Bhaironghati - Ministry of Power
Bhaironghati - Ministry of Power
Bhaironghati - Ministry of Power
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
1. INTRODUCTION<br />
CHAPTER – I<br />
EXECUTIVE SUMMARY<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The Bhairon Ghati Hydroelectric Project located in Uttarkashi district <strong>of</strong><br />
Uttaranchal envisages utilization <strong>of</strong> the waters <strong>of</strong> the river Bhagirathi, a<br />
tributary <strong>of</strong> Ganga for power generation on a run <strong>of</strong> river type development,<br />
harnessing a head <strong>of</strong> about 132 m.<br />
The project with a proposed installation <strong>of</strong> 65 MW (2x32.5 MW) would afford<br />
an annual energy generation <strong>of</strong> 293.18 GWh in a 90% dependable year. The<br />
tariff from the project at present day cost would be Rs 1.57 /kWh (levellised).<br />
The diversion site is located at Latitude 31 o 01’ 55” N; Longitude 78 o 51’<br />
35”E. The dam site is approachable by road from Rishikesh (via Tehri-<br />
Uttarakashi-Gangotri highway) at a distance <strong>of</strong> 267 km. The nearest rail head<br />
is located at Rishikesh and nearest airport is located at Dehradun.<br />
2. SCOPE OF WORKS<br />
The Bhairon Ghati HE project envisages construction <strong>of</strong> :<br />
• a 34 m high Concrete Gravity dam across river Bhagirathi to provide<br />
a live storage <strong>of</strong> 0.853 Mcum with FRL at 2642.0 m and MDDL at<br />
El 2630.00 m;<br />
• 1 no. desilting chamber <strong>of</strong> length 230 m (L) and size 12.0 m (W)x 17 m<br />
(H) to remove silt particles <strong>of</strong> size 0.2 mm and above;<br />
1-1
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
• a 5.1 km long and 4.5 m dia head race tunnel terminating in a surge<br />
shaft<br />
• an 80 m high, 10.0 m dia surge shaft<br />
• 230 m long, 3.75 m dia pressure shaft<br />
• an underground power house having an installation <strong>of</strong> 2 Francis<br />
turbine driven generating units <strong>of</strong> 32.5 MW each operating under a<br />
rated head <strong>of</strong> 108.93 m; and<br />
• 190 m long tail race tunnel 5.0 m diameter ‘D’ Shape to carry the<br />
power house releases back to the river<br />
3. HYDROLOGY<br />
The river Bhagirathi drains a catchment area <strong>of</strong> about 2660 sq. km at the<br />
proposed dam site. The water availability for the project i.e. the dependable<br />
flows both for 90% and 50% dependable year have been assessed, based on<br />
Regional model incorporating glacial cover, snow and forest cover and<br />
incorporating data <strong>of</strong> 17 Gauge Discharge sites (13 CWC sites and 4 state<br />
Govt. sites) in the region utilising the available data for the period 1975-76 to<br />
2001-2002 for many <strong>of</strong> the sites. The computed inflow series worked out has<br />
been utilized for <strong>Power</strong> Potential Studies. The design flood has been<br />
assessed as 8495 cumecs (PMF).<br />
4. POWER POTENTIAL STUDIES<br />
The available data <strong>of</strong> water flows on 10 daily basis has been analysed. Water<br />
flows determined on 90% dependable year, have been utilised for computing<br />
power benefits. An installation <strong>of</strong> 65 MW comprising 2 generating units <strong>of</strong><br />
32.5 MW each has been proposed. The energy availability from the project in<br />
a 90% dependable year has been summarized below :<br />
1-2
Annual Energy Generation<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Annual Energy Generation (GWh) : 293.18<br />
Annual Load Factor (%) : 51.49<br />
Generation during Lean Flow Season<br />
Energy Output (MWc) : 11.13<br />
Load Factor (%) : 17.12<br />
The design energy for tariff at 95% availability in a 90% dependable year has<br />
been worked out as 279.45 GWh.<br />
A pondage <strong>of</strong> 0.853 M cum has been provided in the diversion dam which<br />
would enable the station to operate as peaking station. The pondage is<br />
equivalent to 231.94 MWh which is sufficient to operate the station for 3.57<br />
hours.<br />
5. POWER EVACUATION ASPECTS<br />
The 65 MW power guerated at 11 kv at Bairon Ghati HEP will be stepped upto<br />
220 kv by unit step transformers. The power would be taken to nearby<br />
proposed 400/220 kv Chhamli sub station.<br />
6. ENVIRONMENTAL ASPECTS<br />
The project site is located in reserve forest area in Bhagirathi river basin. The<br />
submergence area is 13.27 ha, and majority <strong>of</strong> land falls under the category<br />
<strong>of</strong> forest land (8.36 ha). About 0.55 ha <strong>of</strong> land is coming under reservoir<br />
1-3
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
submergence. In addition, land will also be required for other project<br />
appurtenances. Based on assessment <strong>of</strong> environmental impacts,<br />
management plans have to be formulated for acquisition <strong>of</strong> forest land in<br />
reserve forest area, wildlife conservation, muck disposal, quarry stabilization,<br />
and other environmental issues. These issues would be addressed during the<br />
investigation for DPR.<br />
7. ESTIMATES OF THE COST<br />
The project is estimated to cost Rs. 296.82 Crores including IDC at June,2003<br />
price level. The preliminary cost estimate <strong>of</strong> the project has been prepared as<br />
per guidelines <strong>of</strong> CEA/CWC. The break up <strong>of</strong> the cost estimates is given<br />
below :<br />
Particulars Rs. (in Crores)<br />
Civil Works : 164.94<br />
Electro Mechanical Works : 91.35<br />
Sub Total : 256.29<br />
Interest During Construction : 40.53<br />
Total (Generation) : 296.82<br />
Transmission Works : 7.50<br />
Grand Total : 304.32<br />
8. FINANCIAL ASPECTS<br />
As indicated above, the Bhairon Ghati HE Project, with an estimated cost<br />
(Generation only) <strong>of</strong> Rs. 296.82 Crores (including IDC <strong>of</strong> Rs. 40.53 Crores)<br />
and design energy <strong>of</strong> 279.45 GWh in a 90% dependable year is proposed to<br />
1-4
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
be completed in a period <strong>of</strong> 5 years. The tariff has been worked out<br />
considering a debt-equity ratio <strong>of</strong> 70:30, 16% return on equity and annual<br />
interest rate on loan at 10%. The tariff for first year and levellised tariff (at<br />
power house bus bar) have been worked out as Rs.1.80 /kWh & Rs.<br />
1.57/kWh respectively.<br />
9. CONCLUSIONS<br />
Bhairon Ghati HE Project involves simple civil works and could be completed<br />
in 5 years. The project would afford a design energy <strong>of</strong> 279.45 GWh in a<br />
90% dependable year. The cost per MW installed work out to Rs.3.94 Crores.<br />
The Preliminary Feasibility Report indicates that the scheme merits<br />
consideration for taking up Survey & Investigation and preparation <strong>of</strong> DPR.<br />
1-5
2.1 GENERAL<br />
CHAPTER – II<br />
BACKGROUND INFORMATION<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
In Nov.2000, Uttaranchal State was carved out <strong>of</strong> thirteen hill districts <strong>of</strong><br />
Northern U.P. The state borders with Nepal and Tibet on the east, Central<br />
Himalayas on the north, Haryana and Himachal Pradesh on the west and<br />
northwest respectively.<br />
Geophysically the state has four Mountain Zones namely Foot hills, Lesser<br />
Himalayas, Greater Himalayas and Trans-Himalayas. The mountains are<br />
covered with perpetual snow and glaciers and has gifted the north India a<br />
perennial river system <strong>of</strong> the Ganga and its tributaries. The tributaries <strong>of</strong><br />
Ganga, namely Alaknanda, Bhagirathi, Yamuna and Sarda originate from<br />
the foothills <strong>of</strong> snow capped peaks and glaciers in the Central Himalayas and<br />
incise their respective courses through the rugged terrain, splash and surge<br />
the steep gradients and most <strong>of</strong> the stream <strong>of</strong>fer excellent potential for<br />
Hydro power development.<br />
The region is blessed with magnificent glaciers, majestic rivers, gigantic snow<br />
capped peaks, Valley <strong>of</strong> flowers natural beauty and rich flora and fauna.<br />
Many holy shrines have blessed the state spiritually and given the name <strong>of</strong><br />
Dev Bhoomi or Land <strong>of</strong> Gods. The seasonal influx <strong>of</strong> tourists, the seekers <strong>of</strong><br />
peace for visit to the holy shrines and lovers <strong>of</strong> nature contribute to the state<br />
income.<br />
The state is divided into Kumaon and Garhwal Division with 13 districts<br />
42 tehsils 95 blocks, and 15689 inhabited villages and 73 towns. The<br />
2-1
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
State has a geographical area <strong>of</strong> 53119 sq. km which is 1.62% <strong>of</strong> the total<br />
area <strong>of</strong> the country and supports 84.8 lakh population which is 0.83% <strong>of</strong><br />
the total population <strong>of</strong> India. The percentage <strong>of</strong> villages having population<br />
more than 500 is about 11.4% (1991 Census). The existing majority <strong>of</strong><br />
smaller settlements <strong>of</strong> Uttaranchal pose a serious challenge for economic<br />
infrastructure and lack <strong>of</strong> services to the far flung places in the hilly terrain<br />
makes Uttaranchal as one <strong>of</strong> the extremely backward states <strong>of</strong> India.<br />
It has 76.1% electrified villages as compared to 75.3% <strong>of</strong> villages <strong>of</strong> U.P.<br />
The average per capita consumption <strong>of</strong> electricity is 245.57 kWh whereas<br />
Dehradun and Nainital consume 480.81 and 447.33 kWh respectively<br />
with a minimum consumption <strong>of</strong> 43.7 kwh in Uttarkashi.<br />
2.2 POWER SCENARIO IN NORTHERN REGION<br />
2.2.1 Present Status<br />
Most <strong>of</strong> the states in the Northern Region have been experiencing energy<br />
shortage as well as shortage <strong>of</strong> Peak <strong>Power</strong> <strong>of</strong> varying degree. Actual <strong>Power</strong><br />
supply position in the Northern Region during the year 2001-2002 has been<br />
as under:<br />
Energy (in MU), year 2001-2002<br />
State Require- Availability Shortage(-)/ %age<br />
ment<br />
Surplus (+)<br />
Chandigarh 1110 1108 (-) 2 0.2<br />
Delhi 19350 18741 (-)609 3.1<br />
Haryana 18138 17839 (-)299 1.6<br />
Himachal Pradesh 3293 3206 (+) 87 2.6<br />
Jammu & Kashmir 6635 5899 (-) 736 11.1<br />
Punjab 28780 27577 (-)1203 4.2<br />
2-2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
State Require- Availability Shortage(-)/ %age<br />
ment<br />
Surplus (+)<br />
Rajasthan 24745 24495 (-)250 1.0<br />
Uttaranchal-U.P 48332 43545 (-)4787 9.9<br />
Northern Region 150383 142410 (-)7973 5.3<br />
2.2.2 Peak <strong>Power</strong> (in MW), year 2001-2002<br />
State Peak Peak Met Shortage(-)/ %age<br />
Demand<br />
Surplus (+)<br />
Chandigarh 180 180 0 0.0<br />
Delhi 3118 2879 (-)239 7.7<br />
Haryana 3000 2900 (-)100 1.6<br />
Himachal Pradesh 562 562 0 0.0<br />
Jammu & Kashmir 1209 999 (-) 210 17.4<br />
Punjab 5420 4936 (-)484 8.9<br />
Rajasthan 3700 3657 (-)43 1.2<br />
Uttaranchal-U.P 7584 6887 (-)607 9.2<br />
Northern Region 24773 23000 (-)1773 7.2<br />
2.3 NECESSITY OF HYDRO POWER DEVELOPMENT IN UTTARANCHAL<br />
2.3.1 Hydro and Thermal <strong>Power</strong> Mix<br />
The main resources for generating electricity are by utilising the hydro<br />
potential available along the river drops besides the use <strong>of</strong> fossil fuel.<br />
Presently the ratio <strong>of</strong> thermal generation and Hydro-electric generation in<br />
Uttaranchal <strong>Power</strong> grid, is quite disproportionate. With the diminishing coal<br />
resources and difficult oil position all over the world, it is necessary that<br />
2-3
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
electric generation be aimed to achieve the economic balance <strong>of</strong> 40:60<br />
between the hydro and thermal generation <strong>of</strong> power, as against the existing<br />
25:75 ratio.<br />
2.4 BRIDGING THE GAP OF HYDRO POWER GENERATION<br />
The requirement <strong>of</strong> power in Uttranchal is very fluctuating because <strong>of</strong> many<br />
seasonal and other similar demands <strong>of</strong> industries. To improve the share <strong>of</strong><br />
hydro-power generation it is essential to develop the hydroelectric power<br />
potential <strong>of</strong> state which is about 15110 MW, <strong>of</strong> which so far only 8% has been<br />
developed.<br />
The existing installed generating capacity in the<br />
State is about 1286 MW ( 2003 fig) and the whole is contributed by hydro<br />
generation. There is no thermal power generation in the state . The major<br />
hydro power stations under construction in the state are (i) Maneri Bhali,<br />
Stage-II (304 MW), (ii) Lakhawar Vyasi, Stage-I (300 MW), (iii) Lakhwari<br />
Vyasi, Stage-II (120 MW), (iv) Srinagar H.E. Project (330 MW), (v)<br />
Vishnuprayag Scheme (400 MW), (vi) Tehri Dam Project, Stage-I (1000 MW),<br />
(vii) Tehri Dam Project, Stage-II (1000 MW), (viii) Koteshwar Dam Project<br />
(400 MW), and (ix) Dhauliganga H.E. Project, Stage-I (280 MW).<br />
With rising hydro power generation and improving efficiencies in distribution<br />
<strong>of</strong> electricity, Uttaranchal hopes to <strong>of</strong>fer energy at stable prices for ec<strong>of</strong>riendly<br />
industrial development. Though the state is more or less sufficient<br />
in its energy generation to meet its own requirement, there is an urgent need<br />
to develop its huge untapped hydro power potential in an early and efficient<br />
manner, manage efficiently the hydro generation capacity <strong>of</strong> existing power<br />
stations and to develop and promote new Hydro projects with the purpose<br />
2-4
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
<strong>of</strong> harnessing hydropower resources in the state for economic well being and<br />
growth <strong>of</strong> the people in the whole region.<br />
In order to meet the load demand satisfactorily, it is considered essential to<br />
maintain a minimum gross margin <strong>of</strong> about 30 per cent over the projected<br />
peak demand while planning for expansion <strong>of</strong> power supply facilities.<br />
To bridge the gap between the demand for power and the availability <strong>of</strong><br />
power, some <strong>of</strong> the major hydro-electric schemes identified in Ganga Valley<br />
for development are indicated below :<br />
i Tapovan<br />
(360 MW)<br />
Vishnugad<br />
ii Bowala<br />
(132 MW)<br />
Nandprayag<br />
viii Karanprayag Dam (252 MW)<br />
ix Lata Tapovan (108 MW)<br />
iii Kishau Dam (600 MW) x Vishnugad Pipalkoti (340 MW)<br />
iv Pala Maneri (416 MW) xi Pancheshwar Dam<br />
v Loharinag<br />
MW)<br />
Pala (520<br />
xii Chamgad Dam (400 MW)<br />
vi Koth Bhel (1000 MW) xiii Dhauliganga, Stage-II<br />
vii Utyasu Dam (1000 MW)<br />
The location <strong>of</strong> H.E. Schemes are indicated in Plate-1 enclosed.<br />
2.5 PRESENT STUDIES<br />
2.5.1 With a view to prioritize the large number <strong>of</strong> identified schemes to harness<br />
vast untapped hydro resources in the order <strong>of</strong> their attractiveness for<br />
implementation, Ranking studies were carried out by CEA. Subsequently,<br />
2-5
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
after consultation process initiated by <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong> with various state<br />
agencies, CPSUs etc., it was considered appropriate that Preliminary<br />
Feasibility Report (PFRs) <strong>of</strong> selected hydroelectric projects be taken up so<br />
that feasibility <strong>of</strong> the scheme considered in ranking studies could be<br />
established.<br />
2.5.2 In order to achieve the above objective the present preliminary feasibility<br />
stage report presents the Bhairon Ghati H.E Project located in Uttarkashi<br />
district, as detailed in the subsequent Chapters.<br />
2-6
3.1 GENERAL<br />
CHAPTER –III<br />
THE PROJECT AREA<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The Bhairon Ghati H.E. Project is located on Bhagirathi river immediately after<br />
the confluence <strong>of</strong> Jadhganga river joining it from the north at Bhairon Ghati<br />
township. The river originates <strong>of</strong> E1 7010 m from Gangotri glaciers and flow<br />
west wards. It passes through the rugged terrain, incise its course through<br />
steep gradients. The Bhairon Ghati H.E. Project is second H.E. Project on<br />
Bhagirathi after Gangotri H.E. Project for development <strong>of</strong> hydro power in<br />
cascade. Bhairon Ghati H.E. Project utilise the river bedfall <strong>of</strong> about 100 m<br />
with the intake located at bed level <strong>of</strong> E1 2610 m and tail race outlet level river<br />
bed at E1 2510.m.<br />
The Bhairon Ghati H.E. Project is a Run-<strong>of</strong>f-the-River scheme with the<br />
arrangement <strong>of</strong> dam and gates a small diurnal storage is created. It is<br />
proposed to locate the intake at bedlevel EL 2610 m which is about 500 m<br />
down stream after its confluence with Jadhganga river in Uttarkashi District at<br />
Lat. 31 0 1’ 55”N and Long 78 0 51’ 35” E. The project diversion structure site is<br />
approached by railway upto Rishikesh and further 267 km by road via Tehri-<br />
Uttarkashi-Jadhganga highway or from Uttarkashi the intake is about 97 km.<br />
The intake proposes to pass a discharge <strong>of</strong> about 66.4 cumecs through a<br />
head race tunnel <strong>of</strong> 4.5 m dia (horse shoe shaped) <strong>of</strong> 5.1 km length to the<br />
under ground power house proposed to be located at Lat 31 0 2’ 30” N and<br />
Long 78 0 48’ 23” E. The tail race <strong>of</strong> 190 m long leads the discharges back to<br />
the river. The power house utilises an average hydraulic head <strong>of</strong> about<br />
132.0 m.<br />
3-1
3.2 CLIMATE<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The available IMD observatory is at Dehradun which hardly represents the<br />
climate <strong>of</strong> Uttarkashi District. However at Dehradun peak winter extend from<br />
Dec. to Jan. months where the temperature remains at 2 0 C and during May-<br />
June months the maximum temperature is around 40 0 C. Rainfall during<br />
monsoon period (June to Sept. ) is about 2770 mm. Large climatic variations<br />
are experienced with in the sub basins at higher altitudes in the sub basins <strong>of</strong><br />
the Ganga. The project is located on the Bhagirathi basin the climate <strong>of</strong><br />
Bhairon Ghati could be considered more synonymous to Badrinath Metstation<br />
(IMD) which is in the adjoining Alaknanda basin. Here substantial<br />
snowfall occurs during winter months ( Dec.-April) with average seasonal<br />
snowfall <strong>of</strong> about 4600 mm. Although some snowfall is experienced in other<br />
months also except during June and July months.<br />
3.3 SOCIO ECONOMIC PROFILE<br />
The entire state has undulating topography with l<strong>of</strong>ty mountains jutting out<br />
and create the rugged terrain with steep valleys. The geology soil texture and<br />
climate are highly variable including the habitation pattern. It has sparse and<br />
scanty population, small sized villages, scattered on the hilly land scape.<br />
Out migration <strong>of</strong> able bodied person is common, subsistance level agriculture<br />
based economy mostly prevails with marginal holdings, the infrastructural<br />
development becomes very costly.<br />
Uttarkashi District has an area <strong>of</strong> 15.8% and supports 4% population as<br />
compared to the state. It has lowest density <strong>of</strong> population <strong>of</strong> about 30<br />
persons per sq. km. as against that <strong>of</strong> 116 persons per sqkm <strong>of</strong> the state.<br />
The litracy rate both among total (men and female) and female is lowest in the<br />
district standing at 47.2% and 23.6% as against state average <strong>of</strong> 59.6 and<br />
3-2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
42.9% respectively. It has largest population <strong>of</strong> schedule casts <strong>of</strong> about<br />
22.8% against state average <strong>of</strong> 16.7%.<br />
The main work force <strong>of</strong> about 75% are engaged in primary and secondary<br />
sectors and balance in allied sectors. As regards land use pattern about 70%<br />
<strong>of</strong> land is under forest and barran lands.<br />
About 64% <strong>of</strong> the inhabited villages are connected with road and the<br />
remaining villages suffer because <strong>of</strong> remoteness and higher altitudes.<br />
As regard rural electrification Uttaranchal has 76.1% electrified village and the<br />
per capita consumption <strong>of</strong> electricity <strong>of</strong> the state is about 245.6 Kwh.<br />
However, Dehradun and Nainital have much higher consumption where as<br />
Uttarkashi has the least <strong>of</strong> 43.7 kwh consumption.<br />
3-3
CHAPTER – IV<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
TOPOGRAPHY AND GEOTECHNICAL ASPECTS<br />
4.1 TOPOGRAPHY & PHYSIOGRAPHY<br />
The terrain is highly undulating with jutting peaks, steep valleys the rivulets<br />
and tributaries cut across and negotiate the mountains with rapids and<br />
steep gradients. The major tributaries <strong>of</strong> Bhagirathi, Alakananda,<br />
Yamuna, Tons originate from the foot <strong>of</strong> glaciers and snow capped<br />
peaks. The pucca road network cover only 64% <strong>of</strong> the inhabitated<br />
villages in Uttaranchal state and rest <strong>of</strong> the villages are not be covered<br />
by roads due to higher altitude and remoteness <strong>of</strong> the areas. Bhagirathi<br />
river on which Bhairon Ghati H.E. Project is located originates at EL-<br />
7010 m at the foot <strong>of</strong> glaciers and flow westwards, direction before it joins<br />
Alkananda at Devprayag.<br />
Present PFR studies do not envisage topographical surveys and hence<br />
this write up is confined to physiographical aspects only.<br />
4.2 REGIONAL GEOLOGY<br />
The topography <strong>of</strong> the area around the proposed scheme is located in inner<br />
parts <strong>of</strong> Lesser Himalayas and outer parts <strong>of</strong> Central Himalayan is<br />
extremely rugged. In Central Himalayan portion the E-W rending strike<br />
ridges are characterized by steep northerly dip slopes and southerly<br />
obsequent escarpments. In the inner parts <strong>of</strong> Lesser Himalayan Zones, the<br />
trend <strong>of</strong> ridges has been modified and controlled by the folding <strong>of</strong> rocks. The<br />
main drainage <strong>of</strong> the area is Bhagirathi River which originates form<br />
Gangotri Glacier at Gaumukh. In the upper reach, the river is fed by<br />
4-1
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
numerous streams such as Jadhganga, Jalandra Gad and Siam Gad. These<br />
streams appear to be subsequence to joints in granite. The drainage pattern<br />
in Central Crystalline country is rectangular. In the rock <strong>of</strong> Garhwal<br />
