result <strong>of</strong> construction and<br />
operation <strong>of</strong> the proposed project. The key environmental impacts which are<br />
likely to accrue as a result <strong>of</strong> the proposed developmental activity are<br />
identified. Various impacts, which can endanger the environmental<br />
9-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
sustainability <strong>of</strong> a project, are highlighted for comprehensive assessment as a<br />
part <strong>of</strong> next level <strong>of</strong> environmental study.<br />
9.2 ENVIRONMENTAL BASELINE SETTING<br />
The study area covered as a part <strong>of</strong> IEE study includes the area within 7 km<br />
radius <strong>of</strong> various project appurtenances. The data was collected through<br />
review <strong>of</strong> existing documents and various engineering reports and<br />
reconnaissance surveys. The various parameters for which baseline setting<br />
has been described have been classified into physio-chemical, ecological and<br />
socio-economic aspects.<br />
9.2.1 Physio-Chemical Aspects<br />
a) Water Quality<br />
The proposed Gangotri hydroelectric project is located in a relatively<br />
inaccessible area, with low population density. Such areas are characterised<br />
by absence <strong>of</strong> pollution sources, which is also reflected in excellent water<br />
quality.<br />
The present population in the catchment area intercepted at the diversion site<br />
has only one village, i.e. Gangotri. The total population <strong>of</strong> the village, as per<br />
1991 census was 123. Considering the decadal population growth rate as<br />
25% to 30%, the present population is <strong>of</strong> the order <strong>of</strong> 160-170. The sewage<br />
so generated, too outfalls into various streams or nallahs flowing adjacent to<br />
the settlements and ultimately reaches river Bhagirathi. The total BOD loading<br />
from domestic sources in the catchment area is <strong>of</strong> the order <strong>of</strong> 7 kg/day. The<br />
quantity <strong>of</strong> BOD loading is insignificant to cause any adverse impact on water<br />
quality, even for the minimum flow in the river. There are no industries in the<br />
9-2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
area. The area under agriculture is quite low in the catchment area. Use <strong>of</strong><br />
various agro-chemicals too is negligible. Thus, the pollution loading in the<br />
area is quite low, which is reflected in excellent water quality.<br />
b) Landuse<br />
The landuse pattern <strong>of</strong> the submergence area was ascertained using satellite<br />
and the details are outlined in Table-9.1. The landuse pattern as per the<br />
satellite data is appended as Figure-9.1. The satellite imagery (IRS 1D, LISS-<br />
III + PAN) <strong>of</strong> the study area is given as Figure-9.2.<br />
9.2.2 Ecological Aspects<br />
a) Vegetation<br />
Table-9.1<br />
Landuse pattern <strong>of</strong> the area to be<br />
acquired for the project<br />
S.<br />
No.<br />
Landuse / Land cover Area (ha)<br />
1. Dense forest 14.90<br />
2. Barren land 1.89<br />
3. Water bodies 8.17<br />
Total 24.96<br />
The proposed project site lies in western Himalayas. The nature and type <strong>of</strong><br />
vegetation occurring in an area depends upon a combination <strong>of</strong> various<br />
factors including prevailing climatic conditions altitude, topography, slope,<br />
biotic factors, etc.<br />
The proposed project area lies between EL 2,600 m to EL 3,000 m and the<br />
vegetation in the area can be broadly categorised as Himalayan moist<br />
temperate forests. The project area lies in Patangani reserve forest. The<br />
9-3
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
major tree species observed in the area is Pine (Pinus roxburghii) and Deodar<br />
(Cedrus deodara). The other tree species observed in the area include Kail<br />
(Pinus wallichiana), Spruce (Picea smithiana), Bhojpatra (Betula utilis). The<br />
submergence area lies in Patangani Reserved Forest.<br />
In the study area elevation ranges from 3000 m to 4500 m. Dense forest is<br />
observed up to an elevation 3,600 m. However, at higher altitudes, dense<br />
vegetation gives way to Himalayan Dry Temperate Forest. The major tree<br />
species observed in these forests are Deodar and Kail. At even higher<br />
elevations, Moist Alpine scrub is observed. The tree species observed in<br />
these areas are Buransh (Rhododendrom arboreum), Junifer (Junifer sp.),<br />
etc. Amongst the shrubs, Barbaris, Lonisera, Pontitella species are observed.<br />
In the study area, downstream <strong>of</strong> the tail race disposal site, dense mixed<br />
forest is observed. The major tree species observed in this forest is deodar.<br />
The major floral species observed in the study area is given in Table-9.2.<br />
Table-9.2<br />
Major floral species observed in the study area<br />
Local Name Scientific Name<br />
Trees<br />
Deodar Cedrus Deodar<br />
Pine Pinus roxburghii<br />
Spruce Picea smithiana<br />
Bhojpatra Betula utilis<br />
Kail Pinus wallichiana<br />
Padam Prunus carasoides<br />
Buransh Rhododendrum arboreum<br />
Junifer Junifer sp.<br />
Kharsu Quercus semicarpifolia<br />
Morinda Abies pindrow<br />
Local Name Scientific Name<br />
Gugal<br />
Juniperus srumata<br />
9-4
Chiraita Swestia chirayita<br />
Bhatkunda Lonisera quinquelacularis<br />
Vazradanti Potentilla fulgens.<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
b) Fauna<br />
As mentioned earlier, project area lies in reserve forest area. The forest in and<br />
around the diversion structure site is quite dense and serves as habitat for<br />
various faunal species. Based on the review <strong>of</strong> secondary data and interaction<br />
with the Forest Department, major faunal species observed in the project area<br />
and the study area include Bharal, Snow leopard, Barking deer, Wild goat and<br />
Wild cat. Apart from lizards, no major reptile species was observed in the<br />
area. Amongst the avi-fauna, the commonly observed species were vulture,<br />
parrot, dove, blue rock piegon, monal, etc.<br />
The list <strong>of</strong> faunal species observed in the study area including project area is<br />
outlined in Table-9.3.<br />
Table-9.3<br />
List <strong>of</strong> faunal species observed in the study area including project area<br />
Common Name Zoological Name Schedule as per<br />
Wildlife Protection<br />
Act<br />
Mammals<br />
Snow leopart Panthera uncia Schedule – I<br />
Goral Nemorhaedus goral Schedule – II<br />
Wild boar Sus scr<strong>of</strong>a<br />
Jungle Cat Felis chaus<br />
Wild goat Pseudois nayaur Schedule I<br />
Serrow Capricornis sunatrensis Schedule I<br />
Leopard Panthera pardus Schedule I<br />
Avi-fauna<br />
Vulture Gyps fulvus<br />
Indian Ringed dove Streptopelia decoacto<br />
Rufous Turtle dove Streptopelis orientalis<br />
Blue rock piegon Columba livia<br />
Reptiles<br />
Lizard Hemidactyles brooki<br />
9-5
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
It is observed, that quite a few species belonged to Schedule-I & Schedule II<br />
category. As per Wildlife Protection Act (1972), such species are akin to rare<br />
and endangered species and need to be protected. Thus, it is recommended<br />
detailed studies are conducted as a part <strong>of</strong> EIA study to ascertain impacts on<br />
such species, as a result <strong>of</strong> the proposed project.<br />
c) Fisheries<br />
The major water body in the project area is river Bhagirathi, which is a<br />
perennial river. Normally in such rivers several fish species are observed. The<br />
project area lies at an altitude <strong>of</strong> nearly 3,000 m. At this elevation, water<br />
temperature gets so low, that even cold water fisheries find it difficult to<br />
survive. Thus, at the diversion structure site large scale riverine fisheries are<br />
not expected. However, elevation at the proposed tail race disposal site is<br />
around 2600 m to 2700 m, where riverine fisheries could be present.<br />
Based on the interaction with the local Fisheries Department, fish species<br />
such as Brown trout and Mahaseer could be present in river Bhagirathi at the<br />
project site especially near power house site. It is recommended that a<br />
detailed fisheries survey be conducted in the river as a part <strong>of</strong> EIA study to<br />
ascertain the spatio-temporal occurrence <strong>of</strong> Mahaseer or other riverine fish<br />
species in the project area. Tank or pond fisheries are not observed in the<br />
project area and its surroundings.<br />
9.2.3 Socio-economic Aspects<br />
It is imperative to study socio-economic characteristics including demographic<br />
pr<strong>of</strong>ile <strong>of</strong> the project area and the study area. The proposed project lies in<br />
tehsil Bhatwari <strong>of</strong> district Uttarkashi. The submergence area is likely to<br />
submerge forest area which comes under the Patangani reserve forest.<br />
9-6
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The entire study area, too lies within tehsil Bhatwari <strong>of</strong> district Uttarkashi.<br />
Within the study area, only one village namely Gangotri is observed. As per<br />
1991 census, the average family size in the village Gangotri is about 2.5, with<br />
a total population <strong>of</strong> 240. Considering a decadal growth rate <strong>of</strong> 25 – 30%, the<br />
present population is around 300-310. The Scheduled Castes Population<br />
accounts for less than 4% <strong>of</strong> the total population. The literacy rate in the<br />
village is around 50%. There is vast difference in the male (95%) and female<br />
literacy rates (3.4%).<br />
9.3 PREDICTION OF IMPACTS<br />
Based on the project details and the baseline environmental status, potential<br />
impacts as a result <strong>of</strong> the construction and operation <strong>of</strong> the proposed project<br />
have been identified. As a part <strong>of</strong> IEE study, impacts on various aspects listed<br />
as below have been assessed:<br />
- Land environment<br />
- Water resources<br />
- Water quality<br />
- Terrestrial flora<br />
- Terrestrial fanna<br />
- Aquatic ecology<br />
- Noise environment<br />
- Ambient air quality<br />
- Socio-economic environment<br />
9.3.1 Impacts on Land Environment<br />
a) Construction phase<br />
Quarrying operations<br />
A hydroelectric project requires significant amount <strong>of</strong> construction material,<br />
which needs to be extracted from various quarry sites in and around the<br />
9-7
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
project area. Normally quarrying is done along the hill face, and generally left<br />
untreated after extraction <strong>of</strong> the required construction material. These sites<br />
can become permanent scar on the hill face and can become potential source<br />
<strong>of</strong> landslides. This aspect needs to be covered as a part <strong>of</strong> the EIA study and<br />
suitable measures for quarry site stabilization be recommended. It is<br />
recommended that the quarry sites be located over non-forest land.<br />
Operation <strong>of</strong> construction equipment<br />
During construction phase, various equipment will be brought to the site.<br />
These include crushers, batching plant, drillers, earth movers, rock bolters,<br />
etc. The siting <strong>of</strong> these construction equipment would require significant<br />
amount <strong>of</strong> space. Similarly, space will be required for workshop, storing <strong>of</strong><br />
other construction equipment and materials, etc. In addition, land will also be<br />
temporarily acquired, for storage <strong>of</strong> the quarried material before crushing,<br />
rubble sand, crushed material, cement, spare parts yard, fuel storage, guard<br />
room, parking area for light and heavy vehicles, petrol, diesel pumps,<br />
temporary & permanent residential colonies for government and contractor’s<br />
labour, water supply and switch yard for construction purposes, etc. Various<br />
storage sites need to be earmarked for this purpose. The storage site should<br />
be selected in such a way that it leads to minimal impacts on human<br />
population, wildlife and vegetation in the area. Since, the proposed project<br />
sites lies in reserved forest, it is recommended that to the extent possible the<br />
above facilities be located over non-forest land to minimize the adverse<br />
impacts.<br />
Problems <strong>of</strong> muck disposal<br />
A large quantity <strong>of</strong> muck is expected to be generated as a result <strong>of</strong> tunneling<br />
operations, construction <strong>of</strong> access roads, etc. The muck so generated needs<br />
9-8
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
to be properly disposed otherwise it can lead to significant adverse impacts on<br />
environment. Normally muck is disposed along the river bank which ultimately<br />
finds it way into the water body, leading to adverse impacts on riverine<br />
ecology.<br />
The other option is to dispose muck over low lying areas. Efforts need to be<br />
made so that the site selected for muck disposal has minimum vegetation.<br />
After disposal <strong>of</strong> muck, the site needs to be stabilized using bio-engineering<br />
measures. Muck disposal sites need to be located over non-forest land.<br />
Specific site specific management measures can be suggested as a part <strong>of</strong><br />
EIA study.<br />
Construction <strong>of</strong> roads<br />
The topography <strong>of</strong> the project area has steep to precipitous slopes which<br />
descends rapidly into narrow valleys. Construction <strong>of</strong> roads in such area can<br />
give rise to erosion hazards due to net downhill movement <strong>of</strong> soil aggregates,<br />
if adequate protection measures are not undertaken. The project construction<br />
would entail significant vehicular movement for transportation <strong>of</strong> large<br />