Group, the tributary streams are mainly transversal.<br />
The Bhagirathi valley is characterized glacial and U shaped upstream <strong>of</strong> Sukhi<br />
Gaumukh. A rapid down cutting by the river has formed a deep narrow<br />
gorge between Gangotri and the Jangla Bridge. Downstream <strong>of</strong> Jangla,<br />
up to Jhala Bridge, the narrow gorge has been filled by sand and gravel<br />
due to the silting connected with the damming <strong>of</strong> river at Sukhi by a<br />
landslide. Further downstream <strong>of</strong> Suklhi, the true pr<strong>of</strong>ile <strong>of</strong> valley has<br />
been masked as a result <strong>of</strong> massive landslides.<br />
The rock <strong>of</strong> the area have been grouped in to Garhwal Group, Central<br />
Crystalline and the meta sedimentaries, possibly equivalent to Martloi<br />
Formation by Kumar, Agarwal and Mukerjee (1969-79). The tectonic<br />
sequence observed in the area is as follows:<br />
NORTH<br />
Meta-sedimentaries Black slates, garnet mica intruded by biotite schist,<br />
quartz-biotite granite, tourmaline schist, garnet-mica<br />
granite aplite & schist, banded augen pegmatite<br />
gneiss (Martoli Formation)<br />
FAULT<br />
Central Crystallines Kyanie-garnet-mica schist and inter bedded augen<br />
and porphyritic gneiss, banded augen gneiss and<br />
garnet mica schist containing tourmaline, migmatite<br />
zone <strong>of</strong> mica schist gneiss, granite, amphibolite and<br />
marble/calc- silicate.<br />
4-2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
MAIN CENTRAL THRUST (MCT)<br />
Garhwal Group Upper massive quartzite, white to light grey and green<br />
coloured, fine grained to gritty, occasionally<br />
schistose, current and graded bedded. Metavolcanics<br />
- occasionally with pillow lava structure, lenticular<br />
limestone/dolomite with slate and minor quartzite;<br />
Lower quartzite and slate.<br />
4.3 GEOLOGICAL FEATURES OF THE PROJECT COMPONENTS<br />
The Bhairon Ghati Hydro-electric Scheme envisage the utilisation <strong>of</strong>. 66.4<br />
Cumecs designed discharge and about 100 m <strong>of</strong> river bed fall available<br />
on the river Bhagirathi between Bhairon Ghati and Markande for<br />
generation <strong>of</strong> 11.13 MW firm power with an installed capacity <strong>of</strong> 65<br />
MW. The diversion structure site is located at an EL 2610.0 and may<br />
encounter problems <strong>of</strong> snow – ice covering the entire river section and<br />
avalanches during the winter months.<br />
At the proposed diversion site, the river Bhagirathi flows from<br />
55 0 E to N50 0 W direction . At the site tourmaline granite traversed by<br />
pegmatite veins is exposed on both the banks <strong>of</strong> the river upto a height <strong>of</strong><br />
nearly 60-70 ms. At this height, both the banks have detached/transported<br />
blocks <strong>of</strong> rocks with soil and support a forest. farther higher up, both the<br />
banks <strong>of</strong> the river are covered with forest with occasional exposed rock<br />
along the alignment <strong>of</strong> the dam. The tourmaline granite is white in colour<br />
with dark coloured laths and specks <strong>of</strong> tourmaline and is designated as<br />
gangotri granite. It is intrusive in the county rock which are represented<br />
essentially by granite – gneiss with subordinate bands <strong>of</strong> schists, quartzite,<br />
phyllite and amphibolite.<br />
4-3
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The diversion site <strong>of</strong> the proposed HE. Scheme has a geological and<br />
topographical, Setting similar to that <strong>of</strong> the diversion site <strong>of</strong> the Gangotri<br />
HE. Scheme, located about 9 Km. farther upstream Consequently, the<br />
proposed diversion site also shows similar geological and topographical<br />
deficiencies as far as siting <strong>of</strong> a dam at the site is concerned. These<br />
deficiencies are briefly enumerated below:<br />
1. The diversion site is located around EL 2610.0 m and may<br />
experience problems <strong>of</strong> snow/ice covering the entire river section and<br />
<strong>of</strong> avalanches during the winter months.<br />
2. The depth <strong>of</strong> overburden in the river section at the dam site may be<br />
high and may be <strong>of</strong> the order <strong>of</strong> over 10-15 m.<br />
3. The base width <strong>of</strong> the gorge at the dam site, limited to approximately<br />
30-40 m is completely occupied by the river and there is no space<br />
for locating the sedimentation/ de-silting structure. Therefore, the<br />
structure may have to be planned underground.<br />
4. The tourmaline granite is the steep gorge <strong>of</strong> the river at the diversion<br />
site is highly jointed and some <strong>of</strong> the joints are quite open.<br />
Therefore, the extent <strong>of</strong> slumping at rock on both the banks <strong>of</strong> the<br />
river is likely to be considerable. Consequently, the extent <strong>of</strong><br />
abutment stripping for removal <strong>of</strong> slumped rock, in order to found the<br />
diversion structure on sound rock would also be larger. This limit<br />
will have to be proved by exploratory drifts in the next stage <strong>of</strong> the<br />
project development/planning. However, at the present stage it may<br />
be assigned to be <strong>of</strong> the order <strong>of</strong> 10-15m at the HFL <strong>of</strong> the river<br />
and 25-30m at the crest level <strong>of</strong> the proposed dam. Slope<br />
stabilization measures above the stripped abutment would have<br />
to be planned and executed soon after stripping operation is over.<br />
4-4
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
5. The head race tunnel which would conduct the water to the power<br />
house is located on the left bank <strong>of</strong> the river Bhagirathi. HRT is<br />
aligned is the direction S 80 0 E – N 80 0 W. The tunnel from the<br />
dam site and, for about one-half <strong>of</strong> its total length would be driven<br />
through the tourmaline granite and remaining one-half <strong>of</strong> the tunnel<br />
upto the power house site would be driven essentially though the<br />
granite – gneiss with subordinate bands <strong>of</strong> schist, quartzite, phyllite<br />
and amphibolite <strong>of</strong> the Central Crystalline Group. These rocks<br />
generally strike N 45 0 W - S 45 0 E to N60 0 W - S 60 0 E with dip <strong>of</strong><br />
45 0 – 50 0 towards north-east. Thus, the headrace tunnel would be<br />
driven at angles <strong>of</strong> 20 0 – 30 0 with respect to the strike <strong>of</strong> the rocks.<br />
Such a direction is not very favourable for execution <strong>of</strong> the tunnel<br />
and may result in some extra overbreak.<br />
The power house for the Bhairoghati HE. Scheme was originally<br />
proposed on the surface near the confluence <strong>of</strong> Sartia Gad with<br />
river Bhagirathi, opposite village Markande. However, the hill slope<br />
between the left bank <strong>of</strong> the river Bhagirathi and the right bank <strong>of</strong> the<br />
Sartia Gad being unstable, the site was not favoured & hence it<br />
was suggested for an alternative site farther upstream <strong>of</strong> the<br />
location. The alternative site lies about 750 m upstream <strong>of</strong> the site<br />
proposed earlier. At the alternative site granite-gneiss are exposed<br />
earlier. At the alternative site granite – gneiss are exposed at the<br />
motor road level. However, enough space for locating the power<br />
house on the surface is not available at the site. It is, therefore,<br />
recommended that the power house may be planned as a semiunderground<br />
or completely underground structure.<br />
4-5
4.4 GEOTECHNICAL APPRAISAL<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The proposed Bhairon Ghati Hydroelectric Project envisages to. utilize the<br />
head along Bhagirathi River between the confluence <strong>of</strong> Jadhganga with<br />
Bhagirathi and Dhorali. The diversion structure <strong>of</strong> this scheme is proposed to<br />
be located in narrow and deep valley <strong>of</strong> Bhagirathi just downstream <strong>of</strong> the<br />
confluence where the powerhouses is proposed to be located. The valley <strong>of</strong><br />
intake structure is expected to be narrow one with sub vertical abutments. It<br />
is suggested that the final location <strong>of</strong> the diversion structure be decided after<br />
<strong>of</strong> over burden in the river bed and stability <strong>of</strong> abutments. The site exposes<br />
biotite granite, which is intruded by tourmaline granite. It is medium to coarse<br />
grained and occasionally porphyritic. The 5.1 km long headrace tunnel may<br />
encounter these biotite granites intruded by tourmaline granite, aplite and<br />
pegmatite. The rock is expected to provided fair to good tunneling media<br />
except in the reaches where there are closely jointed, sheared or locally<br />
faulted. The powerhouse is located near<br />
the confluence <strong>of</strong> Sartia Gad with Bhagirathi. The river valley is wide in this<br />
reach and adequate space for locating the structure and its appurtenants may<br />
be available. However, it is suggested that the powerhouse be located above<br />
HLF <strong>of</strong> Bhagirathi. This geotechnical appraisal is based on the regional<br />
geological set up.<br />
4.5 SEISMOTECTONICS AND SEISMICITY<br />
Seismotectonically, the project area is located in Main Himalayan Seismic<br />
Zone demarcate by the Main Boundary Thrust (MBT) in south and downdip<br />
influence zone <strong>of</strong> the Main Central Thrust (MCT) in north, demonstrating<br />
predominantly thrust type <strong>of</strong> fault plane mechanism. It has been interpreted by<br />
4-6
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Narula (1991) that the strain buildup in different sectors <strong>of</strong> this domain is<br />
taking place at different locales and in Uttarkashi-Kumaon sector, this is<br />
Concentrated around the MCT as evidenced by the clustering <strong>of</strong> the seismic<br />
events in this subdomain to be around, this structural dislocation. The seismic<br />
status,infact has been a subject <strong>of</strong> interest for quite some time, though direct<br />
geological evidences <strong>of</strong> geotectonic activity have not been recorded in the<br />
area. According to Narula (1991), the project area falls in Garhwal Seismic<br />
Block which, is constrained by Alaknanda tectonic flux fault..in the east and<br />
Kautir or Kinnaur Faults in west. This domain contains another tectonic flux<br />
fault which is located in the project area.<br />
MBT & MCT are the two major dislocation features <strong>of</strong> significance in the<br />
project area located about 20 km to 35 km in the southern direction.<br />
Seismically the project area traverses through highly active Himalayan<br />
seismic belt and falls in seismic zone V <strong>of</strong> the seismic zoning map <strong>of</strong><br />
India [ IS 1893 (Part-I): 2002]. Therefore, a suitable seismic factor would<br />
have to be adopted for designing the structures in the area.<br />
4.6 SEISMIC REFRACTION SURVEY<br />
Seismic Refraction Survey conducted at Baironghati site depicts the<br />
presence <strong>of</strong> rock line at shallow depth near the banks but the rock line<br />
goes below 5-25 meters from the river bed.<br />
Based on velocity model three broad layers can be classified, a thick<br />
alluvium, an intermediate layer and rock with different units <strong>of</strong> subsurface<br />
layers (Plate-4.1).<br />
4-7
5.1 GENERAL<br />
CHAPTER - V<br />
HYDROLOGY<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The Ganga river is one <strong>of</strong> the holiest rivers in India and many temples and<br />
religious places are situated on its banks right from its origin to its confluence<br />
near Sagar Island with Bay <strong>of</strong> Bengal. It drains an area <strong>of</strong> 8.61 lakh sq km<br />
and the basin is one <strong>of</strong> the most fertile basins <strong>of</strong> the country.<br />
Bhagirathi and Alaknanda are the two major tributaries <strong>of</strong> Ganga which<br />
originate from Bhairon Ghati and Kamet glacier in Uttarkashi and Chamoli<br />
districts respectively <strong>of</strong> Uttranchal state. Bhagirathi originates at an elevation<br />
<strong>of</strong> 7010 m while Alaknanda rises at an elevation 7800m. Both the Bhagirathi<br />
and Alaknanda rivers join at Deoprayag and thereafter it is known as Ganga.<br />
Jadhganga s the first major tributary <strong>of</strong> Bhagirathi originating near Tagala at<br />
an elevation 5300m and joins Bhagirathi at Bhairon Ghati. The river has very<br />
steep slopes in upper reaches and most <strong>of</strong> the area is covered by permanent<br />
snow and glaciers. Due to steep slopes and area covered by snow, there<br />
exists considerable quantity <strong>of</strong> perennial flow and as such have a large<br />
potential for hydropower development, though irrigation may not be feasible<br />
due to non existence <strong>of</strong> command area. CEA had identified several hydro<br />
electric sites in the basin. The Bhairon Ghati Hydro-Electric Project<br />
(CA=2660sq km) is identified downstream after confluence <strong>of</strong> Jodhganga with<br />
Bhagirathi river. The catchment area map <strong>of</strong> the Project is shown in Plate 5.1.<br />
This report contains the results <strong>of</strong> the Hydrological studies made for Bhairon<br />
Ghati H.E. scheme. The detailed studies in respect <strong>of</strong> water availability and<br />
5 -1
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Design flood are available in the report “ Hydrological studies – Volume I,<br />
Ganga basin” September, 2003.<br />
5.2. HYDROMEOTEROLOGICAL DATA<br />
No rainfall and discharge data at Bhairon Ghati site is available. However,<br />
observed discharges from 1971 – 72 at Uttarkashi (CA=4504 sq km) are<br />
available. The site is maintained by CWC. Discharge data for longer periods<br />
are available at 17 G&D sites (13 CWC sites and 4 States Governments) in<br />
the region, which are much downstream <strong>of</strong> Bhairon Ghati site. The data<br />
availability is given as under which has been utilised for developing the<br />
Regional Model.<br />
Table -1<br />
Sl. Name <strong>of</strong> River Organisation Period<br />
No. Station<br />
1 Tehri Bilanganga CWC 1975-76 to 2001-02<br />
2 Joshimath Alakananda CWC 1975-76 to 2001-02<br />
3 Tehri Bhagirathi CWC 1975-76 to 2001-02<br />
4 Deoprayag Ganga CWC 1975-76 to 2001-02<br />
5 Maror Nayar CWC 1975-76 to 2001-02<br />
6 Deoprayag Bhagirathi CWC 1975-76 to 2001-02<br />
7 Rudraprayag Mandakini CWC 1975-76 to 2001-02<br />
8 Rishikesh Ganga CWC 1975-76 to 2001-02<br />
9 Rudraprayag Alakananda CWC 1975-76 to 2001-02<br />
10 Nandkesri Pinder CWC 1994-95 to 2001-02<br />
11 Chandrapuri Mandakini CWC 1976-77 to 2001-02<br />
12. Karnprayag Pindar CWC 1976-77 to 2001-02<br />
13 Uttarkashi Bhagirathi CWC 1971-72 to 2001-02<br />
14 Raiwala Ganga State Govt. 1946-47 to 1983-84<br />
15 Maneri Bhagirathi State Govt. 1964-65 to 1984-85<br />
16 Lambagarh Alakananda State Govt. 1969-70 to 1990-91<br />
17 Tapovan Alakananda State Govt. 1973-74 to 1981-82<br />
5 -2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Long term flood peaks are available at Raiwala on Ganga (1901 to 1992),<br />
Tehri on Bhagirathi (!963 to 1978), Maneri at Bhagirathi (1964 to 84) besides<br />
at G&D sites on Alaknanda, Sarda, Tons and Yamuna rivers.<br />
5.3 ESTIMATION OF WATER AVAILABILITY<br />
5.3.1 Regional Model<br />
The proposed Bhairon Ghati site is in high altitude area whose major portion<br />
<strong>of</strong> the catchment (a small fraction <strong>of</strong> the nearest observed G&D catchment<br />
area) area is covered by snow and glaciers. As such the traditional method <strong>of</strong><br />
rainfall run <strong>of</strong>f or run <strong>of</strong>f-run <strong>of</strong>f model may not be feasible due to non<br />
availability <strong>of</strong> requisite data. A regional model has been developed on 10 daily<br />
basis utilising the 10 daily flows <strong>of</strong> each 17 G&D sites (CWC and State<br />
Government) together with the mean annual catchment rainfall and the<br />
percentage <strong>of</strong> area intercepted by glacier, snow and forest. The general<br />
format <strong>of</strong> the linear model for the G&D site is as under:<br />
q = K + a * s + b * g + c * f + d * (RF)<br />
or Q = K * (CA) + a * (SA) + b * (GA) + c * (FA) + d * (RF) * (CA)<br />
Where, q = Average specific yield <strong>of</strong> G&D site<br />
Q = Average yield <strong>of</strong> G&D site<br />
CA = Total catchment area in sq. km<br />
GA = Total area under glacier in sq.km<br />
SA = Intermediate area between glacier and permanent<br />
snow line in sq.km<br />
FA = Total forest area in sq.km<br />
5 -3
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
RF= Mean annual catchment rainfall in mm<br />
K, a, b, c, d = Constant <strong>of</strong> the model<br />
S = percentage <strong>of</strong> net snow area to total catchment area<br />
G = percentage <strong>of</strong> glacier area to total catchment area<br />
F = percentage <strong>of</strong> forest area to total catchment area<br />
The linear regional model was developed for Bhagirathi and Alaknanda basin.<br />
After studying the physical parameters responsible for run <strong>of</strong>f for each<br />
catchment upto G&D site, the one parameter, two parameter, three parameter<br />
and four parameter linear models have been developed for each 10 daily<br />
block period. The one parameter model considers the specific yield <strong>of</strong> G&D<br />
sites Vs catchment area, whereas the remaining models consider the<br />
catchment area, glacier area, forest area, net snow area, mean annual<br />
catchment rainfall and the specific yield. After attempting the various<br />
permutations and combinations, the model which gives the maximum<br />
correlation coefficient was selected for estimating the dependable flows at<br />
Bhairon Ghati site.<br />
5.3.2 Dependable flows<br />
Using the most suitable regional model developed for each 10 daily block, the<br />
90%, 50% dependable flows and the average flows have been computed for<br />
the Bhairon Ghati project site (CA=2660 sq. km) as under:<br />
5 -4
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Units:m 3 /sec<br />
Items June I June II June III July I July II July III Aug I Aug II Aug III<br />
90% 75.0 98.7 126.6 106.5 126.9 173.5 139.3 145.3 121.8<br />
50% 138.5 183.9 222.3 196.3 241.5 254.3 253.3 237.0 198.2<br />
Average 149.9 187.7 235.9 214.9 248.3 266.0 255.1 239.3 202.2<br />
Sep I Sep II Sep III Oct I Oct II Oct III Nov I Nov II Nov III<br />
90% 88.7 69.8 53.8 42.5 28.5 27.9 24.0 20.9 18.0<br />
50% 162.4 125.5 87.1 66.0 47.5 44.0 39.9 32.8 27.5<br />
Average 170.3 131.5 93.1 69.6 52.9 47.4 43.0 34.7 29.4<br />
Dec I Dec II Dec III Jan I Jan II Jan III Feb I Feb II Feb III<br />
90% 12.7 12.1 10.3 12.9 12.3 12.5 12.2 11.0 10.3<br />
50% 20.4 19.5 18.8 19.6 19.6 19.1 18.5 17.9 17.4<br />
Average 21.6 20.9 20.4 20.1 19.9 19.7 19.4 18.3 17.8<br />
Mar I Mar II Mar III Apr I Apr II Apr III May I May II May III<br />
90% 10.4 10.0 10.7 11.9 10.4 16.9 26.3 31.6 45.5<br />
50% 17.1 17.5 18.9 20.3 25.6 33.0 45.2 60.1 79.6<br />
Average 18.2 19.0 19.8 21.4 26.7 35.2 48.4 65.6 83.5<br />
5.4 Estimation <strong>of</strong> Design Flood<br />
Since the contentious discharge data for rainy season and concurrent rainfall<br />
is not available, it is not possible to estimate the design flood by unit<br />
Hydrograph method.<br />
The peak flood discharge at Bhairon Ghati site has been estimated based on<br />
the methodology indicated in the Flood Estimation Report for Western<br />
Himalayas, Zone 7 <strong>of</strong> CWC and Regional Frequency analysis (based on 5<br />
and 10 G&D sites) and Synthetic unit hydrograph approach based on<br />
Snyder’s method. The results <strong>of</strong> the study are as under:<br />
5 -5
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Return Period<br />
Methodology 100 years<br />
(m 3 500 years<br />
/sec) (m 3 PMF<br />
/sec) m 3 /sec<br />
i) Flood Estimation Report, CWC<br />
5192 - 8495<br />
ii) Regional Frequent Analysis<br />
(5 G&D sites).<br />
iii) Regional Frequency Analysis<br />
(10 G&D sites).<br />
iv) Snyder’s Method<br />
v) Recommended Design flood<br />
value.<br />
3588 4560 -<br />
4397 5125 -<br />
3432 - -<br />
- - 8495<br />
As furnished above design flood (PMF) <strong>of</strong> 8495 m 3 /sec is recommended for<br />
studies. The computations are enclosed at Annexure 5.1.<br />
5.5 SEDIMENTATION<br />
Since Bhairon Ghati site HE scheme is identified as run <strong>of</strong> the river scheme,<br />
the sedimentation studies are not considered necessary as in the case <strong>of</strong><br />
storage structures. However, based on the experience gained at variousi<br />
<strong>Power</strong> Stations in that valley, it is proposed to exclude silt particles <strong>of</strong> size<br />
0.25 mm and above from the water before it enters the power house. This<br />
aspect will be considered while designing the civil structures.<br />
5 -6
5.6 OBSERVATION OF CWC<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The draft report <strong>of</strong> this project was submitted to CEA for perusal during<br />
October ’03. The observations received from CWC on hydrological studies <strong>of</strong><br />
this project and the replies for above observations, submitted by WAPCOS<br />
are enclosed as Appendix 1.1 and 1.3.<br />
5 -7
6.1 INTRODUCTION<br />
CHAPTER – VI<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
CONCEPTUAL LAYOUT AND PLANNING<br />
Bhairon Ghati H.E. Project is proposed as Run-<strong>of</strong>f-the River scheme on the<br />
river Bhagirathi to tap its hydropower potential. The diversion structure is<br />
located 500 m downstream <strong>of</strong> confluence <strong>of</strong> the river Jadhganga with<br />
Bhagirthi flowing from the north in Uttarkashi district <strong>of</strong> Uttaranchal State. The<br />
project envisages to divert the water <strong>of</strong> Bhagirathi into water conductor<br />
system by means <strong>of</strong> a diversion structure (a concrete gravity dam) across the<br />
river. The water conductor system comprises <strong>of</strong> an intake, underground<br />
desilting chambers followed by a 5.1 km long head race tunnel <strong>of</strong> 4.5 m<br />
diameter (horse shoe shape), a surge shaft <strong>of</strong> 10 m diameter, a pressure<br />
shaft which bifurcates near power house to feed two units <strong>of</strong> 32.5 MW housed<br />
in an underground power house. A 190 m long tail race tunnel discharges<br />
the water back into the river Bhagirathi river upstream <strong>of</strong> Harsil H.E. Project<br />
head works.<br />
6.2 LAYOUT STUDIES<br />
6.2.1 The Bhagirathi river rises at EL 7010 m and falls steeply untill Gaumukh at EL<br />
4000 m to Bhairon Ghati, the river bed fall is about 1000 m in 50 km stretch.<br />
Thereafter, it runs in a gentle to steep slopes in various stretches and is joined<br />