construction material, heavy construction equipment. Most <strong>of</strong> the roads in the<br />
project area, would require widening. Many new roads also shall be<br />
constructed. Construction <strong>of</strong> new roads may lead to removal <strong>of</strong> trees on<br />
slopes and re-working <strong>of</strong> the slopes in the immediate vicinity <strong>of</strong> road, which<br />
may lead to landslides, soil erosion, gully formation, etc. Adequate<br />
management measures need to be implemented to ameliorate such impacts.<br />
b) Operation phase<br />
The area coming under reservoir submergence is 24.96 ha (considering FRL<br />
as 2989 m). The entire land to be submerged lies in Patangani reserved<br />
9-9
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
forest. In addition to above, an area <strong>of</strong> 50-<strong>55</strong> ha will be required for siting <strong>of</strong><br />
project appurtenances, infrastructure, etc. The ownership category <strong>of</strong> such<br />
lands can be ascertained, once project layout is finalized as a part <strong>of</strong> DPR<br />
preparation.<br />
9.3.2 Impacts on Water Resources<br />
The construction <strong>of</strong> barrage as a part <strong>of</strong> the proposed project, diversion <strong>of</strong><br />
discharge for hydropower generation would lead to reduction in flow for a river<br />
stretch downstream <strong>of</strong> the barrage site up to the confluence point <strong>of</strong> tail race<br />
discharge. Since there are no users in the intervening stretch, hence,<br />
reduction in flow in lean season and is unlikely to lead to any significant<br />
impact. However, reduction in flow is likely to have marginal impact on riverine<br />
ecology as the discharge during lean flow is significantly less, it is<br />
supplemented by intervening nallahs and streams do supplement the<br />
minimum flows in the intervening stretch .<br />
9.3.3 Impacts on Water Quality<br />
a) Construction phase<br />
The project construction is likely to last for a period <strong>of</strong> 4-5 years apart from<br />
investigation stage. About 2000 workers and 500 technical staff are likely to<br />
work during project construction phase. The construction phase, also leads to<br />
mushrooming <strong>of</strong> various allied activities to meet the demands <strong>of</strong> the immigrant<br />
labour population in the project area. Thus, the total increase in labour<br />
population during construction phase is expected to be around 5000-6000.<br />
The total quantum <strong>of</strong> sewage generated is expected to be <strong>of</strong> the order <strong>of</strong> 0.4<br />
mld. The BOD load contributed by domestic sources will be about 270 kg/day.<br />
The sewage generally shall be disposed in nearby streams or channels under<br />
9-10
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
gravity through open drains, where ultimately it will find its way into river<br />
Bhagirathi. The inadequate sewage treatment and disposal facilities could<br />
lead to increased incidence <strong>of</strong> water-borne diseases. Thus, it is recommended<br />
to commission adequate sewage treatment facilities in the labour camps.<br />
Normally during construction phase, higher level <strong>of</strong> sewage treatment plants<br />
with secondary treatment facilities are not provided, as they are rendered<br />
useless, once the construction phase is over. Low cost sanitation systems are<br />
commissioned for treatment <strong>of</strong> sewage generated from labour camps. Similar<br />
sewage treatment measures are recommended during the construction phase<br />
<strong>of</strong> the proposed project as well.<br />
b) Operation phase<br />
Effluent from project colony<br />
In the operation phase, about 200 families will be residing in the area which<br />
would generate about 0.15 mld <strong>of</strong> sewage. The quantum <strong>of</strong> sewage<br />
generated is not expected to cause any significant adverse impact on riverine<br />
water quality. Adequate sewage treatment facilities including secondary<br />
treatment facilities need to be commissioned for this purpose to ameliorate<br />
whatever marginal impact that is expected to occur.<br />
Impacts on reservoir water quality<br />
The flooding <strong>of</strong> forest land in the submergence area increases the availability<br />
<strong>of</strong> nutrients resulting from decomposition <strong>of</strong> vegetative matter. Enrichment <strong>of</strong><br />
impounded water with organic and inorganic nutrients at times become a<br />
major water quality problem immediately on commencement <strong>of</strong> the operation<br />
and is likely to continue in the initial years <strong>of</strong> operation. However, in case <strong>of</strong><br />
Run-<strong>of</strong>f-the-river schemes, the submerged area is negligible. The above<br />
9-11
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
referred impact is not expected to be significant. To ascertain the quantum <strong>of</strong><br />
reduction in D.O. levels in initial years <strong>of</strong> reservoir operation, it is<br />
recommended that detailed modelling study be done as a part <strong>of</strong> EIA study.<br />
Eutrophication risks<br />
The fertilizer use in the project area is nil, hence, run<strong>of</strong>f at present does not<br />
contain significant amount <strong>of</strong> nutrients. During post-project phase too, use <strong>of</strong><br />
fertilizers in the project catchment area is not expected to rise significantly.<br />
Thus, problems <strong>of</strong> eutrophication, which are primarily caused by enrichment<br />
<strong>of</strong> nutrients in water are not anticipated in the proposed project.<br />
9.3.4 Impacts on Terrestrial Flora<br />
a) Construction phase<br />
Increased human interferences<br />
As mentioned earlier, about 2,500 technical staff, workers and other group <strong>of</strong><br />
people are likely to congregate in the area during the project construction<br />
phase. The total increase in population is expected to be about 5000-6000.<br />
Workers and other population groups residing in the area may use fuel wood,<br />
if no alternate fuel is provided. On an average, the fuel wood requirements will<br />
be <strong>of</strong> the order <strong>of</strong> 2500-2700 m 3 . Thus, every year, fuel wood equivalent to<br />
about 800-900 trees will be cut, which implies that every year on an average<br />
about 1 ha <strong>of</strong> dense forest area will be cleared for meeting fuel wood<br />
requirements, if no alternate sources <strong>of</strong> fuel are provided. It is recommended<br />
that contractor involved in construction activities to either provide alternative<br />
source <strong>of</strong> fuel or run community kitchens, in which LPG or kerosene is used<br />
as fuel.<br />
9-12
) Operation Phase<br />
Acquisition <strong>of</strong> forest land<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
About 14.9 ha <strong>of</strong> forest area, mainly under reservoir submergence needs to<br />
be acquired, which lies in reserved forest area. In addition to above about 50-<br />
<strong>55</strong> ha land will also be required for siting <strong>of</strong> construction equipment, storage <strong>of</strong><br />
construction material, muck disposal, widening <strong>of</strong> existing roads and<br />
construction <strong>of</strong> new project roads, infrastructure development, etc. In addition<br />
to compensatory afforestation, conservation plan, outlining measures for<br />
development <strong>of</strong> floral species in areas similar to the one being affected needs<br />
to be formulated.<br />
It is recommended that a detailed ecological survey be conducted as a part <strong>of</strong><br />
EIA study to assess the density and diversity <strong>of</strong> flora in the area, based on<br />
which appropriate management measures can be formulated.<br />
9.3.5 Impacts on Terrestrial Fauna<br />
The forest area, in the project area and its surroundings provides habitat to<br />
various faunal species, quite a few which are categorised as Schedule-I or<br />
Schedule-II as per the Wildlife Protection Act (1972). The Wildlife Protection<br />
Act clearly lays specific guidelines for projection <strong>of</strong> Schedule-I & II faunal<br />
species.<br />
During construction phase, there will be considerable human interferences,<br />
and disturbance due to various construction and related activities. A detailed<br />
study needs to be conducted as a part <strong>of</strong> EIA study to assess the impacts on<br />
various faunal species due to such activities. Based on the findings <strong>of</strong> the<br />
survey, detailed management measures including surveillance need to be<br />
suggested to minimize the adverse impacts to the extent possible.<br />
9-13
) Operation phase<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
During project operation phase, accessibility to the area will improve due to<br />
construction <strong>of</strong> roads, which in turn may increase human interference leading<br />
to adverse impacts on the terrestrial ecosystem. The increase in human<br />
population will not be much, hence, significant adverse impacts are not<br />
anticipated.<br />
Perusal <strong>of</strong> various faunal species observed in the project area, indicates that<br />
there are no migratory faunal species observed in the area. River Bhagirathi<br />
in the project area, even in the pre-project phase, acts as a barrier to wildlife<br />
movement. Thus construction <strong>of</strong> the reservoir as a part <strong>of</strong> the proposed<br />
project , is not expected to cause any additional barrier to wildlife movement<br />
in the project area.<br />
9.3.6 Impacts on Aquatic Ecology<br />
a) Construction phase<br />
During construction <strong>of</strong> a river valley project, huge quantity <strong>of</strong> muck is<br />
generated at various construction sites, which if not properly disposed,<br />
invariably would flow down the river during heavy precipitation. Such condition<br />
can lead to adverse impacts on the development <strong>of</strong> aquatic life, which needs<br />
to be avoided.<br />
The increased labour population during construction phase, could lead to<br />
increased pressure on fish fauna, as a result <strong>of</strong> indiscriminate fishing by them.<br />
Adequate protection measures at sensitive locations, identified on the basis <strong>of</strong><br />
fisheries survey in the EIA study need to be implemented.<br />
9-14
) Operation phase<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Amongst the aquatic animals, it is the fish life which would be most affected.<br />
Based on the literature review, large scale riverine fisheries are not<br />
anticipated at the proposed project site. However, in rivers flowing in setting<br />
similar to Bhagirathi, Mahaseer, a migratory fish species could be present in<br />
the project area. A detailed fisheries survey needs to be conducted to<br />
ascertain the severity <strong>of</strong> impacts on Mahaseer and other riverine fish species,<br />
as a result <strong>of</strong> the proposed project.<br />
9.3.7 Impacts on Noise Environment<br />
Increased noise level are anticipated only during project construction phase<br />
due to operation <strong>of</strong> various equipment, increased vehicular movement and<br />
blasting etc. The project area has dense vegetation, which will attenuate noise<br />
levels to a large extent. Since, there are no settlements close to the project<br />
site, no significant impact on human beings is anticipated. However increased<br />
noise level, especially blasting could scare away wildlife from the area. It has<br />
been observed during construction phase <strong>of</strong> similar projects, that wildlife<br />
migrates from such areas and returns after the cessation <strong>of</strong> construction<br />
activities. Similar phenomenon is expected in the proposed project site as<br />
well. It is recommended that a noise modelling study be conducted as a part<br />
<strong>of</strong> EIA study to assess the impacts as a result <strong>of</strong> increased noise level.<br />
9.3.8 Air Pollution<br />
Pollution due to fuel combustion in various equipment<br />
Normally, diesel is used in construction equipment. The major pollutant, which<br />
gets emitted as a result <strong>of</strong> diesel combustion, is SO2. The SPM emissions are<br />
9-15
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
minimal due to low ash content in diesel. Model studies conducted for various<br />
projects with similar level <strong>of</strong> fuel consumption indicate that the short-term<br />
increase in SO2, even assuming that all the equipment are operating at a<br />
common point, is quite low, i.e. <strong>of</strong> the order <strong>of</strong> less than 1µg/m 3 . Hence, no<br />
major impact is anticipated on this account.<br />
Emissions from various crushers<br />
The operation <strong>of</strong> the crusher during the construction phase is likely to<br />
generate fugitive emissions, which can move even up to 1 km along the<br />
predominant wind direction. During construction phase, one crusher each is<br />
likely to be commissioned at the diversion structure site and the power house<br />
site. During crushing operations, fugitive emissions comprising <strong>of</strong> the<br />
suspended particulate will be generated. Since, there are no major<br />
settlements close to the diversion structure site, no major adverse impacts on<br />
this account are anticipated. However, it is recommended that the labour<br />
camp be situated at least 1 km away from the construction sites and that too<br />
on the leeward side <strong>of</strong> the pre-dominant wind direction in the area.<br />
9.3.9 Impacts on Socio-Economic Environment<br />
a) Project construction phase<br />
The construction phase will last for about 4-5 years. Those who would migrate<br />