by Jadhganga at EL 2625.0 m.<br />
As per CEA assessment studies the hydro-potential <strong>of</strong> river Bhagirathi is<br />
proposed to be exploited by potential schemes in a cascade development and<br />
6-1
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
the projects serially planned are Gangotri, Bhairon Ghati, and Harsil Schemes<br />
now proposed for PFR studies.<br />
6.2.2 The entire stretch <strong>of</strong> river between proposed diversion site <strong>of</strong> Bhairon Ghati<br />
scheme to power house site was inspected by WAPCOS expert team and it<br />
was observed that both the banks <strong>of</strong> Bhagirathi are occupied by massive<br />
steep rocky slopes highly jointed and fractured. The weathered zone is<br />
expected to extend 10-15 m deep. The pondage created at this site selected<br />
shall be within safe levels <strong>of</strong> the upstream projects.<br />
6.2.3 As per CEA proposal, the diversion site for Bhairon Ghati H.E. scheme as<br />
proposed d/s <strong>of</strong> the confluence <strong>of</strong> Jadhganga, the diversion site is kept at the<br />
same location with river bed level EL 2610.0 m. However, surface <strong>Power</strong><br />
House site opposite to Sarita Gad as proposed by CEA is not found suitable<br />
due to stability problems. Another site was selected by the expert team<br />
during there site visit which is about 750 m u/s <strong>of</strong> the site proposed by CEA<br />
and an underground power house is proposed by WAPCOS instead <strong>of</strong><br />
surface power house.<br />
6.3 RIVER DIVERSION WORK<br />
6.3.1 The aspect <strong>of</strong> isolating the site for construction activity in the deep river valley<br />
portion was examined for two scenarios i.e. with and without the provision <strong>of</strong><br />
diversion tunnel through abutment. As the diversion site is located in a<br />
narrow valley it was not found practical to isolate the construction area without<br />
the provision <strong>of</strong> diversion tunnel.<br />
6-2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
6.3.2 A diversion tunnel <strong>of</strong> 4.5 m diameter circular and 500 m long is proposed<br />
along left bank to divert the discharge <strong>of</strong> 80 cumecs for the construction <strong>of</strong><br />
dam & appurtenant works. However, during monsoon season, excess<br />
discharges beyond the capacity <strong>of</strong> diversion tunnel is expected to pass over<br />
the c<strong>of</strong>fer dam and over the constructed portion <strong>of</strong> the dam. The diversion<br />
tunnel inlet is proposed to be provided with a gate <strong>of</strong> size 5 m x 5 m which will<br />
be operated by means <strong>of</strong> a rope drum hoist for purposes <strong>of</strong> closure <strong>of</strong> the<br />
diversion tunnel. Suitable c<strong>of</strong>fer dams located approximately 100 m u/s &<br />
150 m d/s <strong>of</strong> the dam axis are proposed. The u/s c<strong>of</strong>fer dam will be 7 m high<br />
with 6 m base width while the d/s c<strong>of</strong>fer dam will be 6 high with base width <strong>of</strong><br />
6 m. These structures are proposed <strong>of</strong> masonry type with colcrete.<br />
6.4 DIVERSION DAM<br />
6.4.1 The type <strong>of</strong> dam to be adopted i.e Earth dam or concrete dam is governed by<br />
the topographical, geotechnical and availability <strong>of</strong> construction materials<br />
considerations. The requisite construction materials for Earth dam alternative<br />
are not expected to be available in the vicinity <strong>of</strong> project area and also not<br />
possible for the narrow gorge. In view <strong>of</strong> the rock exposures along steep<br />
valley on both the banks <strong>of</strong> the river and shallow thickness <strong>of</strong> overburden in<br />
the river bed are anticipated. Accordingly a concrete gravity structure with a<br />
spillway in the deep gorge portion is proposed at this site. Concrete dam, 34<br />
m high above the deepest river bed (El 2610.0 m) 88.0 m long comprises <strong>of</strong> 5<br />
blocks. Three overflow blocks in the deep gorge portion are provided to pass<br />
the floods. A foundation gallery running all along the abutment is also<br />
proposed from drainage, grouting and maintenance considerations. A<br />
downstream slope <strong>of</strong> 0.8:1 is proposed for the dam section keeping in view<br />
the seismicity <strong>of</strong> the area (zone V, as per BIS 1893)<br />
6-3
6.4.2 Reservoir<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Keeping in view the storage characteristics <strong>of</strong> the valley upstream, the crest <strong>of</strong><br />
spillway is proposed at El 2617.5 m. The crest <strong>of</strong> power intake is kept 10.5 m<br />
lower then the MDDL <strong>of</strong> El 2630.0 m. This is to ensure minimum water<br />
cushion requirements above the intake tunnels from air entrainment<br />
considerations. Storage to meet the diurnal peaking requirements has been<br />
provided between MDDL and FRL as it is a Run-<strong>of</strong>f the River type<br />
development. Accordingly, MDDL and FRL are proposed at El 2630.0, and El<br />
2642.0 m respectively which provide live storage <strong>of</strong> around 0.853 M cum.<br />
6.4.3 Spillway & Energy Dissipation<br />
An ogee spillway with radial gates and breast wall is proposed to pass the<br />
design flood <strong>of</strong> 8495.0 cumecs corresponding to probable maximum flood.<br />
Three bays, each <strong>of</strong> clear opening <strong>of</strong> size 13.0 m x 17.5 m (height) are<br />
proposed to cater design flood discharge. Radial gates will be operated by<br />
means <strong>of</strong> hydraulic hoists. Provision <strong>of</strong> stoplog gates with gantry crane is also<br />
made.<br />
Since this project is located in the high altitude area (about El 2650 m above<br />
MSL), and most <strong>of</strong> the time the reservoir water surface will be under sub-zero<br />
temperature. To generate power for maximum period and for smooth running<br />
<strong>of</strong> the power plant, deicing arrangement are proposed to be provided.<br />
Energy dissipation is proposed through a trajectory type bucket as tail water<br />
depth fall short <strong>of</strong> post jump depth requirements during high discharges.<br />
Trajectory bucket with tip angle <strong>of</strong> 35 o would through the jet <strong>of</strong> water through<br />
the air and into the plunge pool. Protection works in the form <strong>of</strong> concrete<br />
6-4
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
apron is also provided immediately downstream <strong>of</strong> bucket from considerations<br />
<strong>of</strong> scour.<br />
The Layout details <strong>of</strong> Dam and Spillway are shown in Drg<br />
No.WAP/PFR/BHAIRON GHATI/1003 (R1) &1004 (R1).<br />
6.5 INTAKE AND DESILTING CHAMBER<br />
6.5.1 One intake structure is proposed on the left bank <strong>of</strong> the river upstream <strong>of</strong><br />
the Diversion structure with its invert at El 2619.5 m i.e. 2.0 m above the<br />
spillway crest level to avoid entry <strong>of</strong> rolling debris into the water conductor<br />
system during floods. The intake tunnel <strong>of</strong> 5.0 m dia (D-shaped) is proposed<br />
on the left bank to carry design discharge <strong>of</strong> 80.0 cumec (including 20%<br />
flushing discharge). A trashrack is proposed at the entry so that debris<br />
/particles exceeding 75 mm do not enter the water conductor system.<br />
6.5.2 One underground desilting chamber is provided about 100 metre<br />
downstream <strong>of</strong> intake structure to remove particles <strong>of</strong> size 0.2 mm and above<br />
to protect the turbine parts against erosion. The chamber proposed is <strong>of</strong> size<br />
230 m x 12 m x 17 m (depth) and is designed to achieve 90% efficiency for<br />
silt removal. The chamber is designed to pass design discharge <strong>of</strong> 80<br />
cumecs and is provided with a gate on downstream end to isolate for routine<br />
maintenance. The bed <strong>of</strong> the trough is provided with a longitudinal duct <strong>of</strong> 2.0<br />
m dia to remove the silt laden water through a silt flushing tunnel to the river<br />
downstream. The details <strong>of</strong> intake and desilting chambers are shown in<br />
drawing no. WAP/PFR/BHAIRON GHATI/1005/R1.<br />
6-5
6.6 HEADRACE TUNNEL<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
6.6.1 The design discharge <strong>of</strong> 66.40 cumec is carried downstream <strong>of</strong> desilting<br />
chamber through 4.5 m dia horse shoe shaped headrace tunnel, 5.1 km<br />
long to meet the surge shaft. The alignment <strong>of</strong> the tunnel has been optimally<br />
fixed to provide adequate rock cover below the nallah crossings.<br />
6.6.2 The excavated tunnel section is proposed to be provided with suitable support<br />
system depending upon the type <strong>of</strong> rock strata met. Accordingly, the entire<br />
tunnel reach has been tentatively divided into 4 categories depending upon<br />
the type <strong>of</strong> rock i.e. Good, Fair, Poor and Very Poor. It is presumed that 20%<br />
<strong>of</strong> the tunnel reach encounters poor/very poor rock conditions while in<br />
remaining reach Good/Fair rock conditions are met. A 300 mm thick PCC<br />
lining <strong>of</strong> M20 grade concrete is proposed for the headrace tunnel. Provision<br />
for contact grouting & consolidation grouting has also been made.<br />
The details <strong>of</strong> the Rock support system are shown in Drg. No<br />
WAP/PFR/BHAIRON GHATI/1006/R1.<br />
6.7 SURGE SHAFT & PRESSURE SHAFT<br />
6.7.1 An 10.0 m dia and 80.0 m high orifice type Surge Shaft is proposed at the end<br />
<strong>of</strong> headrace tunnel to release the effect <strong>of</strong> mass oscillations in the tunnel and<br />
to provide immediate storage requirement near the power house in case <strong>of</strong><br />
sudden acceptance <strong>of</strong> load. The bottom elevation <strong>of</strong> Surge Shaft has been so<br />
fixed as to provide adequate water cushion below the minimum down surge<br />
level. Similarly, it is ensured that maximum upsurge level is contained within<br />
the Surge Shaft.<br />
6-6
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The Surge Shaft is likely to be excavated in tourmaline granite rock<br />
formations. It is proposed to provide 75 mm thick shotcrete with 4m long rock<br />
bolt at suitable intervals. Reinforced concrete lining (M25 grade) 1.0m thick<br />
is proposed in the deeper reaches & reducing to 0.6 m thickness in the upper<br />
portion. Provision for consolidation grouting & contact grouting is also made<br />
to ensure proper consolidation <strong>of</strong> rockmass around the surge shaft.<br />
6.7.2 A vertical pressures shaft <strong>of</strong> size 3.75 m diameter is proposed downstream <strong>of</strong><br />
Surge Shaft keeping in view the adequacy <strong>of</strong> horizontal and vertical rock<br />
cover as per codal requirement. Pressure shaft drops from El 2590.0 m to El<br />
2509.5 m in line with the center line <strong>of</strong> distributor. The horizontal portion <strong>of</strong><br />
pressure shaft is bifurcated into 2 feeders each <strong>of</strong> 3.0 m dia to feed to 2 units<br />
<strong>of</strong> 32.5 MW each.<br />
The pressure shaft liner is designed taking into account 30% rock participation<br />
and 40% as water hammer head. Mild steel is proposed for liner so as to<br />
restrict the liner thickness to reasonable limits to obviate the need for stress<br />
relieving. Liner thickness varies from 12 mm to 28 mm in the pressure shaft<br />
reach. The water velocity in the pressure shaft is approximately 6.0m/sec.<br />
6.8 POWER HOUSE<br />
The underground power house is proposed as the river banks are steep and<br />
there is paucity <strong>of</strong> space for surface power house. The underground power<br />
house complex comprises <strong>of</strong> one cavern <strong>of</strong> 21.5 m width. The machine hall is<br />
15.5 m wide, it house 2 units <strong>of</strong> 32.5 MW each along with 20 m long service<br />
bay. The generator floor level is kept at EL 2514.5 Centre line <strong>of</strong> units is at EL<br />
2509.5 m and invert level <strong>of</strong> draft tubes kept at EL 2504.5 m. EOT crane <strong>of</strong><br />
130/25 tonnes capacity shall be provided at crane beam level at EL 2522.5 m<br />
and travel up to service bay end also. The two main inlet valves, one for each<br />
6-7
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
unit, is also provided. The transformer bay is 6 m wide inside the main power<br />
house cavern to accommodate transformer and GIS. A cable carriage is<br />
provided from this cavern to the outdoor switchyard at the ro<strong>of</strong> level. The<br />
draft tubes shall be by a draft tube gate fitted with gantry crane installed in<br />
the transformer cavern. The TRT <strong>of</strong> 5.0m dia (D-shaped) and 190m long shall<br />
have reverse slope to meet the river bed level. The power house cavern as<br />
well as the transformer bay shall be approached by an access tunnel starting<br />
from the main road.<br />
6.9 ELECTRO - MECHANICAL WORKS<br />
6.9.1 General<br />
The proposed 65 MW Bhairon Ghati Hydro-Electric Project would have<br />
underground type power house. The installed capacity would be provided by<br />
2 nos. Vertical Axis Francis turbine driven generating units <strong>of</strong> 32.5 MW each.<br />
It is proposed to provide Inlet Valve <strong>of</strong> Butterfly type for each turbine, which<br />
would be accommodated in the powerhouse cavern.<br />
The generation voltage <strong>of</strong> 11 kV would be stepped up to 220 kV through a<br />
three phase 38 MVA, 11/220 kV ODWF type unit step up transformers for<br />
each unit located in power house cavern. The 11 kV isolated phase bus ducts<br />
would connect the 11 kV generator terminals with 11 kV bushings <strong>of</strong> step up<br />
transformers. The 220 kV terminal <strong>of</strong> the transformers would be connected<br />
with 220 kV Gas Insulated Switchgear (GIS) located on the floor above the<br />
transformers in powerhouse cavern.<br />
The layout <strong>of</strong> generating equipments, unit step up transformers, switchyard<br />
etc. are indicated in the drawings no. WAP/PFR/BHAIRON GHATI/1007(R1)<br />
&1008(R2).<br />
6-8
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The GIS would accommodate 6 bays, 2 for generator incomings, 2 for<br />
outgoing 220 kV transmission lines, one for step down transformer and one<br />
for bus-coupler. The power generated would thus be evacuated through 2<br />
nos. 220 kV transmission lines. The single line diagram is shown in drawing<br />
no. WAP/PFR/BHAIRON GHATI/1009(R1).<br />
6.9.2. Brief Particulars <strong>of</strong> Equipments<br />
a) Turbine and Governor<br />
The upstream levels, tailrace levels and heads available for power generation<br />
are indicated below:<br />
i) Upstream Levels<br />
• FRL EL 2642.0 M<br />
• MDDL EL 2630.0 M<br />
ii) Tailrace Levels<br />
• Maximum EL 2515.0 M<br />
• Minimum EL 2513.0 M<br />
• Average EL 2514.0 M<br />
iii) Heads<br />
• Maximum net head 113.90 M<br />
• Minimum net head 99.90 M<br />
• Rated head 108.90 M<br />
Francis type turbine is considered appropriate choice considering the capacity<br />
<strong>of</strong> the generating units and head available for power generation. The turbine<br />
6-9
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
would be suitably rated to provide 32.5 MW at generator terminals at rated<br />
head <strong>of</strong> 108.90 M. The speed <strong>of</strong> turbine has been determined as 300 RPM.<br />
The center line <strong>of</strong> turbine runner has been set at EL 2509.5 M, 3.5 m below<br />
the minimum TWL which is at EL 2513 M. The governor would be electrohydraulic<br />
digital PID type suitable for fully automatic control. The closing time<br />
<strong>of</strong> wicket gates would be so adjusted so as not to increase the speed rise and<br />
pressure rise more than 45% and 30% respectively under full load throw <strong>of</strong>f<br />
condition.<br />
b) Main Inlet Valve<br />
It is proposed to provide an Inlet Valve <strong>of</strong> the Butterfly type for each turbine as<br />
second line <strong>of</strong> defence in stopping the water flow to the turbine when due to<br />
governor malfunctioning, the generating units may tend to go to runaway<br />
speed. During the time when the generating unit is under stand still condition,<br />
it would help in minimizing the water leakage through the wicket gates <strong>of</strong> the<br />
turbine. The opening <strong>of</strong> the valve would be achieved through pressurized oil<br />
servomotor and closing through counter weight.<br />
c) Generator and Excitation System<br />
The generator shaft would be directly coupled with the turbine shaft. The<br />
bearing arrangement would be semi-umbrella type with combined thrust and<br />
guide bearings below the rotor and one guide bearing above the rotor. The<br />
generator would be <strong>of</strong> the closed air circuit water-cooled type. The main<br />
parameters <strong>of</strong> the generator would be as indicated below:<br />
i) Rated out put - 32.5 MW<br />
ii) <strong>Power</strong> factor - 0.9 lag<br />
iii) Speed - 300 RPM<br />
iv) Class <strong>of</strong> Insulation <strong>of</strong><br />
stator and rotor winding - Class 'F'<br />
v) Generation Voltage - 11 kV<br />
6-10
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The generators would be provided with static excitation equipment and<br />
voltage regulator. Necessary power for excitation would be provided by<br />
tapping the generator terminals.<br />
d) Unit Step-up Transformer<br />
Three phase 38 MVA, 11/ 220 kV transformers, would be provided for each<br />
generating unit. These transformers would be located in the powerhouse<br />
cavern. The 11 kV bushings <strong>of</strong> the transformer would be connected with 11<br />
kV terminals <strong>of</strong> generator through 11 kV bus ducts. The 220 kV bushings<br />
would be connected with 220 kV Gas Insulated Switchgear located on the<br />
floor above the transformers<br />
e) EOT Crane<br />
The heaviest equipment which the powerhouse crane is required to handle<br />
during erection and subsequently during maintenance is the generator rotor.<br />
The weight <strong>of</strong> the generator rotor has been estimated to be about 112 tonnes.<br />
It is proposed to provide one EOT crane <strong>of</strong> 130/ 25 tonnes capacity.<br />
6.10 AUXILIARY EQUIPMENT AND SYSTEMS FOR THE POWER HOUSE<br />
Following equipments for the auxiliary systems <strong>of</strong> the powerhouse would be<br />
provided:<br />
i) Cooling water system for turbines, generators, unit step up<br />
transformers etc.<br />
ii) Drainage System<br />
iii) Dewatering system<br />
iv) High pressure compressed air equipment for governor and MIV etc.<br />
v) Low pressure compressed air equipment for station services<br />
6-11
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
vi) 415 V LTAC supply system comprising station service transformers,<br />
unit auxiliary transformer, station service board, unit auxiliary boards<br />
etc.<br />
vii) D.C. supply system comprising 220V DC battery, chargers, DC<br />
distribution boards etc.<br />
viii) Ventilation system for the power house<br />
ix) Air conditioning system for control room, conference room etc.<br />
x) Illumination system<br />
xi) Earthing system<br />
xii) Oil handling system<br />
xiii) <strong>Power</strong> and control cables<br />
xiv) Fire protection system<br />
6.11 220 KV SWITCHYARD<br />
It is proposed to provide 220 kV, Gas Insulated Switchgear, having 6 bays; 2<br />
bays for generator incoming, 2 bays for 220 kV transmission lines, 1 bay for<br />
step down transformer and 1 bay for bus-coupler. The double busbar<br />
arrangement has been proposed which would provide flexibility and reliability<br />
in the operation <strong>of</strong> the plant.<br />
6.12 OBSERVATIONS OF CEA & CWC<br />
The Draft Report <strong>of</strong> this project was submitted to CEA for perusal during<br />
October 03. The observations from the various directorates <strong>of</strong> CWC and CEA<br />
on the civil and electrical aspects have been considered and taken care in this<br />
report. The detailing has been kept to the possible extent as the report<br />
pertains to the preliminary feasibility stage studies.<br />
6-12
7.1 GENERAL<br />
CHAPTER - VII<br />
POWER POTENTIAL STUDIES<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The power potential studies have been carried out for Bhairon Ghati Hydel<br />
Scheme. The projected power supply position for 11 th Plan also indicated<br />
that there would be shortage <strong>of</strong> peak power in Uttranchal State as well as<br />
in Northern region. The execution <strong>of</strong> this project would help in reducing<br />
the gap between supply and demand <strong>of</strong> power.<br />
This is a Run <strong>of</strong> river type development with diurnal storage for peaking<br />
purpose and would utilize a rated head <strong>of</strong> water <strong>of</strong> 108.9 M. The<br />
powerhouse would be <strong>of</strong> Under ground type.<br />
7.2 FIXATION OF FRL/MDDL<br />
The FRL <strong>of</strong> the pondage has been fixed at EL 2642.0 m so as to get<br />
adequate storage capacity for peaking operation <strong>of</strong> the plant during lean<br />
period. The MDDL <strong>of</strong> EL 2630.0 m has been fixed keeping the requirement<br />
<strong>of</strong> minimum cushion <strong>of</strong> water above the headrace tunnel (HRT) to rule out<br />
the air entrainment into the HRT. The storage at FRL is computed as<br />
1.883 million cubic metres whereas the storage at MDDL is estimated as<br />
1.03 million cubic metres, thus making available live storage <strong>of</strong> 0.853<br />
million cubic metres The levels v/s capacity characteristics <strong>of</strong> the pondage<br />
are indicated in Annex 7.1.<br />
7-1
7.3 FIXATION OF TAIL RACE WATER LEVEL (TWL)<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The minimum tail water level which corresponds to discharge <strong>of</strong> one<br />
generating unit at 10% load has been determined as EL 2513 m. The<br />
Maximum TWL at EL 2515 m corresponds to the discharge <strong>of</strong> all the<br />
generating units running at full load.<br />
These levels however would need to be verified when it would be possible<br />
to prepare tail rating curve.<br />
7.4 WATER AVAILABILITY<br />
The available data <strong>of</strong> water flows on 10 daily basis has been analysed in<br />
Chapter No. 5 on “hydrology”. Water flows determined in 90% dependable<br />
year and in 50% dependable year, have been utilized for computing power<br />
benefits.<br />
7.5 TYPE OF TURBINE<br />
The specific speed <strong>of</strong> the Turbine for rated head 108.9 m works out to be<br />
174.87 which leads to the choice <strong>of</strong> Francis Turbine to be used for this<br />
station. The following efficiencies applicable for Francis turbine driven<br />
generating unit have been considered for power potential studies.<br />
- Efficiency <strong>of</strong> Turbine 93.5%<br />