to this area are likely to come from various parts <strong>of</strong> the country mainly having<br />
different cultural, ethnic and social backgrounds. Due to longer residence <strong>of</strong><br />
this population in one place, a new culture, having a distinct socio-economic<br />
similarity would develop which will have its own entity. It is recommended that<br />
the labour camps and project colonies and other infrastructure be located over<br />
non-forest area, so that not only the land requirements are minimal, but<br />
9-16
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
adverse impacts due to human interferences are reduced to the extent<br />
possible.<br />
b) Project operation phase<br />
The entire land to be acquired for reservoir submergence is forest land and no<br />
private land or homesteads are to be acquired. However, some <strong>of</strong> the land to<br />
be acquired for various project appurtenances, which are proposed to be<br />
located over non-forest land could entail acquisition <strong>of</strong> private land. A detailed<br />
R&R plan, if required could be formulated as a part <strong>of</strong> EIA study.<br />
9.4 SUMMARY OF IMPACTS AND EMP<br />
A summary <strong>of</strong> impacts and recommended management measures are<br />
summarized in Table-9.4.<br />
Table-9.4<br />
Summary <strong>of</strong> Impacts and suggested management measures<br />
S.<br />
No.<br />
Parameters Impact Management Measures<br />
1. Land Environment<br />
Construction • Soil erosion due to the • Proper treatment <strong>of</strong><br />
phase<br />
extraction <strong>of</strong><br />
quarry site and location<br />
construction material <strong>of</strong> such sites over non-<br />
from various quarry<br />
sites.<br />
forest area.<br />
• Efforts to be made to<br />
ensure that minimal<br />
forest land is acquired.<br />
• Temporary acquisition<br />
<strong>of</strong> land for siting <strong>of</strong><br />
construction equipment<br />
& material, waste<br />
material, etc.<br />
• Generation <strong>of</strong> muck due<br />
to tunnelling operations<br />
& roads.<br />
• Disposal at designated<br />
sites and provision <strong>of</strong><br />
suitable management<br />
measures including<br />
bio-engineering<br />
treatment measures<br />
9-17
S.<br />
No.<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Parameters Impact Management Measures<br />
Operation<br />
phase<br />
2. Water resources<br />
Operation<br />
phase<br />
3. Water quality<br />
Construction<br />
phase<br />
Operation<br />
phase<br />
• Acquisition <strong>of</strong> 14.9 ha <strong>of</strong><br />
forest land.<br />
• River stretch from<br />
diversion structure site<br />
to tail race outfall will<br />
have reduced flow<br />
during lean season.<br />
• Moderation <strong>of</strong><br />
hydrologic<br />
regime.<br />
• Water pollution due to<br />
disposal <strong>of</strong> sewage<br />
from labour colonies.<br />
• Disposal <strong>of</strong> sewage<br />
from project colony.<br />
• Eutrophication<br />
problems.<br />
4. Terrestrial flora<br />
5. Terrestrial fauna<br />
Construction • Disturbance to wildlife<br />
phase<br />
due to operation <strong>of</strong><br />
various construction<br />
equipment.<br />
Operation<br />
phase<br />
• Disturbance to wildlife<br />
due to increased<br />
accessibility in the<br />
area.<br />
The site should be<br />
located over non-forest<br />
area.<br />
• Compensatory<br />
afforestation &<br />
formulation <strong>of</strong><br />
Conservation plan<br />
• In case downstream<br />
nallahs do not<br />
contribute to lean<br />
flows, minimum flow<br />
will be released to<br />
maintain the riverine<br />
ecology.<br />
-<br />
• Provision <strong>of</strong> community<br />
toilets and septic tanks<br />
• Provision <strong>of</strong> adequate<br />
sewage treatment<br />
facilities<br />
• No major impact<br />
expected<br />
• Increased surveillance<br />
to ensure minimum<br />
human activity in the<br />
national park.<br />
-<br />
9-18
S.<br />
No.<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Parameters Impact Management Measures<br />
6. Aquatic Ecology<br />
Construction<br />
phase<br />
Operation<br />
phase<br />
7. Noise Environment<br />
8. Air Environment<br />
Construction<br />
phase<br />
• Marginal decrease in<br />
aquatic productivity due<br />
to increased turbidity<br />
and lesser light<br />
penetration.<br />
• Obstruction in the path<br />
<strong>of</strong> migratory fishes.<br />
• Proliferation <strong>of</strong> species<br />
adapted to the<br />
lacustrine environment.<br />
• Drying <strong>of</strong> river stretch<br />
downstream <strong>of</strong> dam up<br />
to tail race outfall<br />
• Increase in air pollution<br />
due to use <strong>of</strong> machinery<br />
and other civil activities.<br />
9. Socio-economic Environment<br />
Construction<br />
phase<br />
Operation<br />
phase<br />
• Increase in employment<br />
potential.<br />
• Increased power<br />
generation<br />
• Greater employment<br />
opportunities.<br />
• Marginal impact, hence<br />
no specific<br />
management<br />
measures are<br />
suggested.<br />
• Development <strong>of</strong><br />
hatchery for artificial<br />
seed production and<br />
stocking <strong>of</strong> reservoir<br />
and the affected river<br />
stretch<br />
• Provision <strong>of</strong> release <strong>of</strong><br />
minimum flow, in case<br />
downstream nallahs do<br />
not contribute<br />
significant flows<br />
• Provision <strong>of</strong> release <strong>of</strong><br />
minimum flow<br />
• Cyclones will be<br />
provided in crushers<br />
operating at various<br />
construction sites.<br />
-<br />
-<br />
-<br />
9-19
9.5 CONCLUSIONS AND RECOMMENDATIONS<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The project lies in reserve forest area providing habitat to various wildlife<br />
species. The following aspects need to be studied in detail as a part <strong>of</strong> next<br />
phase <strong>of</strong> environmental studies:<br />
- Impacts due to siting <strong>of</strong> various project features requiring temporary<br />
and permanent land acquisition on flora and fauna in reserved forest<br />
area.<br />
- Impediment to migratory fish species as a result <strong>of</strong> construction <strong>of</strong><br />
diversion structure<br />
- Proper stabilization <strong>of</strong> quarry and muck disposal sites<br />
- Management <strong>of</strong> pollution sources from labour camps<br />
9-20
10.1 INTRODUCTION<br />
CHAPTER –X<br />
INFRASTRUCTURE FACILITIES<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The Gangotri Hydroelectric project across the river Bhagirathi envisages<br />
construction <strong>of</strong> a 26 m high gravity dam (above river bed level), an intake with<br />
short tunnels to the under ground desilting basins, a 5.20 km long HRT,<br />
pressure shaft, an underground power house with an installed capacity <strong>of</strong> <strong>55</strong><br />