- Efficiency <strong>of</strong> Generator 98.0%<br />
- Combined efficiency <strong>of</strong><br />
Turbine & Generator<br />
91.63%<br />
7-2
7.6 INSTALLED CAPACITY<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
7.6.1 The power potential with different installed capacity from 30 MW to 80 MW<br />
and 90% dependable year is indicated in Annex-7.2. The simulation<br />
studies have been carried out with FRL at EL 2642 m, MDDL at EL 2630<br />
m, losses in water conductor system as 15.1 m and average TWL at EL<br />
2514 m. The study indicates that the firm power is 11.13 MW continuous.<br />
Considering four hours peaking, the installed capacity required would be<br />
about 66.78 MW.<br />
7.6.2 For optimization <strong>of</strong> Installed Capacity, annual energy generation (KWh),<br />
Incremental Energy generation d (KWh), and ratio <strong>of</strong> Incremental energy<br />
and Incremental Installed Capacity d(KWh)/ d (kW) have been computed<br />
for 90% dependable year for installed capacity varying from 30 MW to 80<br />
MW in steps <strong>of</strong> 5 MW. The results are indicated in Annex-7.3. It would be<br />
seen there from that d (Kwh)/ d (kW) drops steeply for increase in installed<br />
capacity from 65 MW to 70 MW. The installed capacity could be therefore<br />
be 65 MW.<br />
7.6.3 Keeping in view the system requirements and analysis <strong>of</strong> Incremental<br />
energy and Incremental installed capacity; the installed capacity <strong>of</strong> 65 MW<br />
is considered optimum. With installation <strong>of</strong> 65 MW, the load factor <strong>of</strong><br />
operation during lean flow period works out to 17.12 % .<br />
7.6.4 There are two options for number <strong>of</strong> generating units to be installed<br />
1x65 MW<br />
2x32.5 MW<br />
7-3
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Installation <strong>of</strong> one unit <strong>of</strong> 65 MW would be preferable from economic<br />
consideration. Installation <strong>of</strong> two units would provide increased reliability <strong>of</strong><br />
power supply from station and also provide more flexibility for part load<br />
operation. Considering the above in view, it is decided to have installation<br />
<strong>of</strong> the two units <strong>of</strong> 32.5 MW, The turbine would be suitably rated to provide<br />
32.5 MW at generator terminal at rated head <strong>of</strong> 108.90 m. The speed <strong>of</strong><br />
turbine has been determined as 300 RPM.<br />
7.7 RESULTS OF STUDIES<br />
Annual energy generation in 90% dependable year and in 50% dependable<br />
year have been computed for installed capacity <strong>of</strong> 65 MW (2 x 32.5 MW) and<br />
are indicated in Annexures 7.2 and 7.4 respectively. The results are also<br />
briefly indicated below.<br />
Particulars 90% dependable<br />
year<br />
Annual Energy<br />
Generation (Gwh)<br />
50% dependable<br />
year<br />
293.18 365.54<br />
MW continuous 11.13 18.01<br />
Average annual load<br />
factor<br />
Load factor in lean flow<br />
months<br />
51.49 % 64.2 %<br />
17.12 % 27.71 %<br />
The design energy computation have been carried out and indicated in<br />
Annex-7.5. The design energy <strong>of</strong> 279.45 GWh would be considered for<br />
financial evaluation.<br />
7-4
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The live storage <strong>of</strong> 231.94 MWh (0.853 Million cubic meters) is available<br />
whereas the storage required for peaking operation works out to 267.12 MWh.<br />
Thus the storage is available for 3.57 hrs. <strong>of</strong> peaking operation <strong>of</strong> the station.<br />
7.8 CONCLUSIONS<br />
The power potential studies carried out indicates that installed capacity <strong>of</strong> 65<br />
MW comprising 2 generating units <strong>of</strong> 32.5 MW each would be required for this<br />
HEP to derive optimum power benefits. The station would afford generation<br />
<strong>of</strong> 293.18 Million units in a 90% dependable year.<br />
7.9 RECOMMENDATIONS FOR FURTHER STUDIES<br />
7.9.1 At DPR stage, based on the data available <strong>of</strong> topographic survey, tail race<br />
rating curve should be evolved so that in energy computations the head<br />
utilized for power generation is corrected with the change in trail race level<br />
corresponding to discharge. In the present study, tail race level was<br />
considered constant.<br />
7.9.2 The storage at FRL and MDDL should be computed with more accuracy<br />
based on the data <strong>of</strong> topographic survey.<br />
7-5
CHAPTER VIII<br />
POWER EVACUATION<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
8.1 APPRAISAL OF EXISTING POWER EVACUATION FACILITIES<br />
The Project is located at latitude 31-02-30 (D-M-S) North and longitude 78-48-<br />
23 (D-M-S) East. The installed capacity <strong>of</strong> Uttaranchal State is 1286.15 MW as<br />
on March 2003. Its peak demand has been estimated as 771 MW whereas the<br />
met peak is 705 MW in the present scenario. This amounts to deficit <strong>of</strong> 66 MW<br />
(8.56%). Accordingly, energy requirement is 3774 MU against the available<br />
energy <strong>of</strong> about 3670 MU. This depicts deficit <strong>of</strong> 104 MU (2.8%). For the<br />
purpose <strong>of</strong> evacuation <strong>of</strong> power pooling has been proposed for various Hydro<br />
Electric <strong>Power</strong> Projects. As per the geographical locations the following<br />
proposed Hydel Projects lie between the longitude 78.5 o N to 79.5 o N namely<br />
Harsil, Bhairon Ghati, Gangotri, Jadhganga, Karmoli Hydro <strong>Power</strong> Projects.<br />
The next group <strong>of</strong> Hydro Electric Projects which lie between longitude 79.3 o N<br />
to 80 o N are Badrinath, Gohana Tal, Rishiganga II, Rishiganga I, Jelum Tamak,<br />
Deodi, Devasari Dam and Malari Jelum. Whereas in the next series the Hydro<br />
Electric Projects which lie between longitude 80 o to 81 o N are Mapang<br />
Bogudiyar, Sirkari Bhyol Bogudiyar, Sirkari Bhytol Rus Bagar, Khasiya Barah,<br />
Khartoli Lumti Talli, Kalika Dantu, Garba Tawaghat, Sobala Jhimrigaon, Sela<br />
Urthing, Chhanger Chal, Bokang Beiling. The power map <strong>of</strong> Uttranchal as on<br />
1/1/2002 is shown at Annex-8.1.<br />
8.2 PROPOSED EVACUATION SYSTEM TO NEAREST FACILITY<br />
A map has already been prepared indicating various proposed Hydro Electric<br />
Projects for the purpose <strong>of</strong> preparation <strong>of</strong> prefeasibility report (PFR) indicating<br />
their locations which may be seen at Annex-8.2.<br />
8-1
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
8.3 ARRANGEMENT FOR EVACUATION OF POWER FROM BHAIRON GHATI<br />
HEP<br />
The 65 MW power generated at 11 kV at Bhairon Ghati HEP will be stepped<br />
upto 220 kV by unit step-transformers. The power would be taken to nearby<br />
proposed 400/220 kV Chhalmi sub station. Proposed line from Bhairon Ghati<br />
sub-station for evacuation <strong>of</strong> power is shown at Annexure - 8.3.<br />
8.4 ROUTE LENGTH AND COSTING OF 220 KV TRANSMISSION LINE FOR<br />
EVACUATION OF POWER FROM BHAIRON GHATI HEP<br />
The power <strong>of</strong> this project is intended to be evacuated by proposed 220 kV D/C<br />
line to newly proposed 400/220 kV sub-station at Chhalmi. The length <strong>of</strong> this<br />
section <strong>of</strong> line has been estimated as 10 km (220 kV D/C line) from Bhairon<br />
Ghati to Chhalmi including loop out portion <strong>of</strong> line. The cost <strong>of</strong> this line is<br />
estimated as Rs. 7.50 Crores.<br />
8-2
CHAPTER – IX<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
INITIAL ENVIRONMENTAL EXAMINATION STUDIES<br />
9.1. INTRODUCTION<br />
The Initial Environmental Examination <strong>of</strong> Bhairon Ghati hydroelectric project<br />
has following objectives through various phases <strong>of</strong> development which are<br />
proposed to be covered:<br />
• provide information on baseline environmental setting;<br />
• preliminary assessment <strong>of</strong> impacts likely to accrue during construction<br />
and operation phases;<br />
• identify key issues which need to be studied in detail during<br />
subsequent environmental studies<br />
It is essential to ascertain the baseline status <strong>of</strong> relevant environmental<br />
parameters that could undergo significant changes as a result <strong>of</strong> construction<br />
and operation <strong>of</strong> the project. In an Initial Environmental Examination (IEE)<br />
study, baseline status is ascertained through review <strong>of</strong> secondary data,<br />
reconnaissance survey and interaction with the locals.<br />
The Preliminary Impact Assessment conducted as a part <strong>of</strong> IEE Study, is<br />
essentially a process to forecast the future environmental scenario <strong>of</strong> the<br />
project area that might be expected to occur as a result <strong>of</strong> construction and<br />
operation <strong>of</strong> the proposed project. The key environmental impacts which are<br />
likely to accrue as a result <strong>of</strong> the proposed developmental activity are<br />
identified. Various impacts, which can endanger the environmental<br />
sustainability <strong>of</strong> a project, are highlighted for comprehensive assessment as a<br />
part <strong>of</strong> next level <strong>of</strong> environmental study during detailed studies.<br />
9-1
9.2 ENVIRONMENTAL BASELINE SETTING<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The study area covered includes the area within 7 km radius <strong>of</strong> various project<br />
appurtenances. The data was collected through review <strong>of</strong> existing documents<br />
and various engineering reports and reconnaissance surveys.<br />
The various parameters for which baseline setting has been described have<br />
been classified into physio-chemical, ecological and socio-economic aspects.<br />
9.2.1 Physio-Chemical Aspects<br />
a) Water Quality<br />
The Bhairon Ghati hydroelectric project site, lies on river Bhagirathi just below<br />
its confluence with river Jadhganga. The catchment area <strong>of</strong> river Bhagirathi<br />
intercepted at the proposed project site includes the entire catchment <strong>of</strong> river<br />
Jadhganga as well. As per Revenue records, there are only two revenue<br />
villages in the catchment area <strong>of</strong> river Jadhganga. These villages are Jadung<br />
and Nelang. The village Jadung has been classified as uninhabited and<br />
village Nelang has only two residents. As per revenue records, there is only<br />
one village, i.e. Gangotri in the catchment <strong>of</strong> river Bhagirathi intercepted at the<br />
intake site. The present population <strong>of</strong> village Gangotri is <strong>of</strong> the order <strong>of</strong> 160.<br />
Thus, pollution load from domestic sources in the project catchment is<br />
insignificant. Likewise considering the topography and terrain conditions, the<br />
area has no industries as well. Thus, pollution from various sources is virtually<br />
absent in the catchment intercepted at the diversion structure site. The<br />
pristine, relatively undisturbed environment coupled with low temperature<br />
conditions, ensure that the water quality is excellent, with D.O. levels virtually<br />
upto saturation conditions. The TDS levels are well within the permissible<br />
9-2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
limit. As a result, the concentration <strong>of</strong> various cations and anions too are well<br />
within the permissible limits.<br />
b) Landuse<br />
Various project features were superimposed on the satellite data, and the<br />
landuse pattern <strong>of</strong> the submergence area was ascertained and the same is<br />
given in Table-9.1.The land use pattern <strong>of</strong> the submergence area is appended<br />
as Figuirre-9.1 The satellite imagery (IRS 1D, LISS-III + PAN) <strong>of</strong> the study<br />
area is given as Figure-9.2.<br />
Table-9.1<br />
Landuse pattern <strong>of</strong> the submergence area<br />
_______________________________________________________________<br />
S.No. Landuse / Land cover Area (ha)<br />
_______________________________________________________________<br />
1. Forest area with dense vegetation 7.01<br />
2. Forest area with medium vegetation 1.35<br />
3. Scrub land 0.55<br />
4. Water bodies 4.10<br />
5. Rocky outcrop 0.26<br />
______________________________________________________________<br />
Total 13.27<br />
_______________________________________________________________<br />
The submergence area (considering FRL as 2642 m) is 13.27 ha. The major<br />
land cover category in the submergence area is Forest area (8.36 ha) which<br />
includes area with dense vegetation (7.01 ha) and medium vegetation (1.35<br />
ha). The other major landuse category is water bodies (4.10 ha). About 0.55<br />
ha <strong>of</strong> land in the submergence area is scrub land. As a part <strong>of</strong> next phase <strong>of</strong><br />
Environmental study, it is recommended that detailed studies be conducted to<br />
ascertain the ownership status <strong>of</strong> these lands, i.e. whether the land belongs<br />
Forest Department or is it a non-forest government land. The scrub land<br />
could still be categorized as forest land, as far as ownership status is<br />
9-3
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
concerned. In such a scenario, compensatory afforestation as per the norms<br />
<strong>of</strong> Forest Conservation Act (1980) will have to be done in lieu <strong>of</strong> entire forest<br />
land ass per ownership, irrespective <strong>of</strong> its vegetal status to be acquired for the<br />
project.<br />
9.2.2 Ecological Aspects<br />
a) Vegetation<br />
The proposed project site lies in the western Himalayas. The nature and type<br />
<strong>of</strong> vegetation occurring in an area depends upon a combination <strong>of</strong> various<br />
factors including prevailing climatic conditions altitude, topography, slope,<br />
biotic factors, etc.<br />
The proposed project area lies between EL 2,500 m and EL 2,700 m and the<br />
vegetation in the area can be broadly categorised as cool temperate forests.<br />
Amongst the various forest types under temperate forests, Western mixed<br />
coniferous forest is commonly observed in the project area and its<br />
surroundings. Major tree species observed in the area are Morinda (Abies<br />
pindrow) and Rai (Picea smithiana). At many locations, Deodar (Cedrus<br />
deodara) is also observed alongwith Morinda. At higher altitudes, within the<br />
study area, Rai, Morinda and Banj are observed.<br />
Considering FRL as 2642.0 m, the submergence area, works out to 13.27 ha,<br />
<strong>of</strong> which 8.36 ha is the forest area. The submergence on the right bank lies in<br />
Gangotri Reserved Forest and Patangani Reserved Forest. Likewise,<br />
submergence on the left bank side, land belongs to Patangani Reserved<br />
Forest Land.<br />
9-4
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Within the study area, for a stretch <strong>of</strong> 2-3 km on either side <strong>of</strong> river Bhagirathi<br />
dense mixed forest is observed. In different stretches, species such as pine,<br />
deodar are dominant. Beyond a distance <strong>of</strong> 2-3 km on either side <strong>of</strong> river<br />
Bhagirathi, barren lands with no major vegetal species are observed.<br />
The major floral species observed in the study area is given in Table-9.2.<br />
b) Fauna<br />
Table-9.2<br />
Major floral species observed in the study area<br />
Local Name<br />
Trees<br />
Scientific Name<br />
Spruce Picea smithiana<br />
Fir/Morinda Abies pindrow<br />
Pine Pinus roxburghii<br />
Deodar Cedrus deodara<br />
Padam Prunus cornuta<br />
Bhojpatra Betula utilis<br />
Banj<br />
Shrubs<br />
Quercus leucotriphora<br />
Aatas Aconitum heterophyllum<br />
Archa Rheum webbianun<br />
Titphada Sarccoces saligna<br />
Gugal Juniperus srumata<br />
Chiraita Swertia chirayita<br />
Hisar Rubius niveus<br />
The forest in and around the project area especially along the right bank is<br />
quite dense. A part <strong>of</strong> Gangotri and Patangani Reserve Forest is coming<br />
under reservoir submergence. The population density is quite low in the area,<br />
9-5
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
as a result <strong>of</strong> which, human interference are minimal. Thus, project and its<br />
adjacent area have good wildlife. Based on the review <strong>of</strong> secondary data and<br />
interaction with the Forest Department, major faunal species observed in the<br />
project area and the study area include Musk Deer, Tiger, Jackal, Jungle Cat,<br />
Wild Goat, Monkey, Brown bear, etc. Amongst the reptiles, lizard was the<br />
dominant species. The commonly observed bird species observed in the<br />
project area and its surroundings include vulture, dove, blue rock piegon,<br />
pheasant, etc.<br />
The list <strong>of</strong> faunal species observed in the study area including project area is<br />
outlined in Table-9.3.<br />
It can be observed, that many <strong>of</strong> the faunal species belong to Schedule-I &<br />
Schedule II category. As per Wildlife Protection Act (1972), such species are<br />
akin to rare and endangered species and need to be conserved and<br />
preserved. Thus, it is essential to ascertain adverse impacts on such species<br />
due to the proposed project.<br />
Table-9.3<br />
List <strong>of</strong> faunal species observed in the study area<br />
including project area<br />
Common Name Zoological Name Schedule as per<br />
Wildlife<br />
Protection Act<br />
Mammals<br />
Musk Deer Moschus moschiferus Schedule – I<br />
Jackal Canis aureus<br />
Rhesus Monkey Macaca mulatta Schedule II<br />
Wild goat Pseudois nayaur Schedule I<br />
Brown Bear Ursus arctos Schedule I<br />
Tiger Panthera tigris Schedule I<br />
9-6
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Common Name Zoological Name Schedule as per<br />
Wildlife<br />
Protection Act<br />
Python Python sp. Schedule-I<br />
Wild dog<br />
Avi-fauna<br />
Cuon alpinus -<br />
Vulture Gyps fulvus<br />
Indian Ringed dove Streptopelia decoacto<br />
Rufous Turtle dove Streptopelis orientalis<br />
Blue rock piegon Columba livia<br />
Monal Lopophorus imnejanus<br />
Pheasant<br />
Reptiles<br />
Catreus wallichii<br />
Lizard Hemidactyles brooki<br />
a) Fisheries<br />
The major water body in the project area are rivers Bhagirathi and<br />
Jadhganga. Since these are perennial rivers, it is expected that there could<br />
be quite a few species in these rivers. Based on the review <strong>of</strong> existing<br />
literature and secondary data, it can be said that fish species such as Black<br />
fish, Brown trout could be present in these rivers. Mahaseer, a migratory fish<br />
species could also be present. Generally in fast flowing mountainous streams,<br />
fish species show definite behaviour, which includes reaction to fast current<br />
and seeking <strong>of</strong> shelter in the almost stagnant water behind rocks and<br />
boulders. Even good swimmers like Mahaseer seek shelter for most <strong>of</strong> the<br />
time. Majority <strong>of</strong> the fishers in such streams spend most <strong>of</strong> their life facing the<br />
current. This helps them in two ways, viz. to maintain their upright position<br />
and to make respiration easier.<br />
9-7
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
It is recommended that a detailed fisheries survey be conducted in the river as<br />
a part <strong>of</strong> EIA study to ascertain the spatio-temporal occurrence <strong>of</strong> Mahaseer.<br />
Tank or pond fisheries is absent in the project area or study area.<br />
9.2.3 Socio-economic Aspects<br />
S.<br />
No.<br />
It is imperative to study socio-economic characteristics including demographic<br />
pr<strong>of</strong>ile <strong>of</strong> the project area and the study area. The proposed project lies in<br />
tehsil Bhatwari <strong>of</strong> district Uttarkashi. The submergence area is not expected to<br />
affect private land or homesteads. The entire study area, too lies within tehsil<br />
Bhatwari <strong>of</strong> district Uttarkashi. Only three villages are observed within the<br />
study. The demographic pr<strong>of</strong>ile <strong>of</strong> these study area villages is given in Table<br />
9.4.<br />
Table-9.4<br />
Demographic pr<strong>of</strong>ile <strong>of</strong> the study area villages<br />
Village No. <strong>of</strong><br />
households<br />
Population SC ST Literates<br />
Male Female Total<br />
Male Female<br />
1. Gangotri 51 117 6 123 8 1 117 4<br />
2 Mukhaba 190 593 635 958 130 76 475 116<br />
3. Dharali 95 271 246 517 65 - 182 23<br />
Total 336 981 617 1598 203 77 674 143<br />
Source : District Census Handbook<br />
The average family size in the study area villages is about 4.8, with a total<br />
population <strong>of</strong> 1598. The sex ratio, i.e. number <strong>of</strong> females per 1000 males is<br />
629. The SC population accounts for 12.7% <strong>of</strong> the total population. The ST<br />
population is quite low in the area (4.8%). The literacy rate in the study area<br />
is quite high (51.1%) compared to other villages in the area. The male literacy<br />
rate is quite high (67.7%). However, female literacy rate is quite low (23.2%).<br />
9-8
9.3 PREDICTION OF IMPACTS<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Based on the project details and the baseline environmental status, potential<br />
impacts as a result <strong>of</strong> the construction and operation <strong>of</strong> the proposed project<br />
have been identified. As a part <strong>of</strong> IEE study, impacts on various aspects listed<br />
as below have been assessed:<br />
- Land environment<br />
- Water resources<br />
- Water quality<br />
- Terrestrial flora<br />
- Terrestrial fanna<br />
- Aquatic ecology<br />
- Noise environment<br />
- Ambient air quality<br />
- Socio-economic environment<br />
9.3.1 Impacts on Land Environment<br />
a) Construction phase<br />
Quarrying operations<br />
A hydroelectric project requires significant amount <strong>of</strong> construction material,<br />
which needs to be extracted from various quarry sites in and around the<br />
project area. To the extent possible, existing quarries need to be tapped.<br />
Normally quarrying is done along the hill face, and generally left untreated<br />
after extraction <strong>of</strong> the required construction material. These sites can become<br />
permanent scar on the hill face and can become potential source <strong>of</strong><br />
landslides. This aspect needs to be covered as a part <strong>of</strong> the EIA study and<br />
suitable measures for stabilization <strong>of</strong> quarry sites need to be recommended. It<br />
9-9
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
is recommended that the quarry sites be located in non-forest land, so that<br />
adverse impacts on flora & fauna are ameliorated to the extent possible.<br />
Operation <strong>of</strong> construction equipment<br />
During construction phase, various equipment will be brought to the site.<br />
These include crushers, batching plant, drillers, earth movers, rock bolters,<br />