<strong>MW</strong> and a tail race tunnel. The gravity dam is located at a distance <strong>of</strong> about<br />
2.5 km before Gangotri shrine. The major infrastructure facilities needed are<br />
described in the following paragraphs.<br />
10.2 COMMUNICATIONS<br />
10.2.1 The nearest rail head available to the project is Rishikesh which is about 276<br />
km from the intake site.<br />
From Rishikesh upto Gangotri via Dunda, Uttarkashi and Bhaironghati a wide<br />
black topped road exists. From Bhaironghati to existing main road near<br />
Gangotri HE <strong>Power</strong> house Site a motorable road exists but this requires<br />
extensive improvement, widening and hill slope stability measure for carry<br />
construction machinery & equipment. From existing main road onwards up to<br />
intake site a new approach road is required to be constructed<br />
10.2.2 Roads in the Project Area<br />
Apart from improvement <strong>of</strong> existing Bhaironghati – Gangotri road, an<br />
approach road is required to be built to the proposed Dam site (3 km).<br />
10-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Other permanent roads to be constructed include a road from existing main<br />
road to <strong>Power</strong> House (about 4 km),access tunnel, project colony, work adits,<br />
and other <strong>Power</strong> House Complex requirements like road to switch yard,<br />
<strong>Power</strong> House Colony etc.<br />
Construction roads are also required from intake / power house site to quarry<br />
sites, and plant and machinery workshops etc.<br />
Considering the existing road facilities, lengths <strong>of</strong> permanent and temporary<br />
roads that are needed will not be large.<br />
10.2.3 Railways<br />
The nearest railway station is Rishikesh on the broad gauge line. Railway<br />
siding for unloading heavy machineries and equipment is to be provided at<br />
Rishikesh.<br />
10.3 CONSTRUCTION POWER<br />
The power demand for the construction activities is estimated to be about 5<br />
<strong>MW</strong> taking capacity <strong>of</strong> electric driven equipment and lighting which are to<br />
work within the target time for consideration. The initial requirement in the first<br />
two years could be 2 <strong>MW</strong> and this subsequently has to be increased to 5 <strong>MW</strong><br />
The power requirement can be met with by procuring the supply from<br />
Uttaranchal authorities. For making the power available at project site<br />
required 33/11 kV substation and alongwith new power lines about 8 km to<br />
route from Bhaironghathi is proposed.<br />
10-2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
In addition to tapping grid supply, it is also proposed to provide supplemental<br />
power aggregating to 2 <strong>MW</strong> as a stand by in case <strong>of</strong> interruptions in grid<br />
supply.<br />
10.4 TELECOMMUNICATION<br />
To ensure efficient execution at various sites, adequate and reliable<br />
telecommunication network is necessary. An electronic private Automatic<br />
Exchange with a capacity <strong>of</strong> about 50 lines is proposed.<br />
A VHF system is also proposed to link project Head Quarters with clients<br />
head-quarters.<br />
Suitable number <strong>of</strong> mobile phones / walky talkies are also proposed.<br />
10.5 <strong>PROJECT</strong> COLONIES / BUILDINGS<br />
10.5.1 The main project colony is proposed near Gangotri about 5-6 km from intake<br />
site and 12 km from power location. Facilities such as school, post <strong>of</strong>fice,<br />
police station, market, primary health centre, fire fighting arrangement,<br />
canteen and recreation facility are already available at Gangotri town which is<br />
very near to intake Site. Administrative building and 30 family quarters and a<br />
hostel are also proposed.<br />
Two more small colonies one near dam site and another near <strong>Power</strong> House<br />
location are also to be built with other facilities.<br />
10-3
10.5.2 Contractor’s Colony and Labour Colony<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Contractors colonies and two or three labour colonies with all amenities are to<br />
be located at sites near the major works.<br />
10.6 WORKSHOPS STORES, FABRICATION YARDS AND MAGAZINES<br />
Workshops for maintaining the plant and equipment used for construction,<br />
stores for construction materials, hydro-mechanical and electro-mechanical<br />
equipments etc. will be built and maintained by the contractor. However, a<br />
small workshop is planned for repair and maintenance facilities <strong>of</strong> project<br />
transport vehicles and minimum essential equipment will be built by the client.<br />
Areas for fabrication yards for the hydro – mechanical equipment, viz the<br />
various gates and hoists, pressure tunnel liners, penstocks etc. will have to be<br />
identified near the work sites.<br />
Two explosive magazines one for the works at dam site and rock quarries and<br />
another for the underground works are to be built.<br />
10.7 WATER SUPPLY AND SANITATION<br />
For drinking purposes in the colony areas, suitable water treatment plants for<br />
treating water drawn from the river Bhagirathi will be used. For construction<br />
purposes, water directly pumped from the river and stored will be used.<br />
Suitable sanitation and sewerage treatment facilities will have to be made at all<br />
the project and labour colony areas.<br />
10-4
11.1 INTRODUCTION<br />
CHAPTER – XI<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
CONSTRUCTION PLANNING & SCHEDULE<br />
The Gangotri H.E. Project is located in the higher altitudes <strong>of</strong> about EL 2965<br />
m in the Himalayas and within the region heavy snow is experienced. At<br />
Badrinath (IMD Station) located on the Alaknanda valley snow is experienced<br />
5 months from December to April. The climatic parameters vary considerably<br />
within the basin also as such the project area has a limited working season<br />
as regards surface works are concerned. A period <strong>of</strong> 24 months has been<br />
provided for preparation <strong>of</strong> field investigations, subsurface exploration as<br />
required for Detailed Project Report preparation including statutory clearance/<br />
approvals. Thereafter 24 months’ have been provided for pre-construction<br />
activities <strong>of</strong> surveys, infrastructure facilities, construction power, decision on<br />
accounts <strong>of</strong> development funds / agencies for execution engineering design,<br />
approach roads, tender engineering etc. The construction phase includes all<br />
the pre construction activities. A construction period <strong>of</strong> 5 years has been<br />
considered based on location <strong>of</strong> the project in higher altitude and remoteness<br />
<strong>of</strong> the area. The initial 24 months period for DPR preparation could be<br />
optimised incase other potential projects on the basin are taken up<br />
simultaneously.<br />
11.2 CONSTRUCTION METHODOLOGY<br />