etc. The siting <strong>of</strong> these construction equipment would require significant<br />
amount <strong>of</strong> space. Similarly, space will be required for workshop, storing <strong>of</strong><br />
other construction equipment and materials, etc. In addition, land will also be<br />
temporarily acquired, for storage <strong>of</strong> the quarried material before crushing,<br />
rubble, sand crushed material, cement, spare parts yard, fuel storage, guard<br />
room, parking <strong>of</strong> light and heavy vehicles, petrol & diesel pumps, temporary &<br />
permanent residential colonies for government and contractor’s labour, water<br />
supply and switch yard for construction purposes, etc. Various storage sites<br />
need to be earmarked for this purpose. It is recommended that to the extent<br />
possible, such sites are located over non-forest land.<br />
Problems <strong>of</strong> muck disposal<br />
A large quantity <strong>of</strong> muck is expected to be generated as a result <strong>of</strong> tunneling<br />
operations, construction <strong>of</strong> access roads, etc. The muck so generated needs<br />
to be properly disposed otherwise it can lead to significant adverse impacts on<br />
environment. Normally muck is disposed along the river bank which ultimately<br />
finds it way into the water body, leading to adverse impacts on riverine<br />
ecology.<br />
It is proposed that muck be disposed over low lying areas, with minimum<br />
vegetal cover and preferably over non-forest land. Muck has low nutrients,<br />
hence, natural vegetal growth is unlikely at muck disposal sites, as a result <strong>of</strong><br />
9-10
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
which specific bio-engineering measures need to be implemented. Specific<br />
site-specific management measures can be suggested as a part <strong>of</strong> EIA study.<br />
Construction <strong>of</strong> roads<br />
The topography <strong>of</strong> the project area has steep to precipitous slopes which<br />
descends rapidly into narrow valleys. Significant vehicular movement for<br />
transportation <strong>of</strong> large construction material, heavy construction equipment is<br />
anticipated during construction phase. Most <strong>of</strong> the roads in the project area,<br />
would require widening. Many new roads also would have to be constructed.<br />
Construction <strong>of</strong> new roads may lead to removal <strong>of</strong> trees on slopes and reworking<br />
<strong>of</strong> the slopes in the immediate vicinity <strong>of</strong> road, which may lead to<br />
landslides, soil erosion, gully formation, etc. Adequate management<br />
measures need to be implemented to ameliorate such impacts.<br />
b) Operation Phase<br />
The area coming under reservoir submergence is 13.27 ha (considering FRL<br />
as 2642 m). The submergence area lies in Reserve Forest area. In addition to<br />
above, an area <strong>of</strong> 50-55 ha will be required for siting <strong>of</strong> various project<br />
appurtenances, infrastructure, etc. It is recommended that to the extent<br />
possible, such sites be located over non-forest land. The ownership category<br />
<strong>of</strong> land required for various project appurtenances can be ascertained, once<br />
project layout is finalized as a part <strong>of</strong> DPR preparation.<br />
9.3.2 Impacts on Water Resources<br />
The construction <strong>of</strong> dam as a part <strong>of</strong> the proposed project diversion <strong>of</strong><br />
discharge for hydropower generation would lead to reduction in flow for a river<br />
stretch <strong>of</strong> about 6.5 km downstream <strong>of</strong> the dam site up to the confluence point<br />
9-11
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
<strong>of</strong> tail race discharge. Since there are no users in the intervening stretch,<br />
hence, reduction in flow during lean season is unlikely to lead to any<br />
significant impact. However, reduction in flow is likely to have a minor impact<br />
on riverine ecology as the discharge during lean flow is significantly less, but<br />
intervening nallahs and streams do supplement the minimum flow in the<br />
stretch under study.<br />
9.3.3 Impacts on Water Quality<br />
a) Construction phase<br />
The project construction is likely to last for a period <strong>of</strong> 4-5 years apart from<br />
investigation stage. About 2000 workers and 500 technical staff are likely to<br />
work during project construction phase. The construction phase, also leads to<br />
mushrooming <strong>of</strong> various allied activities to meet the demands <strong>of</strong> the immigrant<br />
labour population in the project area. Thus, the total increase in labour<br />
population during construction phase is expected to be around 5000-6000.<br />
The total quantum <strong>of</strong> sewage generated is expected to be <strong>of</strong> the order <strong>of</strong> 0.4<br />
mld. The BOD load contributed by domestic sources will be about 270 kg/day.<br />
The sewage generally shall be disposed in nearby streams or channels<br />
through open drains, where ultimately it will find its way into river Bhagirathi.<br />
The inadequate sewage treatment and disposal facilities could lead to<br />
formation <strong>of</strong> pools <strong>of</strong> sewage, which can lead to increased incidence <strong>of</strong> waterborne<br />
diseases. Thus, it is recommended to commission adequate sewage<br />
treatment facilities in the labour camps.<br />
Normally, during construction phase, elaborate sewage treatment facilities<br />
including primary and secondary treatment units are not commissioned, as<br />
they are rendered useless once the construction phase is over. At such sites<br />
septic tanks and or other low cost sanitation units are developed. Similar<br />
9-12
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
sewage treatment measures are envisaged in the labour camps <strong>of</strong> the<br />
proposed project as well.<br />
b) Operation phase<br />
Effluent from project colony<br />
In the operation phase, about 200 families will be residing in the area which<br />
would generate about 0.15 mld <strong>of</strong> sewage. The quantum <strong>of</strong> sewage<br />
generated is not expected to cause any significant adverse impact on riverine<br />
water quality. Adequate sewage treatment facilities including secondary<br />
treatment facilities need to be commissioned for this purpose to ameliorate<br />
the marginal impacts. The type <strong>of</strong> treatment units that need to be installed can<br />
be finalized, based on topography, population served, etc.<br />
Impacts on reservoir water quality<br />
The flooding <strong>of</strong> forest and agricultural land in the submergence area<br />
increases the availability <strong>of</strong> nutrients resulting from decomposition <strong>of</strong><br />
vegetative matter. Enrichment <strong>of</strong> impounded water with organic and inorganic<br />
nutrients at times become a major water quality problem immediately on<br />
commencement <strong>of</strong> the operation and is likely to continue in the initial years <strong>of</strong><br />
operation. However, in case <strong>of</strong> Run-<strong>of</strong>f the river schemes, the submerged<br />
area is negligible. The above referred impact is not expected to be significant.<br />
It is recommended that a detailed modelling study be done to estimate the<br />
D.O. level in the reservoir during its initial years <strong>of</strong> operation.<br />
9-13
Eutrophication risks<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The fertilizer use in the catchment area intercepted at the diversion structure<br />
site is nil and is unlikely to change even during project operation phase.<br />
Since, the present proposal envisages only hydropower generation and does<br />
not entail command area development, problems <strong>of</strong> eutrophication, which are<br />
primarily caused by enrichment <strong>of</strong> nutrients in water are not anticipated. Being<br />
a Run-<strong>of</strong>f-the-river scheme, no eutrophication risks are expected.<br />
9.3.4 Impacts on Terrestrial Flora<br />
a) Construction phase<br />
Increased human interferences<br />
As mentioned earlier, about 2,500 technical staff, workers and other group <strong>of</strong><br />
people are likely to congregate in the area during the project construction<br />
phase. The total increase in population is expected to be about 5000-6000.<br />
Workers and other population groups residing in the area may use fuel wood,<br />
if no alternate fuel is provided. On an average, the fuel wood requirements will<br />
be <strong>of</strong> the order <strong>of</strong> 2500-2700 m 3 . Thus, every year, fuel wood equivalent to<br />
about 800-900 trees will be cut, which implies that every year on an average<br />
about 1 ha <strong>of</strong> dense forest area will be cleared for meeting fuel wood<br />
requirements, if no alternate sources <strong>of</strong> fuel are provided. It should be made<br />
mandatory for the contractor involved in project construction to provide<br />
alternate source <strong>of</strong> fuel to the labour population. Alternatively, community<br />
kitchen using LPG or kerosene as a fuel can also be run at various labour<br />
camps.<br />
9-14
) Operation Phase<br />
Acquisition <strong>of</strong> forest land<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
About 8.36 ha <strong>of</strong> forest area and 0.55 ha <strong>of</strong> scrub land is coming under<br />
reservoir submergence. In addition about 50-55 ha <strong>of</strong> land will also be<br />
required for siting <strong>of</strong> construction equipment, storage <strong>of</strong> construction material,<br />
muck disposal, widening <strong>of</strong> existing roads, construction <strong>of</strong> new project roads,<br />
infrastructure development. Since, the proposed site is located in a reserve<br />
forest area, adequate management measures in the form <strong>of</strong> compensatory<br />
afforestation need to be implemented. It is recommended that a detailed<br />
ecological survey be conducted as a part <strong>of</strong> EIA study to assess the density<br />
and diversity <strong>of</strong> flora in the area. Species requiring conservation need to be<br />
identified and if required the conservation plan for the same be prepared.<br />
9.3.5 Impacts on Terrestrial Fauna<br />
a) Construction phase<br />
The forest area, in the project area and its surroundings provides habitat to<br />
various faunal species, quite a few which are categorised as Schedule-I and<br />
Schedule-II as per the Wildlife Protection Act (1972), which have to be<br />
protected and conserved. As a part <strong>of</strong> the EIA study, detailed data collection<br />
from various secondary sources needs to be done to assess the severity <strong>of</strong><br />
impacts due to various activities in the construction and operation phases on<br />
Schedule-I & II species & other faunal species as well.<br />
Perusal <strong>of</strong> various faunal species observed in the project area, indicates that<br />
there are no migratory faunal species observed in the area. River Bhagirathi<br />
in the project area, even in the pre-project phase, acts as a barrier to wildlife<br />
9-15
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
movement. Thus construction <strong>of</strong> a small reservoir as a part <strong>of</strong> the proposed<br />
project is not expected to cause any additional barrier to wildlife movement in<br />
the project area.<br />
b) Operation phase<br />
During project operation phase, accessibility to the area will improve due to<br />
construction <strong>of</strong> roads, which in turn may increase human interference leading<br />
to marginal adverse impacts on the terrestrial ecosystem. Since, the increase<br />
in human population is not expected to be large, hence significant adverse<br />
impacts on this account are not anticipated.<br />
9.3.6 Impacts on Aquatic Ecology<br />
a) Construction phase<br />
During construction <strong>of</strong> a river valley project, huge quantity <strong>of</strong> muck is<br />
generated at various construction sites, which if not properly disposed,<br />
invariably would flow down the river during heavy precipitation. Such condition<br />
can lead to adverse impacts on the development <strong>of</strong> aquatic life, which needs<br />
to be avoided.<br />
The increased labour population during construction phase, could lead to<br />
increased pressure on fish fauna, as a result <strong>of</strong> indiscriminate fishing by them.<br />
Adequate protection measures at sensitive locations, identified on the basis <strong>of</strong><br />
fisheries survey in the EIA study need to be implemented.<br />
9-16
) Operation phase<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Amongst the aquatic animals, it is the fish life which would be most affected.<br />
The migratory fish species, e.g. Brown trout, Black fish and Mahaseer are<br />
likely to be adversely affected due to obstruction to their migratory route<br />
created by the proposed barrage. The dispersal and migration pattern <strong>of</strong><br />
various fish species need to be ascertained to assess the degree <strong>of</strong> severity<br />
<strong>of</strong> impacts, which needs to be done as a part <strong>of</strong> EIA study.<br />
9.3.7 Impacts on Noise Environment<br />
Increased noise levels are anticipated only during construction phase due to<br />
operation <strong>of</strong> various equipment, increased vehicular traffic and blasting etc.<br />
No human settlements are located close to the project site. However<br />
increased noise level, especially blasting could scare away wildlife from the<br />
area. It has been observed during construction phase <strong>of</strong> similar projects, that<br />
wildlife migrates from such areas and returns after the cessation <strong>of</strong><br />
construction activities. Similar phenomenon is expected in the proposed<br />
project site as well. However, presence <strong>of</strong> Schedule-I & Schedule II species in<br />
the project area, makes its imperative to conduct detailed noise modelling<br />
studies as a part <strong>of</strong> EIA study. Based on the increased noise levels, as<br />
estimated through modelling studies, impacts on each faunal species<br />
observed in areas adjacent to the project site needs to be assessed.<br />
9.3.8 Air Pollution<br />
Pollution due to fuel combustion in various equipment<br />
Normally, diesel is used in construction equipment. The major pollutant which<br />
gets emitted as a result <strong>of</strong> diesel combustion is SO2. The SPM emissions are<br />
9-17
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
minimal due to low ash content in diesel. Model studies conducted for various<br />
projects with similar level <strong>of</strong> fuel consumption indicate that the short-term<br />
increase in SO2, even assuming that all the equipment are operating at a<br />
common point, is quite low, i.e. <strong>of</strong> the order <strong>of</strong> less than 1µg/m 3 . Hence, no<br />
major impact is anticipated on this account.<br />
Emissions from various crushers<br />
The operation <strong>of</strong> the crusher during the construction phase is likely to<br />
generate fugitive emissions, which can move even up to 1 km along the<br />
predominant wind direction. During construction phase, one crusher each is<br />
likely to be commissioned at the diversion structure and the power house<br />
sites. During crushing operations, fugitive emissions comprising <strong>of</strong> the<br />
suspended particulate will be generated. Since, there are no major<br />
settlements close to the diversion structure site, hence, significant adverse<br />
impacts on this account are not anticipated. However, it is recommended that<br />
the labour camp be situated at least 1 km away from the construction sites<br />
and that too on the leeward side <strong>of</strong> the pre-dominant wind direction in the<br />
area.<br />
9.3.9 Impacts on Socio-Economic Environment<br />
a) Project construction phase<br />
The construction phase will last for about 5 years. Those who would migrate<br />
to this area are likely to come from various parts <strong>of</strong> the country mainly having<br />
different cultural, ethnic and social backgrounds. Due to longer residence <strong>of</strong><br />
this population in one place, a new culture, having a distinct socio-economic<br />
similarity would develop which will have its own entity. It is recommended that<br />
labour camps/colonies be located over non-forest area.<br />
9-18
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Normally during construction phase <strong>of</strong> a project, there is significant impact on<br />
the employment potential <strong>of</strong> the area. Many people migrate in the area in<br />
search <strong>of</strong> jobs.<br />
b) Project operation phase<br />
The land to be acquired for reservoir submergence lies in reserve forest. No<br />
private land or homestead are to be acquired. The commissioning <strong>of</strong> a hydroelectric<br />
project provides significant impetus to economic development in the<br />
area being supplied with power. Likewise, in the project area, commissioning<br />
<strong>of</strong> a hydro-electric project would lead to mushrooming <strong>of</strong> various allied<br />
activities, providing employment to locals in the area.<br />
9.4 SUMMARY OF IMPACTS AND EMP<br />
A summary <strong>of</strong> impacts and recommended management measures are<br />
summarized in Table-9.5.<br />
Table-9.5<br />
Summary <strong>of</strong> Impacts and suggested management measures<br />
S.<br />
No.<br />
Parameters Impact Management Measures<br />
1. Land Environment<br />
Construction • Soil erosion due to the • Proper treatment <strong>of</strong><br />
phase<br />
extraction <strong>of</strong><br />
quarry site, and such<br />
construction material sites be located over<br />
from various quarry<br />
sites.<br />
non-forest land<br />
• Temporary acquisition • Such sites be located<br />
<strong>of</strong> land for siting <strong>of</strong><br />
construction equipment<br />
& material, waste<br />
material, etc.<br />
over non-forest land<br />
9-19
S.<br />
No.<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Parameters Impact Management Measures<br />
Operation<br />
phase<br />
2. Water resources<br />
Operation<br />
phase<br />
3. Water quality<br />
Construction<br />
phase<br />
Operation<br />
phase<br />
4. Terrestrial flora<br />
Construction<br />
phase<br />
Operation<br />
phase<br />
• Generation <strong>of</strong> muck due<br />
to tunnelling operations<br />
& roads.<br />
• Acquisition <strong>of</strong> forest<br />
land in reserve forest<br />
area.<br />
• River stretch from<br />
diversion structure site<br />
to tail race outfall will<br />
have reduced flow<br />
especially during lean<br />
season.<br />
• Water pollution due to<br />
disposal <strong>of</strong> sewage<br />
from labour colonies.<br />
• Disposal <strong>of</strong> sewage<br />
from project colony.<br />
• Cutting <strong>of</strong> trees for<br />
meeting fuel wood<br />
requirements by labour.<br />
• Acquisition <strong>of</strong> 8.36 ha<br />
<strong>of</strong> forest area, located<br />
in reserve forest area.<br />
• Disposal at designated<br />
sites and provision <strong>of</strong><br />
suitable management<br />
measures including<br />
bio-engineering<br />
treatment measures<br />
and location <strong>of</strong> such<br />
sites over non-forest<br />
land.<br />
• Compensatory<br />
afforestation &<br />
formulation <strong>of</strong><br />
Conservation Plan<br />
• In case downstream<br />
nallahs do not<br />
contribute lean flows<br />
minimum flow will be<br />
released to maintain<br />
the riverine ecology.<br />
• Provision <strong>of</strong> community<br />
toilets and septic tanks<br />
• Provision <strong>of</strong> adequate<br />
sewage treatment<br />
facilities<br />
• Provision <strong>of</strong> community<br />
kitchen by the<br />
contractors engaged in<br />
project construction.<br />
• Compensatory<br />
afforestation as per the<br />
Indian Forest<br />
Conservation Act<br />
(1980) and formulation<br />
<strong>of</strong> Conservation Plan.<br />
9-20
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
S.<br />
No.<br />
Parameters Impact Management Measures<br />
5. Terrestrial fauna<br />
Construction • Disturbance to wildlife • Increased surveillance,<br />
phase<br />
due to operation <strong>of</strong> in the form <strong>of</strong> check<br />
various construction posts at major<br />
equipment.<br />
construction sites and<br />
Operation • Disturbance to wildlife labour camps.<br />
phase<br />
due to increased • Specific management<br />
accessibility in the measures are not<br />
area.<br />
required<br />
6. Aquatic Ecology<br />
Construction<br />
phase<br />
Operation<br />
phase<br />
7. Noise Environment<br />
Construction<br />
phase<br />
8. Air Environment<br />
Construction<br />
phase<br />
• Marginal decrease in<br />
aquatic productivity due<br />
to increased turbidity<br />
and lesser light<br />
penetration.<br />
• Obstruction in the path<br />
<strong>of</strong> migratory fishes.<br />
• Drying <strong>of</strong> river stretch<br />
downstream <strong>of</strong><br />
diversion structure up to<br />
tail race outfall<br />
• Increase in noise levels<br />
due to operation <strong>of</strong><br />
various construction<br />
equipment.<br />
• Increase in air pollution<br />
due to use <strong>of</strong> machinery<br />
and other civil activities.<br />
• Marginal impact, hence<br />
no specific<br />
management<br />
measures are<br />
suggested.<br />
• Development <strong>of</strong><br />
hatchery for artificial<br />
seed production and<br />
stocking <strong>of</strong> reservoir<br />
and the affected river<br />
stretch<br />
• Provision <strong>of</strong> release <strong>of</strong><br />
minimum flow in case<br />
downstream nallahs do<br />
not contribute to lean<br />
flows.<br />
• Construction<br />
equipment to be<br />
provided with noise<br />
control measures.<br />
• Cyclones will be<br />
provided in various<br />
crushers.<br />
9-21
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
S.<br />
No.<br />
Parameters Impact Management Measures<br />
9. Socio-economic Environment<br />
Construction • Increase in employment -<br />
phase<br />
potential.<br />
Operation<br />
phase<br />
• Increased power<br />
generation<br />
• Greater employment<br />
opportunities.<br />
9.5 CONCLUSIONS AND RECOMMENDATIONS<br />
The project lies in reserve forest area. Detailed ecological studies need to be<br />
conducted to ascertain the adverse impacts on terrestrial flora & fauna. The<br />
following aspects need to be studied in detail as a part <strong>of</strong> next phase <strong>of</strong><br />
environmental studies:<br />
- Impacts due to acquisition <strong>of</strong> forest land in reserve forest area.<br />
- Impacts on wildlife, especially species categorized as Schedule-I &<br />
Schedule– II species as per Wildlife Protection Act (1972).<br />
- Impediment to migratory fish species as a result <strong>of</strong> construction <strong>of</strong><br />
diversion structure.<br />
- Proper stabilization <strong>of</strong> quarry and muck disposal sites<br />
- Management <strong>of</strong> pollution from various sources from labour camps<br />
-<br />
9-22
10.1 INTRODUCTION<br />
CHAPTER –X<br />
INFRASTRUCTURE FACILITIES<br />
PFR STUDIES OF BHAIRONGHATI H.E. PROJECT<br />
The <strong>Bhaironghati</strong> hydroelectric project across the river Bhagirathi envisages<br />
construction <strong>of</strong> a 34 m high dam (above river bed level), a diversion tunnel, a<br />
5.1 km long HRT, an under ground desilting basin, pressure tunnel, an<br />
underground power house with an installed capacity <strong>of</strong> 65 MW and a tail race<br />
tunnel. The dam is located at a distance <strong>of</strong> about 97 km from Uttarkashi. The<br />
major infrastructure facilities needed are described in the following<br />
paragraphs.<br />
10.2 COMMUNICATIONS<br />
10.2.1 The nearest rail head available to the project is Rishikesh which is about 267<br />
km from the Barrage site.<br />
From Rishikesh to <strong>Bhaironghati</strong> via chamba, Dobata, Dunda, Uttarkashi,<br />
Bhatwari, Gangani, Harsil a wide black topped road exists. From Uttarkashi<br />
upto Bhairaonghati (97 km) a motorable road exists but this requires<br />
extensive improvement, widening and hill slope stability measures.<br />
10.2.2 Roads in the Project Area<br />
Apart from improvement <strong>of</strong> existing road, a new approach road is required to<br />
be built from existing main road to intake site (4km).<br />
10-1
PFR STUDIES OF BHAIRONGHATI H.E. PROJECT<br />
Other permanent roads to be constructed include a road from existing main<br />
road to <strong>Power</strong> House, access tunnel (about 3.5 km), project colony, work<br />
adits, and other <strong>Power</strong> House Complex requirements like road to switch yard,<br />
<strong>Power</strong> House Colony etc.<br />
Construction roads are also required from barrage / power house site from<br />
quarry sites, and plant and machinery workshops etc.<br />
Considering the existing road facilities, lengths <strong>of</strong> permanent and temporary<br />
roads that are needed will not be large.<br />
10.2.3 Railways<br />
The nearest railway station is Rishikesh on the broad gauge line. Railway<br />
siding for unloading heavy machineries and equipment is to be provided at<br />
Rishikesh.<br />
10.3 CONSTRUCTION POWER<br />
The power demand for the construction activities is estimated to be about 5<br />
M.W. taking capacity <strong>of</strong> electric driven equippent and lighting which are to<br />
work within the target time for consideration. The initial requirement in the first<br />
two years could be 2 M.W. and this subsequently has to be increased to 3<br />
M.W.<br />
The power requirement can be met with by procuring the supply from<br />
Uttaranchal authorities. For making the power available at project site<br />
required 33/11 K.V. substation and alongwith new power lines about 3 km to<br />
route from <strong>Bhaironghati</strong> is proposed.<br />
10-2
PFR STUDIES OF BHAIRONGHATI H.E. PROJECT<br />
In addition to tapping grid supply, it is also proposed to provide supplemental<br />
power aggregating to 2 M.W. as a stand by in case <strong>of</strong> interruptions in grid<br />
supply.<br />
10.4 TELECOMMUNICATION<br />
To ensure efficient execution at various sites, adequate and reliable<br />
telecommunication net work is necessary. An electronic private Automatic<br />
Exchange with a capacity <strong>of</strong> about 50 lines is proposed.<br />
A VHF system is also proposed to link project Head Quarters with clients<br />
head-quarters.<br />
Suitable number <strong>of</strong> mobile phones / walky talkies are also proposed.<br />
10.5 PROJECT COLONIES/BUILDINGS<br />
10.5.1 The main project colony is proposed near <strong>Bhaironghati</strong> about 3-4 km from<br />
intake site and 10 km from power location. Facilities such as school, post<br />
<strong>of</strong>fice, police station, market, primary health centre are available at<br />
<strong>Bhaironghati</strong> however fire fighting arrangement, canteen, recreation facility,<br />
administrative building, 30 family quarters and a hostel are proposed to be<br />
built.<br />
Two more small colonies are near dam site and another near <strong>Power</strong> House<br />
location are also to be built with other facilities.<br />
10-3
10.5.2 Contractor’s Colony and Labour Colony<br />
PFR STUDIES OF BHAIRONGHATI H.E. PROJECT<br />
Contractors colonies and two or three labour colonies with all amenities are to<br />
be located at sites near the major works.<br />
10.6 WORKSHOPS STORES, FABRICATION YARDS AND MAGAZINES<br />
Workshops for maintaining the plant and equipment used for construction,<br />
stores for construction materials, hydro-mechanical and electro-mechanical<br />
equipments etc. will be built and maintained by the contractor. However, a<br />
small workshop is planned for repair and maintenance facilities <strong>of</strong> project<br />
transport vehicles and minimum essential equipment will be built by the<br />
client.<br />
Areas for fabrication yards for the hydro – mechanical equipment, viz the<br />
various gates and hoists, pressure tunnel liners, penstocks etc. will have to be<br />
identified near the work sites.<br />
Two explosive magazines one for the works at dam site and rock quarries and<br />
another for the underground works are to be built.<br />
10.7 WATER SUPPLY AND SANITATION<br />
For drinking purposes in the colony areas, suitable water treatment plants for<br />
treating water drawn from the river Bhagirathi will be used. For construction<br />
purposes, water directly pumped from the river and stored will be used.<br />
Suitable sanitation and sewerage treatment facilities will have to be mode at<br />
all the project and labour colony areas.<br />
10-4
11.1 INTRODUCTION<br />
CHAPTER – XI<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
CONSTRUCTION PLANNING & SCHEDULE<br />
The Bhairon Ghati H.E. Project is located in the higher attitudes <strong>of</strong> about EL<br />
2610 m in the Himalayas and within the region heavy snow is experienced<br />
during winters. At Badrinath, in Alaknanda sub-basin adjoining Bhagirathi subbasin<br />
an IMD observatory is located reveal that for about 5 months from<br />
December to April heavy snow fall takes place. As such it is inferred that the<br />
project area also has a limited working season as regards construction <strong>of</strong><br />
surface works are concerned. A period <strong>of</strong> 24 months has been provided for<br />
preparation <strong>of</strong> field investigations, subsurface exploration as required for<br />
preparation Detailed Project Report including statutory clearances / approvals.<br />
Thereafter 24 months’ have been provided for pre-construction activities,<br />
surveys, development <strong>of</strong> infrastructure facilities, and construction power,<br />
deciding on the developmental funds / agencies for execution, engineering<br />
design, approach roads, tender engineering etc. Thereafter construction<br />
phase starts only after completion <strong>of</strong> the initial two phases. A construction<br />
period <strong>of</strong> 5 years has been considered based on the specific location <strong>of</strong> the<br />
project in higher attitude and remoteness <strong>of</strong> the area. The initial 24 months<br />
period for DPR preparation could be optimized in case other potential projects<br />
in the basin are taken up simultaneously.<br />
11.2 CONSTRUCTION METHODOLOGY<br />
Bhairon Ghati H.E. Project is envisage as a Run-<strong>of</strong>f-the-River scheme across<br />
Bhagirathi river. Diurnal gross Storage <strong>of</strong> about 1.883 Mcum and with live<br />
storage <strong>of</strong> 0.853 Mcum shall be created by a gravity dam and with the<br />
11-1
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
arrangement <strong>of</strong> gates the flow is proposed to be diverted through a tunnel <strong>of</strong><br />
4.5 m dia <strong>of</strong> horse shoe shaped and 5.1 Km long to the underground power<br />
house and a small tailrace tunnel leading the discharges back to the river.<br />
11.3 MATERIAL SOURCES<br />
During the reconnaissance visit with a geologist and Engineer it is seen that<br />
sand is available near by <strong>of</strong> the power house site and further d/s in the river<br />
bed. Coarse aggregate shall have to be crushed from the nearby quary site<br />
selected for the construction purpose.<br />
11.4 CONTRACT PACKAGES<br />
The contracts packages shall be mainly in the following packages :<br />
a) Headworks including Hydro mechanical<br />
b) Intake tunneling work including adits with desilting chambers.<br />
c) <strong>Power</strong> house, pressure shaft, surge shaft, tailrace tunnel with adits and<br />
approaches<br />
d) Hydro mechanical equipment.<br />
e) Hydro Electrical equipment<br />
The eligibility <strong>of</strong> the contractors shall have to be suitably fixed based on<br />
working experience under similar conditions. The auxiliary works <strong>of</strong> river<br />
diversion including diversion tunnel, c<strong>of</strong>fer dam, penstock installation and<br />
fabrication shall be part <strong>of</strong> the civil works. However, the basic site facilities <strong>of</strong><br />
storage at sites for contractor, approach roads, construction equipment,<br />
testing laboratory, staff colony, field <strong>of</strong>fices and hostels at power house and<br />
intake site could be taken up departmentally to enhance the pace <strong>of</strong> work and<br />
cost recovered from the contractors. The construction equipment packages<br />
11-2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
could be contracted earlier so that by the time civil contractors mobilize the<br />
site facilities and some minimum equipment are made available.<br />
11.5 SCHEDULE OF WORK<br />
As envisaged the underground works could progress and may not be<br />
hampered much by the restricted working season but the progress <strong>of</strong> work<br />
shall be at a lower rate. The surface work shall be limited to about 150 days<br />
in a year with 25 working days in a month and 8 working hours. For the<br />
subsurface works the seasonal effect will be felt on the progress <strong>of</strong> work due<br />
to low temperatures restricted and reduced supplies as such reduction <strong>of</strong><br />
progress in snowy period is considered and about 200 days could be utilized.<br />
Two shift working is considered economical due to shortage <strong>of</strong> working<br />
season, but third shift could be planned based on progress <strong>of</strong> work and<br />
seasonal constraints.<br />
11.6 CONSTRUCTION ACTIVITIES<br />
After the financial terms and the Party/ Agency for investment in the<br />
construction is decided, NIT for fixing the civil contractor can be invited within<br />
6 months on ICB basis.<br />
a) Diversion <strong>of</strong> river<br />
As the river gorge is narrow a diversion tunnel on the left bank is proposed<br />
before construction <strong>of</strong> the dam. The diversion tunnel invert level is kept at<br />
minimum flow level and completed in three months immediately after the<br />
floods recede and before snow fall starts and hampers the surface works,<br />
however, the underground works could progress. The c<strong>of</strong>fer dams could be<br />
constructed during next lean flood period and subsequent floods could be<br />
11-3
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
allowed to over top the masonry c<strong>of</strong>fer dam. The dam shall be constructed in<br />
phases <strong>of</strong> overflow and non-overflow sections. Once the dam is fully operative<br />
the diversion tunnel could be plugged. The river bed excavation shall be<br />
handled by 3.0 cum hydraulic excavators and Rear Dumpers (25t).<br />
b) Construction <strong>of</strong> the dam shall be completed in 33 months.<br />
c) <strong>Power</strong> House<br />
The under ground <strong>Power</strong> house accommodates 2x32.5 MW units. The<br />
excavation <strong>of</strong> the power house cavern shall be by convential drilling and<br />
blasting method deploying air track, jack hammers and mucking shall be<br />
through trolleys mounted on rails as the working space in the tunnel shall be<br />
limited. Approach to the <strong>Power</strong> House cavern shall be from the highway by a<br />
small additional road with an access tunnel from the same bank.<br />
d) Tunnelling<br />
The finished dia <strong>of</strong> the tunnel (HRT) is proposed as 4.5 m and 5.1 Km long.<br />
As regards approach to <strong>Power</strong> House from the highway which is in the left<br />
bank a small approach road shall be constructed on the same bank to<br />
approach the <strong>Power</strong> House adit and also approach the Surge Shaft. One Adit<br />
each at <strong>Power</strong> House, Surge Shaft shall be provided. As both the banks <strong>of</strong> the<br />
river are under Deodar Forest as such no additional adit is proposed and<br />
approach roads to Surge shaft, <strong>Power</strong> house and intake structure shall be <strong>of</strong><br />
minimum length. There shall be two faces for working on the HRT. Tunnel<br />
excavation shall be based on conventional drilling and blasting and supported<br />
by ribs where essential and supporting the excavated rock face by<br />
shotcreting. A period <strong>of</strong> 39 months has been kept for tunnel & power house<br />
11-4
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
construction. The pressure shaft and Surge shaft shall be excavated through<br />
Alimak Raise Climber.<br />
The construction schedule at PFR stage studies is given in the enclosed<br />
Plate 11-1.<br />
11-5
12.1 INTRODUCTION<br />
CHAPTER-XII<br />
COST ESTIMATE<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
Bhairon Ghati H.E. Project is proposed as Run-<strong>of</strong>f-the River scheme on the<br />
river Bhagirathi to tap its hydropower potential. The diversion structure is<br />
located downstream <strong>of</strong> its confluence with Jadhganga in Uttarkashi district.<br />
The project envisages to divert the water <strong>of</strong> Bhagirathi into water conductor<br />
system by means <strong>of</strong> a diversion structure (a concrete gravity dam) across the<br />
river. The water conductor system comprises <strong>of</strong> an intake, underground<br />
desilting chambers followed by a 5.1 km long head race tunnel <strong>of</strong> 4.5 m<br />
diameter (horse shoe shaped), a surge shaft <strong>of</strong> 10 m diameter, a pressure<br />
shaft which bifurcates near power house to feed two units <strong>of</strong> 32.5 MW each<br />
and housed in an underground power house. A 190 m long tail race tunnel<br />
discharges the water back into the river Bhagirathi upstream <strong>of</strong> another<br />
proposed Harsil H.E. scheme head works.<br />
12.2 ABSTRACT OF COSTS<br />
The Project is estimated to cost Rs. 256.29 crores at June 2003 price level<br />
the break down <strong>of</strong> cost is given below :<br />
Item Estimated Cost<br />
( Rs. Crore )<br />
Civil Works 164.94<br />
Electrical Works 91.35<br />
Sub Total (Generation) 256.29<br />
12-1
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The project estimate has been prepared on the basis <strong>of</strong> “ Guidelines for<br />
preparation <strong>of</strong> cost estimates for River Valley projects” published by Central<br />
Water Commission, New Delhi. The abstract <strong>of</strong> cost <strong>of</strong> civil works is<br />
enclosed as Annexure 12.1. The above cost does not include the cost <strong>of</strong><br />
transmission. However cost <strong>of</strong> power evacuation for this project under<br />
construction has been arrived as Rs. 7.5 Crores. Cost <strong>of</strong> Electromechanical<br />
is enclosed as Annexure 12.2<br />
The estimate for civil & Hydro mechanical works have been prepared based<br />
on the as average rates for major items <strong>of</strong> works made available by CWC in<br />
the “guidelines for estimating the civil cost for the preparation <strong>of</strong> PFR”.<br />
The electro mechanical rates have been adopted on the basis <strong>of</strong> enquiry<br />
floated to various reputed manufactures / supplier. The rates are inclusive <strong>of</strong><br />
excise duty & taxes.<br />
The phased programme <strong>of</strong> construction has been given in the relevant<br />
chapter with this report.<br />
Cost provisions for the various items mentioned below has been made on<br />
lump sum percentage basis <strong>of</strong> C-Works & J – <strong>Power</strong> Plant Civil Works for<br />
working out the total cost <strong>of</strong> project at pre - feasibility stage.<br />
12-2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
S.No. Items Provisions <strong>of</strong> % <strong>of</strong><br />
C- Works & J - <strong>Power</strong><br />
Plant Civil Works<br />
1 A. Preliminary 2%<br />
2 K. Buildings 4%<br />
3 O. Miscellaneous 5%<br />
4 P. Maintenance 1% <strong>of</strong> (C+J+K+R)<br />
5 R. Communication 4%<br />
6 X. Environment & Ecology 2.0%<br />
7 Y. Losses on Stock 0.25% <strong>of</strong> C – Works,<br />
J - <strong>Power</strong> Plant - Civil<br />
Works, K - Building &<br />
R - Communication<br />
12-3
13.1 GENERAL<br />
CHAPTER – XIII<br />
ECONOMIC EVALUATION<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The economic and financial evaluation <strong>of</strong> the Bhairon Ghati H.E project have<br />
been carried out considering the standard guidelines issued by Central<br />
Electricity Authority and the norms laid down by the Central Electricity<br />
Regulatory Commission (CERC) for Hydro projects.<br />
13.2 PROJECT BENEFITS<br />
13.2.1 The scheme would afford on annual energy generation <strong>of</strong> 293.18 GWh in a<br />
90% dependable year. For assessing the tariff, design energy generation <strong>of</strong><br />
279.45 GWh , calculated with 95% capacity availability in a 90% dependable<br />
year, has been adopted. The project would provide 65 MW <strong>of</strong> peaking<br />
capacity benefits.<br />
13.3 CAPITAL COST<br />
The project cost has been estimated at Rs. 256.29 crores without IDC based<br />
on the criteria for “Adoption <strong>of</strong> Rates and Cost for preparation <strong>of</strong> PFRs <strong>of</strong><br />
hydro-electric projects” issued by CEA and is as given below:<br />
1. Cost <strong>of</strong> civil works = Rs. 164.94 Crores<br />
2. Cost <strong>of</strong> Electrical/Mechanical works = Rs 91.35 Crores<br />
Total = Rs. 256.29 Crores<br />
13-1
13.4 MODE OF FINANCING<br />
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
The project is proposed to be financed with a debt equity ratio <strong>of</strong> 70:30. An<br />
interest rate <strong>of</strong> 10% on the loan component has been considered for the<br />
financial analysis <strong>of</strong> the project. The interest on the working capital is taken<br />
as 9.75%.<br />
13.5 PHASING OF EXPENDITURE<br />
The project is proposed to be completed in 5 years period in all respect with<br />
full benefit available after 5 years. The detailed year wise phasing <strong>of</strong><br />
expenditure based upon the above construction programme for Civil &<br />
Electrical works is given in Annexure 13.1.<br />
13.6 FINANCIAL ANALYSIS<br />
13.6.1 Basic and Normative Parameters<br />
The following basic parameters have been adopted for working out the<br />
financial analysis <strong>of</strong> the project.<br />
i) Estimated capital cost <strong>of</strong> Rs. 296.82 Crores considering the Interest<br />
during construction.<br />
ii) Annual energy generation <strong>of</strong> 293.18 GWh in 90% dependable year and<br />
Design energy <strong>of</strong> 279.45 GWh.<br />
iii) Operation & maintenance expenses (including insurance) @ 1.5% <strong>of</strong><br />
the project cost in the first year with 5% escalation every year.<br />
iv) Depreciation @ 3.5 % has been considered on an average basis.<br />
v) Auxiliary consumption @ 0.7 % <strong>of</strong> the energy generated.<br />
vi) Transformation loss @ 0.5% <strong>of</strong> the energy generated.<br />
vii) Interest on working capital @ 9.75%.<br />
13-2
PFR STUDIES OF BHAIRON GHATI H.E. PROJECT<br />
viii) Interest during construction has been worked out based upon the<br />
interest rates as mentioned above. The computations are given in<br />
Annexure 13.2 for present day capital cost.<br />
ix) Corporate tax @ 30%.<br />
x) Return on equity @ 16%.<br />
13.6.2 ASSESSMENT OF TARIFF<br />
Based upon the parameters given above, the sale rate <strong>of</strong> energy at bus bar<br />
has been computed in Annexure 13.3. The sale rate applicable in the first<br />
year and levellised tariff is indicated below.<br />
13.7 CONCLUSION<br />
Tariff Period<br />
First Year<br />
Levellised Tariff<br />
TABLE – 13.2<br />
Tariff<br />
(Rs./KWh)<br />
1.80<br />
1.57<br />
The sale rate <strong>of</strong> energy indicated above shows that the energy generated<br />
from the project is financially viable and economically attractive.<br />
13-3
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
Calculation <strong>of</strong> Interest During Construction<br />
Debt : Equity 70 : 30<br />
Interest rate @ 10 %<br />
(INR crores)<br />
Annexure 13.2<br />
Year Project Equity Loan<br />
ITERATION - I GRAND TOTAL<br />
cost component component Cummulative IDC Equity for Loan for TOTAL Capitalised<br />
(30%) (70%) loan 10.0% IDC IDC IDC IDC cost<br />
(Civil & E&M)<br />
(6) x 0.30 (6) x 0.70 10.0%<br />
1 2 3 4 5 6 7 8 9 10 11<br />
1 25.63 25.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.63<br />
2 76.89 51.26 25.63 25.63 1.28 0.38 0.90 0.04 1.33 78.21<br />
3 76.89 0.00 76.89 102.52 6.41 1.92 4.49 0.31 6.72 83.61<br />
4 51.26 0.00 51.26 153.77 12.81 3.84 8.97 0.99 13.80 65.06<br />
5 25.63 0.00 25.63 179.40 16.66 5.00 11.66 2.02 18.68 44.31<br />
Total 256.29 76.89 179.40 37.16 11.15 26.01 3.36 40.53 296.82
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
Phasing <strong>of</strong> Expenditure<br />
Year Civil cost E & M cost Total cost<br />
1 16.49 9.14 25.63<br />
2 49.48 27.41 76.89<br />
3 49.48 27.41 76.89<br />
4 32.99 18.27 51.26<br />
5 16.49 9.14 25.63<br />
Total 164.94 91.35 256.29<br />
Annexure -13.1<br />
INR crores
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
TARIFF CALCULATIONS WITH PROJECTED COMPLETION COST<br />
Annexure - 13.3<br />
Debt:Equity Ratio 7.0 : 3.0<br />
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12<br />
BASIC PARAMETERS<br />
Capacity (MW) 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00<br />
Capital Cost (INR crores) 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29<br />
Capital Cost with IDC . 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82<br />
Equity Portion (%) 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00<br />
Debt Portion (%) 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00<br />
Capital Cost/MW (INR crores) 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57<br />
Interest rate for WC (%) 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75<br />
Tax rate (%) 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00<br />
Interest rate on loan from Financial Institutions (%) 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00<br />