Gagotri H.E. Project is envisaged as Run-<strong>of</strong>f-the-River scheme across the<br />
Bhagirathi river. Diurnal gross Storage <strong>of</strong> about 4.37 Mcum with live storage<br />
<strong>of</strong> 0.91 M cum shall be created by a dam and gates arrangements, a<br />
discharge <strong>of</strong> 18.19 cumecs flow is proposed to be diverted through a tunnel<br />
11-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
<strong>of</strong> 2.5 m dia, D-shaped and 5.2 Km long to the underground power house and<br />
thereafter tailrace tunnel leading the discharges back to the river.<br />
11.3 MATERIAL SOURCES<br />
During the site visit by the WAPCOS Team which included a geologist,<br />
reconnaissance visit reveal that sand is not available in the nearby area and<br />
has to be transported from down below or produced by crushing stones<br />
similarly coarse aggregate shall have to be crushed from the nearby quarry<br />
sites.<br />
11.4 CONTRACT PACKAGES<br />
The contracts packages shall be mainly in the following packages :<br />
a) Headworks including Hydro mechanical<br />
b) Intake, tunneling work including adits and desilting chambers.<br />
c) <strong>Power</strong> house, pressure shaft, surge shaft, tailrace tunnel.<br />
d) Hydro mechanical.<br />
e) Hydro Electrical<br />
The eligibility <strong>of</strong> the contractors shall have to be suitably fixed based on<br />
working experience under similar condition. The auxiliary works <strong>of</strong> river<br />
diversion, c<strong>of</strong>fer dam, penstock fabrication shall be part <strong>of</strong> the civil works<br />
package. However, for basic site facilities storage sites for contractor,<br />
approach roads, construction equipment, testing laboratory, staff colony, field<br />
<strong>of</strong>fices at power house and intake sites could be taken up departmentally to<br />
enhance the pace <strong>of</strong> work <strong>of</strong> the contractor and cost recovered from the<br />
contractor. The packages could be contracted earlier so that by the time civil<br />
contractors mobilize the site facilities are made available.<br />
11-2
11.5 SCHEDULE OF WORK<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
As envisaged the underground works could progress and may not be<br />
hampered by restricted working season but with lower rate <strong>of</strong> progress. The<br />
surface work shall be limited to about 150 days in a year with 25 working days<br />
in a month and 8 working hours. For the subsurface works the seasonal<br />
effect will be felt on the progress <strong>of</strong> work due to low temperatures restricted<br />
and reduced supplies as such reduction <strong>of</strong> progress in snowy period is<br />
considered and about 200 days could be utilized. Two shift working is<br />
considered economical due to shortage <strong>of</strong> working season, but third shift<br />
could be planned based on progress <strong>of</strong> work and seasonal constraints.<br />
11.6 CONSTRUCTION ACTIVITIES<br />
After the financial terms for construction are decided, NIT for fixing the civil<br />
contractor can be invited within 6 months on ICB basis.<br />
a) Diversion <strong>of</strong> river<br />
As the river gorge is narrow a diversion tunnel on the right bank is<br />
proposed before construction <strong>of</strong> the dam. The diversion tunnel invert<br />
level is kept at minimum flow level and completed in first three<br />
months immediately after snowing period ends and before the river<br />
water starts rising due to rise <strong>of</strong> temperature from June onwards and<br />
the excavation <strong>of</strong> diversion tunnel will be carried out by conventional<br />
drilling and blasting method. After the next floods recede a masonry<br />
c<strong>of</strong>fer dam shall be constructed in parts and foundation works in river<br />
bed level completed upto the planned block level before the next floods<br />
are allowed to over top the concrete block. After the dam and<br />
appartment works are completed the diversion tunnel shall be plugged.<br />
11-3
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The river bed excavation shall be handled by 3.0 cum Hydraulic<br />
Excavator and Rear Dumpers (25t).<br />
b) The construction <strong>of</strong> the dam and appurtenant works shall be completed<br />
in 30 months period.<br />
c) Intake tunnel and Desilting Chamber<br />
The intake structure and the intake tunnel <strong>of</strong> 2.75 m dia D-shaped and<br />
the desilting chamber <strong>of</strong> size 110 m x 8.0 m x 9.0 m are planned to be<br />
excavated by Conventional method <strong>of</strong> drilling and blasting and will be<br />
completed in 24 months.<br />
d) Tunnelling<br />
The head race tunnel finished dia is 2.5 m, D-shaped and 5.2 Km long<br />
and the excavation will be approach to the underground power house<br />
from the existing highway is proposed to be constructed upto the<br />
power house adit and also going further to the surge shaft. One Adit<br />
each at power house and surge shaft shall be provided. As both the<br />
banks <strong>of</strong> the river are under dense mix Forest with Deodar trees as<br />
such no additional adit is proposed and approach roads to Surge shaft,<br />
<strong>Power</strong> House and intake structure shall be minimum from the existing<br />
highway. There shall be only two faces for working on the HRT and<br />
one face each from Surge shaft are proposed Tunnel excavation shall<br />
be based on conventional drilling and blasting and supported by ribs<br />
where essential and supporting the excavated rock face by shotcreting<br />
and bolting. A period <strong>of</strong> 39 months has been kept for tunnel and 42<br />
months for power house excavation and concreting. The pressure<br />
shaft and Surge shaft shall be excavated through Alimak Raise<br />
11-4
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Climber. The construction schedule at PFR stage studies is given in<br />
the enclosed Plate 11-1.<br />
e) <strong>Power</strong> House<br />
The under ground <strong>Power</strong> house accommodates 1 x <strong>55</strong> <strong>MW</strong> units. The<br />
excavation <strong>of</strong> the power house cavern shall be by conventional drilling<br />
and blasting method deploying air track, jack hammers and mucking<br />
shall be through trolleys mounted on rails as the working space in the<br />
tunnel shall be limited. Approach to the power house cavern shall be<br />
from the highway on the right bank leading from Bhaironghati by a<br />
small additional approach road and access tunnel from the same bank.<br />
11-5
12.1 INTRODUCTION<br />
CHAPTER - XII<br />
COST ESTIMATE<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
Gangotri H.E. Project is proposed as run <strong>of</strong> the river scheme on the river<br />
Bhagirathi to tap its hydropower potential. The diversion structure is located<br />
2.5 downstream <strong>of</strong> the Gangotri Shrine in district Uttarkashi. The project<br />