Total annual energy (GWh) 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18<br />
Design energy with 90% dependibility (GWh) 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45<br />
Saleable Energy after aux. (GWh) 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11<br />
consumption & transformation losses<br />
FINANCIAL PACKAGE (INR crores)<br />
LOAN % <strong>of</strong> % <strong>of</strong> Intt. AMOUNT EQUITY % <strong>of</strong> % <strong>of</strong> AMOUNT<br />
Loan Component 207.8 total project Rate (INR total project (INR<br />
loan cost (%) crores) equity cost crores)<br />
Fin. Institutions 207.77<br />
Equity component 89.04 Fin. Institutions 100.00 70.00 10.00 207.77 Equity 100.00 30.00 89.04<br />
89.04 296.8<br />
Period Repayment Moratorium Installment/yr.<br />
Financial Inst. 10 0 1<br />
Repayment Amount/year<br />
Financial Institutions 20.78<br />
Construction Period (Yrs.) 5<br />
Total 100.00 70.00 207.77 Total 100.00 30.00 89.04<br />
1/12
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
TARIFF CALCULATIONS WITH PROJECTED COMPLETION COST<br />
Annexure - 13.3<br />
Debt:Equity Ratio 7.0 : 3.0<br />
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12<br />
NORMATIVE PARAMETERS Year 1 2 3 4 5 6 7 8 9 10 11 12<br />
O & M Charges incl. Insurance (%) 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50<br />
O & M Inflation rate (%) 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00<br />
Rate <strong>of</strong> return on equity (%) 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00<br />
Rate <strong>of</strong> Depreciation (ES Act) (%) 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50<br />
Rate <strong>of</strong> Depreciation (IT Act) (%) 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00<br />
Spares for 1 yr -1/5th C.S 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59<br />
Auxiliary consumption (%) 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70<br />
Transformation Losses (%) 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50<br />
SCHEDULE OF LOAN REPAYMENT<br />
AGENCY Year 1 2 3 4 5 6 7 8 9 10 11 12<br />
FINANCIAL INSTITUTIONS<br />
Outstanding Term loan 207.77 186.99 166.22 145.44 124.66 103.89 83.11 62.33 41.55 20.78 0.00 0.00<br />
Term loan installment 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 0.00 0.00<br />
Cum. Loan Repaid 20.78 41.55 62.33 83.11 103.89 124.66 145.44 166.22 186.99 207.77 207.77 207.77<br />
Interest on Term loan 19.74 17.66 15.58 13.51 11.43 9.35 7.27 5.19 3.12 1.04 0.00 0.00<br />
Total Yearly installment 40.52 38.44 36.36 34.28 32.20 30.13 28.05 25.97 23.89 21.82 0.00 0.00<br />
LOAN SERVICING<br />
Outstanding Term loan 207.77 186.99 166.22 145.44 124.66 103.89 83.11 62.33 41.55 20.78 0.00 0.00<br />
Loan Repayment Installment 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 0.00 0.00<br />
Sources <strong>of</strong> Funds for Repayment<br />
- Depreciation (ES Act) 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 0.00 0.00<br />
- Advance Depreciation 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
- Additional sources (ROE ) 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 0.00 0.00<br />
COMPUTATION OF TARIFF COMPONENTS<br />
INTEREST ON CAPITAL<br />
Interest on Term loan 19.74 17.66 15.58 13.51 11.43 9.35 7.27 5.19 3.12 1.04 0.00 0.00<br />
Total Yearly Installment 40.52 38.44 36.36 34.28 32.20 30.13 28.05 25.97 23.89 21.82 0.00 0.00<br />
2/12
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
TARIFF CALCULATIONS WITH PROJECTED COMPLETION COST<br />
Annexure - 13.3<br />
Debt:Equity Ratio 7.0 : 3.0<br />
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12<br />
RATE OF RETURN<br />
Equity amount 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04<br />
Return on Equity 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25<br />
O & M EXPENSES 4.45 4.67 4.91 5.15 5.41 5.68 5.97 6.26 6.58 6.91 7.25 7.61<br />
INTEREST ON WORKING CAPITAL<br />
WORKING CAPITAL<br />
O & M Expenses - 1 month 0.37 0.39 0.41 0.43 0.45 0.47 0.50 0.52 0.55 0.58 0.60 0.63<br />
Spares 1 year - 1/5th cap spares 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59<br />
Receivables for 2 months<br />
DEP(ES Act) 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73<br />
Interest 3.29 2.94 2.60 2.25 1.90 1.56 1.21 0.87 0.52 0.17 0.00 0.00<br />
Return on Equity 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37<br />
O&M 0.74 0.78 0.82 0.86 0.90 0.95 0.99 1.04 1.10 1.15 1.21 1.27<br />
I.Tax 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.29 1.85<br />
Interest on W.C. 0.11 0.11 0.10 0.10 0.10 0.09 0.09 0.09 0.08 0.08 0.08 0.10<br />
Total Working capital 9.21 8.92 8.63 8.34 8.05 7.77 7.49 7.22 6.95 6.68 6.88 8.55<br />
Interest on Working Capital 0.90 0.87 0.84 0.81 0.79 0.76 0.73 0.70 0.68 0.65 0.67 0.83<br />
DEPRECIATION (ES ACT) (INR crores)<br />
Total Depreciable Amount 267.13 256.75 246.36 235.97 225.58 215.19 204.80 194.41 184.03 173.64 163.25 152.86<br />
Opening Depreciation Fund 0.00 -10.39 -20.78 -31.17 -41.55 -51.94 -51.94 -51.94 -51.94 -51.94 -51.94 -41.55<br />
Yearly Depreciation (ES Act) 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39<br />
Cumulative Depreciation Fund 10.39 0.00 -10.39 -20.78 -31.17 -41.55 -41.55 -41.55 -41.55 -41.55 -41.55 -31.17<br />
Loan Repayment Installment 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 20.78 0.00 0.00<br />
Advance Dep. for loan Repayment 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
Return on Eq. for loan Repayment 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 0.00 0.00<br />
Closing Cummulative Dep. Fund -10.39 -20.78 -31.17 -41.55 -51.94 -51.94 -51.94 -51.94 -51.94 -51.94 -41.55 -31.17<br />
Total Depreciation 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39<br />
Net Depreciable Amount 267.13 256.75 246.36 235.97 225.58 215.19 204.80 194.41 184.03 173.64 163.25 152.86<br />
DEPRECIATION (IT ACT) (INR crores)<br />
Sum at charge 296.82 222.61 166.96 125.22 93.91 70.44 52.83 39.62 29.72 22.29 16.71 12.54<br />
Depreciation (IT Act) 74.20 55.65 41.74 31.30 23.48 17.61 13.21 9.91 7.43 5.57 4.18 3.13<br />
Dep.limited to 90% <strong>of</strong> capital cost 74.20 55.65 41.74 31.30 23.48 17.61 13.21 9.91 0.03 0.00 0.00 0.00<br />
3/12
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
TARIFF CALCULATIONS WITH PROJECTED COMPLETION COST<br />
Annexure - 13.3<br />
Debt:Equity Ratio 7.0 : 3.0<br />
Yr 1 Yr 2 Yr 3 Yr 4 Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Yr 10 Yr 11 Yr 12<br />
TAX LIABILITY (INR crores)<br />
Yearly Pr<strong>of</strong>it/loss -49.57 -31.02 -17.10 -6.67 1.16 7.03 11.43 14.73 24.60 24.64 24.64 24.64<br />
Cummulative Pr<strong>of</strong>it/loss (+/-) -49.57 -80.59 -97.69 -104.36 -103.20 -96.17 -84.75 -70.02 -45.41 -20.78 3.86 28.49<br />
Tax liability 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.74 11.09<br />
CAPACITY AND ENERGY CHARGES<br />
Annual Capacity Charge (INR crores) 30.13 28.05 25.97 23.89 21.82 19.74 17.66 15.58 13.51 11.43 10.39 10.39<br />
Annual Energy Charge (INR crores) 19.60 19.79 20.00 20.21 20.44 20.69 20.94 21.22 21.50 21.81 23.91 33.78<br />
Total Annual Charge (INR crores) 49.72 47.84 45.97 44.11 42.26 40.43 38.60 36.80 35.01 33.23 34.30 44.17<br />
Average Tariff (INR/kWh) 1.80 1.73 1.66 1.60 1.53 1.46 1.40 1.33 1.27 1.20 1.24 1.60<br />
Average Tariff for 5 years (INR/kWh) 1.67 1.33 1.55<br />
Discount rate (%) 12.00 / Year 1 2 3 4 5 6 7 8 9 10 11 12<br />
Discounted Average Tariff (INR/kWh) 1.80 1.55 1.33 1.14 0.97 0.83 0.71 0.60 0.51 0.43 0.40 0.46<br />
Levellised Eq.Avg. Tariff (INR/kWh) 1.57<br />
4/12
BASIC PARAMETERS<br />
Capacity (MW)<br />
Capital Cost (INR crores)<br />
Capital Cost with IDC .<br />
Equity Portion (%)<br />
Debt Portion (%)<br />
Capital Cost/MW (INR crores)<br />
Interest rate for WC (%)<br />
Tax rate (%)<br />
Interest rate on loan from Financial Institutions (%)<br />
Total annual energy (GWh)<br />
Design energy with 90% dependibility (GWh)<br />
Saleable Energy after aux. (GWh)<br />
consumption & transformation losses<br />
FINANCIAL PACKAGE (INR crores)<br />
Loan Component 207.8<br />
Fin. Institutions 207.77<br />
Equity component 89.04<br />
89.04 296.8<br />
Period Repayment Moratorium Installment/yr.<br />
Financial Inst. 10 0 1<br />
Repayment Amount/year<br />
Financial Institutions 20.78<br />
Construction Period (Yrs.) 5<br />
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
TARIFF CALCULATIONS WITH PROJECTED COMPLETION COST<br />
Annexure - 13.3<br />
Debt:Equity Ratio 7.0 : 3.0<br />
Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24<br />
65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00<br />
256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29<br />
296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82<br />
30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00<br />
70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00<br />
4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57<br />
9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75<br />
30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00<br />
10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00<br />
293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18<br />
279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45<br />
276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11<br />
5/12
NORMATIVE PARAMETERS Year<br />
O & M Charges incl. Insurance (%)<br />
O & M Inflation rate (%)<br />
Rate <strong>of</strong> return on equity (%)<br />
Rate <strong>of</strong> Depreciation (ES Act) (%)<br />
Rate <strong>of</strong> Depreciation (IT Act) (%)<br />
Spares for 1 yr -1/5th C.S<br />
Auxiliary consumption (%)<br />
Transformation Losses (%)<br />
SCHEDULE OF LOAN REPAYMENT<br />
AGENCY Year<br />
FINANCIAL INSTITUTIONS<br />
Outstanding Term loan<br />
Term loan installment<br />
Cum. Loan Repaid<br />
Interest on Term loan<br />
Total Yearly installment<br />
LOAN SERVICING<br />
Outstanding Term loan<br />
Loan Repayment Installment<br />
Sources <strong>of</strong> Funds for Repayment<br />
- Depreciation (ES Act)<br />
- Advance Depreciation<br />
- Additional sources (ROE )<br />
COMPUTATION OF TARIFF COMPONENTS<br />
INTEREST ON CAPITAL<br />
Interest on Term loan<br />
Total Yearly Installment<br />
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
TARIFF CALCULATIONS WITH PROJECTED COMPLETION COST<br />
Annexure - 13.3<br />
Debt:Equity Ratio 7.0 : 3.0<br />
Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24<br />
13 14 15 16 17 18 19 20 21 22 23 24<br />
1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50<br />
5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00<br />
16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00<br />
3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50<br />
25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00<br />
0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59<br />
0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70<br />
0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50<br />
13 14 15 16 17 18 19 20 21 22 23 24<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
6/12
RATE OF RETURN<br />
Equity amount<br />
Return on Equity<br />
O & M EXPENSES<br />
INTEREST ON WORKING CAPITAL<br />
WORKING CAPITAL<br />
O & M Expenses - 1 month<br />
Spares 1 year - 1/5th cap spares<br />
Receivables for 2 months<br />
DEP(ES Act)<br />
Interest<br />
Return on Equity<br />
O&M<br />
I.Tax<br />
Interest on W.C.<br />
Total Working capital<br />
Interest on Working Capital<br />
DEPRECIATION (ES ACT) (INR crores)<br />
Total Depreciable Amount<br />
Opening Depreciation Fund<br />
Yearly Depreciation (ES Act)<br />
Cumulative Depreciation Fund<br />
Loan Repayment Installment<br />
Advance Dep. for loan Repayment<br />
Return on Eq. for loan Repayment<br />
Closing Cummulative Dep. Fund<br />
Total Depreciation<br />
Net Depreciable Amount<br />
DEPRECIATION (IT ACT) (INR crores)<br />
Sum at charge<br />
Depreciation (IT Act)<br />
Dep.limited to 90% <strong>of</strong> capital cost<br />
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
TARIFF CALCULATIONS WITH PROJECTED COMPLETION COST<br />
Annexure - 13.3<br />
Debt:Equity Ratio 7.0 : 3.0<br />
Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24<br />
89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04<br />
14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25<br />
8.00 8.40 8.82 9.26 9.72 10.20 10.71 11.25 11.81 12.40 13.02 13.68<br />
0.67 0.70 0.73 0.77 0.81 0.85 0.89 0.94 0.98 1.03 1.09 1.14<br />
0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59<br />
1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73 1.73<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37<br />
1.33 1.40 1.47 1.54 1.62 1.70 1.79 1.88 1.97 2.07 2.17 2.28<br />
1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85 1.85<br />
0.10 0.11 0.11 0.11 0.11 0.11 0.11 0.11 0.12 0.12 0.12 0.12<br />
8.65 8.75 8.86 8.97 9.09 9.21 9.34 9.47 9.62 9.77 9.92 10.09<br />
0.84 0.85 0.86 0.87 0.89 0.90 0.91 0.92 0.94 0.95 0.97 0.98<br />
142.47 132.08 121.69 111.31 100.92 90.53 80.14 69.75 59.36 48.97 38.59 28.20<br />
-31.17 -20.78 -10.39 0.00 10.39 20.78 31.17 41.55 51.94 62.33 72.72 83.11<br />
10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39<br />
-20.78 -10.39 0.00 10.39 20.78 31.17 41.55 51.94 62.33 72.72 83.11 93.50<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
-20.78 -10.39 0.00 10.39 20.78 31.17 41.55 51.94 62.33 72.72 83.11 93.50<br />
10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39<br />
142.47 132.08 121.69 111.31 100.92 90.53 80.14 69.75 59.36 48.97 38.59 28.20<br />
9.40 7.05 5.29 3.97 2.97 2.23 1.67 1.26 0.94 0.71 0.53 0.40<br />
2.35 1.76 1.32 0.99 0.74 0.56 0.42 0.31 0.24 0.18 0.13 0.10<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
7/12
TAX LIABILITY (INR crores)<br />
Yearly Pr<strong>of</strong>it/loss<br />
Cummulative Pr<strong>of</strong>it/loss (+/-)<br />
Tax liability<br />
CAPACITY AND ENERGY CHARGES<br />
Annual Capacity Charge (INR crores)<br />
Annual Energy Charge (INR crores)<br />
Total Annual Charge (INR crores)<br />
Average Tariff (INR/kWh)<br />
Average Tariff for 5 years (INR/kWh)<br />
Discount rate (%) 12.00 / Year<br />
Discounted Average Tariff (INR/kWh)<br />
Levellised Eq.Avg. Tariff (INR/kWh)<br />
BHAIRONGHATI HYDEL SCHEME ( Underground <strong>Power</strong> House )<br />
TARIFF CALCULATIONS WITH PROJECTED COMPLETION COST<br />
Annexure - 13.3<br />
Debt:Equity Ratio 7.0 : 3.0<br />
Yr 13 Yr 14 Yr 15 Yr 16 Yr 17 Yr 18 Yr 19 Yr 20 Yr 21 Yr 22 Yr 23 Yr 24<br />
24.64 24.64 24.64 24.64 24.64 24.64 24.64 24.64 24.64 24.64 24.64 24.64<br />
53.13 77.77 102.40 127.04 151.67 176.31 200.94 225.58 250.22 274.85 299.49 324.12<br />
11.09 11.09 11.09 11.09 11.09 11.09 11.09 11.09 11.09 11.09 11.09 11.09<br />
10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39 10.39<br />
34.17 34.58 35.01 35.46 35.94 36.44 36.96 37.51 38.08 38.69 39.32 39.99<br />
44.56 44.97 45.40 45.85 46.33 46.82 47.35 47.90 48.47 49.08 49.71 50.38<br />
1.61 1.63 1.64 1.66 1.68 1.70 1.71 1.73 1.76 1.78 1.80 1.82<br />
1.70 1.80<br />
13 14 15 16 17 18 19 20 21 22 23 24<br />
0.41 0.37 0.34 0.30 0.27 0.25 0.22 0.20 0.18 0.16 0.15 0.13<br />
8/12
BASIC PARAMETERS<br />
Capacity (MW)<br />
Capital Cost (INR crores)<br />
Capital Cost with IDC .<br />
Equity Portion (%)<br />
Debt Portion (%)<br />
Capital Cost/MW (INR crores)<br />
Interest rate for WC (%)<br />
Tax rate (%)<br />
Interest rate on loan from Financial Institutions (%)<br />
Total annual energy (GWh)<br />
Design energy with 90% dependibility (GWh)<br />
Saleable Energy after aux. (GWh)<br />
consumption & transformation losses<br />
FINANCIAL PACKAGE (INR crores)<br />
Loan Component 207.8<br />
Fin. Institutions 207.77<br />
Equity component 89.04<br />
89.04 296.8<br />
Period Repayment Moratorium Installment/yr.<br />
Financial Inst. 10 0 1<br />
Repayment Amount/year<br />
Financial Institutions 20.78<br />
Construction Period (Yrs.) 5<br />
Annexure - 13.3<br />
7.0 : 3.0<br />
Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33 Yr 34 Yr 35<br />
65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00 65.00<br />
256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29 256.29<br />
296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82 296.82<br />
30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00<br />
70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00<br />
4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57 4.57<br />
9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75 9.75<br />
30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00 30.00<br />
10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00<br />
293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18 293.18<br />
279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45 279.45<br />
276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11 276.11<br />
9/12
NORMATIVE PARAMETERS Year<br />
O & M Charges incl. Insurance (%)<br />
O & M Inflation rate (%)<br />
Rate <strong>of</strong> return on equity (%)<br />
Rate <strong>of</strong> Depreciation (ES Act) (%)<br />
Rate <strong>of</strong> Depreciation (IT Act) (%)<br />
Spares for 1 yr -1/5th C.S<br />
Auxiliary consumption (%)<br />
Transformation Losses (%)<br />
SCHEDULE OF LOAN REPAYMENT<br />
AGENCY Year<br />
FINANCIAL INSTITUTIONS<br />
Outstanding Term loan<br />
Term loan installment<br />
Cum. Loan Repaid<br />
Interest on Term loan<br />
Total Yearly installment<br />
LOAN SERVICING<br />
Outstanding Term loan<br />
Loan Repayment Installment<br />
Sources <strong>of</strong> Funds for Repayment<br />
- Depreciation (ES Act)<br />
- Advance Depreciation<br />
- Additional sources (ROE )<br />
COMPUTATION OF TARIFF COMPONENTS<br />
INTEREST ON CAPITAL<br />
Interest on Term loan<br />
Total Yearly Installment<br />
Annexure - 13.3<br />
7.0 : 3.0<br />
Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33 Yr 34 Yr 35<br />
25 26 27 28 29 30 31 32 33 34 35<br />
1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50<br />
5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00<br />
16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00 16.00<br />
3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50<br />
25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00 25.00<br />
0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59<br />
0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70<br />
0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50<br />
25 26 27 28 29 30 31 32 33 34 35<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77 207.77<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
10/12
RATE OF RETURN<br />
Equity amount<br />
Return on Equity<br />
O & M EXPENSES<br />
INTEREST ON WORKING CAPITAL<br />
WORKING CAPITAL<br />
O & M Expenses - 1 month<br />
Spares 1 year - 1/5th cap spares<br />
Receivables for 2 months<br />
DEP(ES Act)<br />
Interest<br />
Return on Equity<br />
O&M<br />
I.Tax<br />
Interest on W.C.<br />
Total Working capital<br />
Interest on Working Capital<br />
DEPRECIATION (ES ACT) (INR crores)<br />
Total Depreciable Amount<br />
Opening Depreciation Fund<br />
Yearly Depreciation (ES Act)<br />
Cumulative Depreciation Fund<br />
Loan Repayment Installment<br />
Advance Dep. for loan Repayment<br />
Return on Eq. for loan Repayment<br />
Closing Cummulative Dep. Fund<br />
Total Depreciation<br />
Net Depreciable Amount<br />
DEPRECIATION (IT ACT) (INR crores)<br />
Sum at charge<br />
Depreciation (IT Act)<br />
Dep.limited to 90% <strong>of</strong> capital cost<br />
Annexure - 13.3<br />
7.0 : 3.0<br />
Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33 Yr 34 Yr 35<br />
89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04 89.04<br />
14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25<br />
14.36 15.08 15.83 16.62 17.45 18.33 19.24 20.20 21.21 22.28 23.39<br />
1.20 1.26 1.32 1.39 1.45 1.53 1.60 1.68 1.77 1.86 1.95<br />
0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59<br />
1.73 1.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37 2.37<br />
2.39 2.51 2.64 2.77 2.91 3.05 3.21 3.37 3.54 3.71 3.90<br />
1.85 1.63 1.07 1.07 1.07 1.07 1.07 1.07 1.07 1.07 1.07<br />
0.12 0.12 0.10 0.10 0.10 0.11 0.11 0.11 0.11 0.12 0.12<br />
10.26 9.72 8.09 8.29 8.50 8.72 8.96 9.20 9.45 9.72 10.00<br />
1.00 0.95 0.79 0.81 0.83 0.85 0.87 0.90 0.92 0.95 0.98<br />
17.81 7.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
93.50 103.89 111.31 111.31 111.31 111.31 111.31 111.31 111.31 111.31 111.31<br />
10.39 7.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
103.89 111.31 111.31 111.31 111.31 111.31 111.31 111.31 111.31 111.31 111.31<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
103.89 111.31 111.31 111.31 111.31 111.31 111.31 111.31 111.31 111.31 111.31<br />
10.39 7.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
17.81 7.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
0.30 0.22 0.17 0.13 0.09 0.07 0.05 0.04 0.03 0.02 0.02<br />
0.07 0.06 0.04 0.03 0.02 0.02 0.01 0.01 0.01 0.01 0.00<br />
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
11/12
TAX LIABILITY (INR crores)<br />
Yearly Pr<strong>of</strong>it/loss<br />
Cummulative Pr<strong>of</strong>it/loss (+/-)<br />
Tax liability<br />
CAPACITY AND ENERGY CHARGES<br />
Annual Capacity Charge (INR crores)<br />
Annual Energy Charge (INR crores)<br />
Total Annual Charge (INR crores)<br />
Average Tariff (INR/kWh)<br />
Average Tariff for 5 years (INR/kWh)<br />
Discount rate (%) 12.00 / Year<br />
Discounted Average Tariff (INR/kWh)<br />
Levellised Eq.Avg. Tariff (INR/kWh)<br />
Annexure - 13.3<br />
7.0 : 3.0<br />
Yr 25 Yr 26 Yr 27 Yr 28 Yr 29 Yr 30 Yr 31 Yr 32 Yr 33 Yr 34 Yr 35<br />
24.64 21.67 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25 14.25<br />
348.76 370.43 384.67 398.92 413.17 427.41 441.66 455.91 470.16 484.40 498.65<br />
11.09 9.75 6.41 6.41 6.41 6.41 6.41 6.41 6.41 6.41 6.41<br />
10.39 7.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00<br />
40.69 40.02 37.28 38.09 38.94 39.83 40.77 41.76 42.79 43.88 45.02<br />
51.08 47.44 37.28 38.09 38.94 39.83 40.77 41.76 42.79 43.88 45.02<br />
1.85 1.72 1.35 1.38 1.41 1.44 1.48 1.51 1.55 1.59 1.63<br />
1.46 1.55<br />
25 26 27 28 29 30 31 32 33 34 35<br />
0.12 0.10 0.07 0.06 0.06 0.05 0.05 0.05 0.04 0.04 0.03<br />
12/12
S.No. Item Unit Oty Rate Amount<br />
1 DIVERSION TUNNEL WORK<br />
Gate (Size) MT 40 100000 40.00<br />
Embedded Parts MT 10 50,000 5.00<br />
Rope Drum Hoist (as per capacity) Set 1 6000000 60.00<br />
2 SPILLWAY STRUCTURE<br />
a Radial Gates (Size) MT 500 100000 500.00<br />
Embedded Parts (Including anchorages) MT 170 50,000 85.00<br />
Hydraulic hoist Set 3 20000000 600.00<br />
b Bulkhead Gates (Sizes) MT 170 60000 102.00<br />
Embedded Parts MT 60 30,000 18.00<br />
Gantry Crane Set 1 6000000 60.00<br />
3 INTAKE STRUCTURE<br />
a Intake Gate (Size) 4 <strong>of</strong> 4.5 x 4.5 MT 40 100000 40.00<br />
Embedded Parts for Intake Gate MT 10 50,000 5.00<br />
Rope drum hoist (as per capacity) Set 2 3000000 60.00<br />
b Bulkhead Gates (Sizes) MT 20 60,000 12.00<br />
Embedded Parts for Bulkhead Gates MT 8 50,000 4.00<br />
Gantry Crane (as per capacity) Set 1 1000000 10.00<br />
4 CLEANNING MACHINE<br />
J - <strong>Power</strong> Plant Civil Work - 8<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - HYDRO - MECHANICAL WORKS<br />
a Trash Racks and Embedded Parts MT 70 50000 35.00<br />
5 SURGE SHAFT<br />
a Gate MT 40 100000 40.00<br />