envisages to divert the water <strong>of</strong> Bhagirathi into water conductor system by<br />
means <strong>of</strong> a diversion dam 26 m high (above river bed level) across the river.<br />
The water conductor system comprises <strong>of</strong> an intake, underground desilting<br />
chambers followed by a 5.20 km long head race tunnel <strong>of</strong> 2.5 m diameter<br />
(D-shaped), a surge shaft <strong>of</strong> 6 m diameter, a pressure shaft to feed one unit<br />
<strong>of</strong> <strong>55</strong> <strong>MW</strong> housed in an underground power house. A 450 m long tail race<br />
tunnel discharges the water back into the river Bhagirathi just upstream <strong>of</strong><br />
another proposed Bhaironghati H.E. scheme head works.<br />
12.2 ABSTRACT OF COSTS<br />
The Project is estimated to cost Rs. 211.64 Crore at June 2003 price level<br />
the break down <strong>of</strong> cost is given below :<br />
Item Estimated Cost<br />
(Rs. Crore)<br />
Civil Works 148.46<br />
Electrical Works 63.18<br />
Sub Total (Generation) 211.64<br />
The project estimate has been prepared on the basis <strong>of</strong> “ Guidelines for<br />
preparation <strong>of</strong> cost estimates for River Valley projects” published by Central<br />
Water Commission, New Delhi. The abstract <strong>of</strong> cost <strong>of</strong> civil works is<br />
12-1
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
enclosed as Annexure 12.1. The above cost does not include the cost <strong>of</strong><br />
transmission. However cost <strong>of</strong> power evacuation for this project under<br />
construction has been arrived as Rs. 7.5 Crores. Cost <strong>of</strong> Electromechanical<br />
is enclosed as Annexure 12.2<br />
The estimate for civil & Hydro mechanical works have been prepared based<br />
on the as average rates for major items <strong>of</strong> works made available by CWC in<br />
the “guidelines for estimating the civil cost for the preparation <strong>of</strong> PFR”.<br />
The electro mechanical rates have been adopted on the basis <strong>of</strong> enquiry<br />
floated to various reputed manufactures / supplier. The rates are inclusive <strong>of</strong><br />
excise duty & taxes.<br />
The phased programme <strong>of</strong> construction has been given in the relevant<br />
chapter with this report.<br />
Cost provisions for the various items mentioned below has been made on<br />
lump sum percentage basis <strong>of</strong> C-Works & J – <strong>Power</strong> Plant Civil Works for<br />
working out the total cost <strong>of</strong> project at pre - feasibility stage.<br />
S.<br />
Items Provisions <strong>of</strong> % <strong>of</strong><br />
No.<br />
C-Works & J-<strong>Power</strong> Plant Civil<br />
Works<br />
1 A. Preliminary 2%<br />
2 K. Buildings 4%<br />
3 O. Miscellaneous 4%<br />
4 P. Maintenance 1% <strong>of</strong> (C+J+K+R)<br />
5 R. Communication 4%<br />
6 X. Environment & Ecology 2%<br />
7 Y. Losses on Stock 0.25% <strong>of</strong> C – Works,<br />
J - <strong>Power</strong> Plant - Civil Works,<br />
K- Building & R - Communication<br />
12-2
13.1 GENERAL<br />
CHAPTER – XIII<br />
ECONOMIC EVALUATION<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The economic and financial evaluation <strong>of</strong> the Gangotri H.E project have been<br />
carried out considering the standard guidelines issued by Central Electricity<br />
Authority and the norms laid down by the Central Electricity Regulatory<br />
Commission (CERC) for Hydro projects.<br />
13.2 <strong>PROJECT</strong> BENEFITS<br />
13.2.1 The scheme would afford on annual energy generation <strong>of</strong> 264.76 GWh in a<br />
90% dependable year. For assessing the tariff, design energy generation <strong>of</strong><br />
256.64 GWh, calculated with 95% capacity availability in a 90% dependable<br />
year, has been adopted. The project would provide <strong>55</strong> <strong>MW</strong> <strong>of</strong> peaking<br />
capacity benefits.<br />
13.3 CAPITAL COST<br />
The project cost has been estimated at Rs. 211.64 Crores without IDC based<br />
on the criteria for “Adoption <strong>of</strong> Rates and Cost for preparation <strong>of</strong> PFRs <strong>of</strong><br />
hydro-electric projects” issued by CEA and is as given below:<br />
1. Cost <strong>of</strong> civil works = Rs. 148.46 Crores<br />
2. Cost <strong>of</strong> Electrical/Mechanical works = Rs. 63.18 Crores<br />
Total = Rs.211.64 Crores<br />
13-1
13.4 MODE OF FINANCING<br />
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
The project is proposed to be financed with a debt equity ratio <strong>of</strong> 70:30. An<br />
interest rate <strong>of</strong> 10% on the loan component has been considered for the<br />
financial analysis <strong>of</strong> the project. The interest on the working capital is taken<br />
as 9.75%.<br />
13.5 PHASING OF EXPENDITURE<br />
The project is proposed to be completed in 5 years period in all respect with<br />
full benefit available after 5 years. The detailed year wise phasing <strong>of</strong><br />
expenditure based upon the above construction programme for Civil &<br />
Electrical works is given in Annexure 13.1.<br />
13.6 FINANCIAL ANALYSIS<br />
13.6.1 BASIC AND NORMATIVE PARAMETERS<br />
The following basic parameters have been adopted for working out the<br />
financial analysis <strong>of</strong> the project.<br />
i) Estimated capital cost <strong>of</strong> Rs. 245.11 Crores considering the Interest<br />
during construction.<br />
ii) Annual energy generation <strong>of</strong> 264.76 GWh in 90% dependable year and<br />
Design energy <strong>of</strong> 256.64 GWh.<br />
iii) Operation & maintenance expenses (including insurance) @ 1.5% <strong>of</strong><br />
the project cost in the first year with 5% escalation every year.<br />
iv) Depreciation @ 3.5 % has been considered on an average basis.<br />
v) Auxiliary consumption @ 0.7 % <strong>of</strong> the energy generated.<br />
vi) Transformation loss @ 0.5% <strong>of</strong> the energy generated.<br />
13-2
PFR STUDIES OF <strong>GANGOTRI</strong> H.E. <strong>PROJECT</strong><br />
vii) Interest on working capital @ 9.75%.<br />
viii) Interest during construction has been worked out based upon the<br />
interest rates as mentioned above. The computations are given in<br />
Annexure 13.2 for present day capital cost.<br />
ix) Corporate tax @ 30%.<br />
x) Return on equity @ 16%.<br />
13.6.2 Assessment <strong>of</strong> Tariff<br />
Based upon the parameters given above, the sale rate <strong>of</strong> energy at bus bar<br />
has been computed in Annexure 13.3. The sale rate applicable in the first<br />
year and levellised tariff is indicated below.<br />
Tariff Period<br />
First Year<br />
13.7 CONCLUSION<br />
Levellised Tariff<br />
TABLE – 13.2<br />
Tariff<br />
(Rs./KWh)<br />
1.62<br />
1.42<br />
The sale rate <strong>of</strong> energy indicated above shows that the energy generated<br />
from the project is financially viable and economically attractive.<br />
13-3