b Embedded Parts MT 10 50,000 5.00<br />
c Hoist Set 1 6000000 60.00<br />
6 Disilting Channel<br />
Gate MT 40 100000 40.00<br />
Embedded MT 10 50000 5.00<br />
Hoist/Hydraulic Set 2 3000000 60.00<br />
1846.00<br />
Say 1846.00
J-1 533 Say 533.00 Works-1 365 Say 365.00<br />
J-2 1070 Say 1070.00 2 154 Say 154.00<br />
J-3 3445 Say 3445.00 3 2245 Say 2245.00<br />
J-4 455 Say 455.00<br />
J-5 185 Say 185.00 2764<br />
J-6 945 Say 945.00<br />
J-7 133 Say 133.00<br />
J-8 1846 Say 1846.00<br />
J-9 120 Say 120.00<br />
J 8732 459.84<br />
A 229.92 2.30<br />
B 101 1.01 Say 101.00<br />
C 2764 27.64<br />
J 8732 87.32<br />
K 459.84 4.60<br />
M 0.5<br />
O 574.8 5.75<br />
P 114.96 1.15<br />
Q 872 8.72<br />
R 574.8 5.75<br />
X 287.4 2.87<br />
Y 31.3266 0.31<br />
Total I work 14742.547 0<br />
V 28.74
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Common excavtion M 3<br />
1.2 Rock excavation M 3<br />
2 Underground Excavation M 3<br />
3 Support System<br />
24500 125 30.63<br />
4500 300 13.50<br />
6700 1000 67.00<br />
3.1 Rockbolts RM 13500 400 54.00<br />
3.2 Shotcreting M 3<br />
4500 4000 180.00<br />
4 Concrete<br />
4.1 M-15 M 3<br />
4.2 M-20 M 3<br />
4.3 Cement lining M-20 M 3<br />
2000 2930 58.6<br />
700 3390 23.73<br />
650 4000 26.00<br />
5 Reinforeing Steel T 130 27000 35.10<br />
6 Miscellaneous and Ancillary Works<br />
6.1 Various miscellaneous works like drilling &<br />
grouting, wiremesh reinforcement, slope protection<br />
488.56<br />
works, othr steel works etc. 2% 9.77<br />
6.2 Instrumentation 1% 4.89<br />
6.3 Dewatering 1% 4.89<br />
6.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - INTAKE STRUCTURE<br />
Item <strong>of</strong> Work Unit<br />
J-<strong>Power</strong> Plant Civil Works-1<br />
Qty Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
workcharged establishment except on L.S. items 5% 24.43<br />
Total 532.52<br />
Say 533.00
Sl.No<br />
.<br />
1 Underground Excavation M 3<br />
2 Support System<br />
48700 1000 487.00<br />
2.1 Rockbolts RM 8150 400 32.60<br />
2.2 Shotcreting M 3<br />
5550 4000 222.00<br />
3 Concrete Lining<br />
3.1 Cement Lining M-20 M 3<br />
4 Miscellaneous and Ancillary Works<br />
4.1 Various Miscellaneous works like wiremesh/steel<br />
5550 4000 222.00<br />
963.60<br />
fibre reinforcement, drilling & grouting etc. 4% 38.54<br />
4.2 Dewatering 2% 19.27<br />
4.3 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE DESILTING CHAMBER & SILT FLUSHING TUNNEL<br />
Item <strong>of</strong> Work Unit<br />
workcharged establishment except on L.S. items 5% 48.18<br />
Total 1069.60<br />
Qty<br />
J-<strong>Power</strong> Plant Civil Works-2<br />
Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
Say 1070.00
Sl.No<br />
.<br />
1 Underground Excavation M 3<br />
2 Support System<br />
112010 1000 1120.10<br />
2.1 Rockbolts RM 58750 400 235.00<br />
2.3 Shotcreting M 3<br />
13250 4000 530.00<br />
3 Concrete Lining<br />
3.1 Cement concrete lining M-20 M 3<br />
26450 4000 1058.00<br />
4 Reinforceing Steel T 100 27000 27.00<br />
2970.10<br />
5 Miscellaneous and Ancillary Works<br />
5.1 Various Miscellaneous works like wiremesh/steel<br />
fibre reinforcement, drilling & grouting, PVC pipes<br />
for drainage, slope prolection works etc. 8% 237.61<br />
5.2 Instrumentation 1% 29.70<br />
5.3 Dewatering 2% 59.40<br />
5.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - HEAD RACE TUNNEL + INTAKE TUNNELS<br />
Item <strong>of</strong> Work<br />
J-<strong>Power</strong> Plant Civil Works-3<br />
Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
workcharged establishment except on L.S. items 5% 148.51<br />
Total 3445.32<br />
Unit<br />
Qty<br />
Say 3445.00
Sl.No<br />
.<br />
1 Underground Excavation M 3<br />
2 Support System<br />
9600 1000 96.00<br />
2.1 Rockbolts RM 5700 400 22.80<br />
2.2 Shotereting M 3<br />
1300 4000 52.00<br />
3 Concrete<br />
3.1 M-15 backfill concrete M 3<br />
2550 2930 74.72<br />
4 Penstock Steel Liners MT 240 70000 168.00<br />
5 Miscellaneous and Ancillary Works<br />
5.1 Various Miscellaneous works like drilling &<br />
& grouting, wiremesh/steel fibre reinforcement,<br />
413.52<br />
swellex anchor, etc. 3% 12.41<br />
5.2 Instrumentation 1% 4.14<br />
6.3 Dewatering 1% 4.14<br />
6.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - PRESSURE SHAFTS AND PENSTOCKS<br />
J-<strong>Power</strong> Plant Civil Works-4<br />
Item <strong>of</strong> Work Unit Qty Rate Amount (Rs.<br />
(Rs.) in Lakh)<br />
workcharged establishment except on L.S. items 5% 20.68<br />
Total 454.87<br />
Say 455.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
1.2 Rock excavation M 3<br />
2 Underground Excavation M 3<br />
4000 300 12.00<br />
46500 1000 465.00<br />
3 Support System<br />
3.1 Rockbolts RM 4000 400 16.00<br />
3.2 Shotcreting M 3<br />
900 0.00<br />
4 Concrete<br />
4.1 M20 M 3<br />
4.2 M15 M 3<br />
J-<strong>Power</strong> Plant Civil Works-6<br />
COST ESTIMATE - POWER HOUSE COMPLEX INCLUDING TRANFORMER CAVERN<br />
Item <strong>of</strong> Work Unit<br />
Qty Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
1150 3392 39.01<br />
4100 2930 120.13<br />
5 Reinforcing Steel T 550 27000 148.50<br />
6 Structural Steel for ro<strong>of</strong> trusses T 50 42000 21.00<br />
7 Stone/Brick Masonry LS 15.00<br />
836.64<br />
8 Miscellaneous<br />
8.1 Various miscellaneous works like site clearance,<br />
drilling & grouting, wiremesh/steel fibre,<br />
reinforcement, flooring, water pro<strong>of</strong>ing system<br />
swellex anchor, doors & windows,painting, lift<br />
arrangement, architectural works, other metalworks<br />
etc. 5% 41.83<br />
8.2 Instrumentation 1% 8.37<br />
8.3 Dewatering 2% 16.73<br />
8.4 Add 5% on account <strong>of</strong> contingencies and<br />
workcharged establishment except on L.S. items<br />
5% 41.83<br />
Total 945.40<br />
Say 945.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Common excavtion M 3<br />
1.2 Rock excavation M 3<br />
2 Under Ground Excavation M 3<br />
3 Support system<br />
500 125 0.63<br />
1500 300 4.50<br />
4000 1000 40.00<br />
3.1 Rock Bolling RM 2500 400 10.00<br />
3.2 Shot Creting M 3<br />
560 4000 22.40<br />
4 Concrete Lining M 3<br />
5 Miscellaneous<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
1120 4000 44.80<br />
122.33<br />
5.1 MISC. 3% 3.67<br />
5.2 Dewatering 1% 1.22<br />
5.3 Add. 5% on account <strong>of</strong> contingencies and work<br />
COST ESTIMATE - TAIL RACE TUNNEL<br />
Item <strong>of</strong> Work Unit Qty Rate<br />
(Rs.)<br />
J-<strong>Power</strong> Plant Civil Works-7<br />
Amount (Rs.<br />
in Lakh)<br />
charged establishment 5% 6.12<br />
Total 133.33<br />
Say 133.00
Sl.No<br />
.<br />
1 Cost <strong>of</strong> surveys and investigation including<br />
geological investigation, hydrological<br />
investigation, preliminary construction materials<br />
surveys, C/O access paths and roads etc. at PFR<br />
stage.<br />
2 Topographical & other surveys for dam,<br />
powerhouse, reservoir etc.<br />
3 Geological Investigation<br />
4 Drilling & Drifting<br />
5 Construction Material Survey<br />
6 Hydrological and meteorological observation<br />
7 Geophysical survey, seismological study.<br />
8 Hydraulic model studies<br />
9 Ground water studies<br />
10 Charges for preliminary consultancy & specialists<br />
11 Training <strong>of</strong> Engineers during investigation<br />
12 Instrument and equipment for S & I works<br />
13 Stationary. Writing <strong>of</strong> completion report &<br />
history <strong>of</strong> project.<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE A - PRELIMINARY<br />
Item <strong>of</strong> Work Unit<br />
Qty Rate Amount (Rs.<br />
(Rs.) in Lakh)<br />
L.S. 2% OF C & J WORKS 254.42<br />
254.42<br />
Say 254.00
Sl.No<br />
.<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
Item <strong>of</strong> Work<br />
1 Requirement <strong>of</strong> land ha 200 50,000 100.00<br />
2 Staff for demoreacation and measurement <strong>of</strong><br />
COST ESTIMATE - B - LAND<br />
Unit Qty<br />
Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
<strong>of</strong> land @ 1% <strong>of</strong> value <strong>of</strong> land 1.00<br />
Total 101.00<br />
Say 101.00
Sl.No<br />
.<br />
1 Residential Buildings<br />
1.1 Permanent residential buildings<br />
Services Charges @<br />
1.2 Temorary Buildings<br />
Servoces Charges @<br />
Total Residential Buildings<br />
Non Residential Buildings<br />
2.1 Permanent non-residential buildings<br />
2.2.<br />
Services Charges @<br />
Services Charges @<br />
Total Non-residential Buildings<br />
JADH GANGA HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - K - BUILDINGS<br />
Item <strong>of</strong> Work Unit Qty Rate Amount (Rs.<br />
(Rs.) in Lakh)<br />
L.S. 4 % OF C & J Work 508.84<br />
Grant Total ( Residential + Non-Residential) 508.84<br />
Say 509.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1,1 Rock excavation M 3<br />
2 Underground Excavation<br />
2.1 Surge shaft excavation M 3<br />
2.2 Surge shaft excavation with raise climber M 3<br />
3 Support System<br />
6750 300 20.25<br />
4000 1200 48.00<br />
3000 1500 45.00<br />
3.1 Rockbolts RM 1800 400 7.20<br />
3.3 Shotcreting M 3<br />
400 4000 16.00<br />
4 Concrete<br />
4.1 M-20 M 3<br />
5 Steel Works<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - SURGE SHAFT<br />
Item <strong>of</strong> Work Unit Qty<br />
J-<strong>Power</strong> Plant Civil Works-5<br />
Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
800 4000 32.00<br />
5.1 Deformed Reinforcement MT 50 2700 1.35<br />
169.80<br />
6 Miscellaneous and Ancillary Works<br />
6.1 Various miscellaneious works like site clearance,<br />
drilling & grouting, wire mesh reinforcement,<br />
Airvent pipes, lift arrangement, other steel works etc. 2% 3.40<br />
6.2 Instrumentation 1% 1.70<br />
6.3 Dewatering 1% 1.70<br />
6.4 Add 5% on account <strong>of</strong> contingencies and<br />
workcharged establishment except on L.S. items 5% 8.49<br />
Total 185.08<br />
Say 185.00
Sl.No<br />
.<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - Q - SPECIAL T&P<br />
Item <strong>of</strong> Work<br />
Unit Qty Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
1 Inspection and Transport Vehicles<br />
Staff Car no 4 3.75 15.00<br />
Gypsy / Jeep no 12 3.75 45.00<br />
Amulance no 2 8 16.00<br />
School / Staff Bus no 2 6.5 13.00<br />
Mini Truck no 4 5 20.00<br />
Truck 10 ton no 5 8 40.00<br />
2 Miscellaneous Equipments<br />
Crane 50 ton no 1 155 310.00<br />
Carane 18 ton no 1 75 75.00<br />
Carane 10 ton no 2 45 90.00<br />
DG sets 500 KVA no 4 25 100.00<br />
Welding set no 4 2.25 9.00<br />
Tractor Trailor no 2 18 36.00<br />
Weight Bridge-20 ton no 2 8 16.00<br />
Explosive Van 10 ton no 2 6 12.00<br />
Pump 5 HP no 20 0.2 4.00<br />
Pump 10 HP no 10 0.3 3.00<br />
Pump 50 HP no 10 1 10.00<br />
3 Workshop Equipments<br />
Lathe machine no 2 4 8.00<br />
Shaper machine no 2 1 2.00<br />
Bench Drilling machine no 2 0.7 1.40<br />
Grinder no 4 0.15 0.60<br />
Drill Steel Grinder no 2 0.75 1.50<br />
<strong>Power</strong> hacksw no 6 0.25 1.50<br />
Hydrulic jack no 2 0.5 10.00<br />
Engine repair shop no 2 0.15 8.00<br />
Auto-electrical repair shop no 2 1.25 1.00<br />
Battery charger no 2 1.00<br />
Compressor for tyre inflation no 2 0.30<br />
Gas cutting set no 6 7.50<br />
Unforeseen item no 15.00<br />
Total cost <strong>of</strong> special tools and plants 871.80<br />
Say 872.00<br />
NOTE : The project has been planned for construction through private agencies. The contractor shall arrange<br />
heavy equipments for works for which no provision has been kept under Q - Special T&P.
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Command Excavation M 3<br />
1.2 Rock excavation M 3<br />
2 Underground Excavation M 3<br />
3 Support System<br />
500 125 0.63<br />
1000 300 3.00<br />
10500 1000 105.00<br />
3.1 Rockbolts RM 5800 400 23.20<br />
3.2 Shotcreting M 3<br />
1300 4000 52.00<br />
4 Concrete<br />
4.1 Cement concrete lining M-20 M 3<br />
2600 4000 104.00<br />
5 Reinforcing Steel T 100 27000 27.00<br />
6 Miscellaneous<br />
6.1 Various miscellaneious works like wiremesh/steel fibre<br />
reinforcement,drilling & grouting PVC pipes<br />
314.83<br />
for drainage, slope protection works etc. 8% 25.19<br />
6.2 Instrumentation 1% 3.15<br />
6.3 Dewatering 2% 6.30<br />
6.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - DIVERSION TUNNEL<br />
Item <strong>of</strong> Work Unit Qty Rate<br />
(Rs.)<br />
C-Works-1<br />
Amount (Rs.<br />
in Lakh)<br />
workcharged establishment except on L.S. items 5% 15.74<br />
Total 365.20<br />
Say 365.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Common Excavation M 3<br />
2 Concrete<br />
2.1 Plum Concrete M 3<br />
2.2 M-15 M 3<br />
400 125 0.50<br />
3000 2000 60.00<br />
2000 4000 80.00<br />
3 Rock Bolting & Drilling RM 400 400 1.60<br />
4 Miscellaneous<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
142.10<br />
4.1 Various miscellaneious works 0.5% 0.71<br />
4.2 Dewatering 3% 4.26<br />
4.3 Add 5% on account <strong>of</strong> contingencies and 5% 7.11<br />
workcharged establishment except on L.S. items<br />
COST ESTIMATE - COFFER DAM<br />
Item <strong>of</strong> Work Unit Qty Rate<br />
(Rs.)<br />
C-Works-2<br />
Amount (Rs.<br />
in Lakh)<br />
Total 154.18<br />
Say 154.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Rock Excavation M 3<br />
2 Support System<br />
20000 300 60.00<br />
2.1 Rockbolts RM 3700 400 14.80<br />
2.2 Shotcreting M 3<br />
500 4000 20.00<br />
3 Concrete<br />
3.1 M 15 M 3<br />
3.2 M 20 M 3<br />
9200 2930 269.56<br />
23000 3392 780.16<br />
4 Reinforcing Steel MT 3250 27000 877.50<br />
5 Miscellaneous<br />
5.1 Various miscellaneious works like wiremesh/steel fibre<br />
reinforcement,drilling & grouting PVC pipes, other<br />
steel works, slope protection works, elevator, road<br />
2022.02<br />
works, archktectural works for dam etc. 3% 60.66<br />
5.2 Instrumentation 1% 20.22<br />
5.3 Dewatering 2% 40.44<br />
5.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - CONCRETE DAM<br />
Item <strong>of</strong> Work Unit Qty<br />
Rate<br />
(Rs.)<br />
C-Works-3<br />
Amount (Rs.<br />
in Lakh)<br />
workcharged establishment except on L.S. items 5% 101.10<br />
Total 2244.44<br />
Say 2245.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Common excavation M 3<br />
1.2 Rock excavation M 3<br />
2 Underground Excavation<br />
2.1 Excavation <strong>of</strong> adits M 3<br />
3 Supports Systems<br />
500 125 0.63<br />
1000 300 3.00<br />
2600 1000 26.00<br />
3.1 Rockbolts RM 1900 400 7.60<br />
3.2 Shotcreting M 3<br />
450 4000 18.00<br />
4 Concrete<br />
4.1 Cement Concrete Lining M-20 M 3<br />
950 4000 38.00<br />
5 Reinforcing Steel 50 27000 13.50<br />
6 Miscellaneous<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - ADITS<br />
6.1 Various miscellaneous works like drilling & grouting,<br />
wiremesh reinforcement, masonery works, PVC<br />
106.73<br />
pipes for drainage etc. 4% 4.27<br />
Instrumentation 1% 1.07<br />
6.2 Dewatering 2% 2.13<br />
6.3 Add 5% on account <strong>of</strong> contingencies and 5% 5.34<br />
workcharged establishment except on L.S. items<br />
J - POWER PLANT CIVIL WORKS - 9<br />
Item <strong>of</strong> work Unit Qty Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
Total 119.53<br />
Say 120.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Common excavtion M 3<br />
1.2 Rock excavation M 3<br />
2 Underground Excavation M 3<br />
3 Support System<br />
24500 125 30.63<br />
4500 300 13.50<br />
6700 1000 67.00<br />
3.1 Rockbolts RM 13500 400 54.00<br />
3.2 Shotcreting M 3<br />
4500 4000 180.00<br />
4 Concrete<br />
4.1 M-15 M 3<br />
4.2 M-20 M 3<br />
4.3 Cement lining M-20 M 3<br />
2000 2930 58.6<br />
700 3390 23.73<br />
650 4000 26.00<br />
5 Reinforeing Steel T 130 27000 35.10<br />
6 Miscellaneous and Ancillary Works<br />
6.1 Various miscellaneous works like drilling &<br />
grouting, wiremesh reinforcement, slope protection<br />
488.56<br />
works, othr steel works etc. 2% 9.77<br />
6.2 Instrumentation 1% 4.89<br />
6.3 Dewatering 1% 4.89<br />
6.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - INTAKE STRUCTURE<br />
Item <strong>of</strong> Work Unit<br />
J-<strong>Power</strong> Plant Civil Works-1<br />
Qty Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
workcharged establishment except on L.S. items 5% 24.43<br />
Total 532.52<br />
Say 533.00
Sl.No<br />
.<br />
1 Underground Excavation M 3<br />
2 Support System<br />
48700 1000 487.00<br />
2.1 Rockbolts RM 8150 400 32.60<br />
2.2 Shotcreting M 3<br />
5550 4000 222.00<br />
3 Concrete Lining<br />
3.1 Cement Lining M-20 M 3<br />
4 Miscellaneous and Ancillary Works<br />
4.1 Various Miscellaneous works like wiremesh/steel<br />
5550 4000 222.00<br />
963.60<br />
fibre reinforcement, drilling & grouting etc. 4% 38.54<br />
4.2 Dewatering 2% 19.27<br />
4.3 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE DESILTING CHAMBER & SILT FLUSHING TUNNEL<br />
Item <strong>of</strong> Work Unit<br />
workcharged establishment except on L.S. items 5% 48.18<br />
Total 1069.60<br />
Qty<br />
J-<strong>Power</strong> Plant Civil Works-2<br />
Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
Say 1070.00
Sl.No<br />
.<br />
1 Underground Excavation M 3<br />
2 Support System<br />
112010 1000 1120.10<br />
2.1 Rockbolts RM 58750 400 235.00<br />
2.3 Shotcreting M 3<br />
13250 4000 530.00<br />
3 Concrete Lining<br />
3.1 Cement concrete lining M-20 M 3<br />
26450 4000 1058.00<br />
4 Reinforceing Steel T 100 27000 27.00<br />
2970.10<br />
5 Miscellaneous and Ancillary Works<br />
5.1 Various Miscellaneous works like wiremesh/steel<br />
fibre reinforcement, drilling & grouting, PVC pipes<br />
for drainage, slope prolection works etc. 8% 237.61<br />
5.2 Instrumentation 1% 29.70<br />
5.3 Dewatering 2% 59.40<br />
5.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - HEAD RACE TUNNEL + INTAKE TUNNELS<br />
Item <strong>of</strong> Work<br />
J-<strong>Power</strong> Plant Civil Works-3<br />
Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
workcharged establishment except on L.S. items 5% 148.51<br />
Total 3445.32<br />
Unit<br />
Qty<br />
Say 3445.00
Sl.No<br />
.<br />
1 Underground Excavation M 3<br />
2 Support System<br />
9600 1000 96.00<br />
2.1 Rockbolts RM 5700 400 22.80<br />
2.2 Shotereting M 3<br />
1300 4000 52.00<br />
3 Concrete<br />
3.1 M-15 backfill concrete M 3<br />
2550 2930 74.72<br />
4 Penstock Steel Liners MT 240 70000 168.00<br />
5 Miscellaneous and Ancillary Works<br />
5.1 Various Miscellaneous works like drilling &<br />
& grouting, wiremesh/steel fibre reinforcement,<br />
413.52<br />
swellex anchor, etc. 3% 12.41<br />
5.2 Instrumentation 1% 4.14<br />
6.3 Dewatering 1% 4.14<br />
6.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - PRESSURE SHAFTS AND PENSTOCKS<br />
J-<strong>Power</strong> Plant Civil Works-4<br />
Item <strong>of</strong> Work Unit Qty Rate Amount (Rs.<br />
(Rs.) in Lakh)<br />
workcharged establishment except on L.S. items 5% 20.68<br />
Total 454.87<br />
Say 455.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
1.2 Rock excavation M 3<br />
2 Underground Excavation M 3<br />
4000 300 12.00<br />
46500 1000 465.00<br />
3 Support System<br />
3.1 Rockbolts RM 4000 400 16.00<br />
3.2 Shotcreting M 3<br />
900 0.00<br />
4 Concrete<br />
4.1 M20 M 3<br />
4.2 M15 M 3<br />
J-<strong>Power</strong> Plant Civil Works-6<br />
COST ESTIMATE - POWER HOUSE COMPLEX INCLUDING TRANFORMER CAVERN<br />
Item <strong>of</strong> Work Unit<br />
Qty Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
1150 3392 39.01<br />
4100 2930 120.13<br />
5 Reinforcing Steel T 550 27000 148.50<br />
6 Structural Steel for ro<strong>of</strong> trusses T 50 42000 21.00<br />
7 Stone/Brick Masonry LS 15.00<br />
836.64<br />
8 Miscellaneous<br />
8.1 Various miscellaneous works like site clearance,<br />
drilling & grouting, wiremesh/steel fibre,<br />
reinforcement, flooring, water pro<strong>of</strong>ing system<br />
swellex anchor, doors & windows,painting, lift<br />
arrangement, architectural works, other metalworks<br />
etc. 5% 41.83<br />
8.2 Instrumentation 1% 8.37<br />
8.3 Dewatering 2% 16.73<br />
8.4 Add 5% on account <strong>of</strong> contingencies and<br />
workcharged establishment except on L.S. items<br />
5% 41.83<br />
Total 945.40<br />
Say 945.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Common excavtion M 3<br />
1.2 Rock excavation M 3<br />
2 Under Ground Excavation M 3<br />
3 Support system<br />
500 125 0.63<br />
1500 300 4.50<br />
4000 1000 40.00<br />
3.1 Rock Bolling RM 2500 400 10.00<br />
3.2 Shot Creting M 3<br />
560 4000 22.40<br />
4 Concrete Lining M 3<br />
5 Miscellaneous<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
1120 4000 44.80<br />
122.33<br />
5.1 MISC. 3% 3.67<br />
5.2 Dewatering 1% 1.22<br />
5.3 Add. 5% on account <strong>of</strong> contingencies and work<br />
COST ESTIMATE - TAIL RACE TUNNEL<br />
Item <strong>of</strong> Work Unit Qty Rate<br />
(Rs.)<br />
J-<strong>Power</strong> Plant Civil Works-7<br />
Amount (Rs.<br />
in Lakh)<br />
charged establishment 5% 6.12<br />
Total 133.33<br />
Say 133.00
Sl.No<br />
.<br />
1 Cost <strong>of</strong> surveys and investigation including<br />
geological investigation, hydrological<br />
investigation, preliminary construction materials<br />
surveys, C/O access paths and roads etc. at PFR<br />
stage.<br />
2 Topographical & other surveys for dam,<br />
powerhouse, reservoir etc.<br />
3 Geological Investigation<br />
4 Drilling & Drifting<br />
5 Construction Material Survey<br />
6 Hydrological and meteorological observation<br />
7 Geophysical survey, seismological study.<br />
8 Hydraulic model studies<br />
9 Ground water studies<br />
10 Charges for preliminary consultancy & specialists<br />
11 Training <strong>of</strong> Engineers during investigation<br />
12 Instrument and equipment for S & I works<br />
13 Stationary. Writing <strong>of</strong> completion report &<br />
history <strong>of</strong> project.<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE A - PRELIMINARY<br />
Item <strong>of</strong> Work Unit<br />
Qty Rate Amount (Rs.<br />
(Rs.) in Lakh)<br />
L.S. 2% OF C & J WORKS 254.42<br />
254.42<br />
Say 254.00
Sl.No<br />
.<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
Item <strong>of</strong> Work<br />
1 Requirement <strong>of</strong> land ha 200 50,000 100.00<br />
2 Staff for demoreacation and measurement <strong>of</strong><br />
COST ESTIMATE - B - LAND<br />
Unit Qty<br />
Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
<strong>of</strong> land @ 1% <strong>of</strong> value <strong>of</strong> land 1.00<br />
Total 101.00<br />
Say 101.00
Sl.No<br />
.<br />
1 Residential Buildings<br />
1.1 Permanent residential buildings<br />
Services Charges @<br />
1.2 Temorary Buildings<br />
Servoces Charges @<br />
Total Residential Buildings<br />
Non Residential Buildings<br />
2.1 Permanent non-residential buildings<br />
2.2.<br />
Services Charges @<br />
Services Charges @<br />
Total Non-residential Buildings<br />
JADH GANGA HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - K - BUILDINGS<br />
Item <strong>of</strong> Work Unit Qty Rate Amount (Rs.<br />
(Rs.) in Lakh)<br />
L.S. 4 % OF C & J Work 508.84<br />
Grant Total ( Residential + Non-Residential) 508.84<br />
Say 509.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1,1 Rock excavation M 3<br />
2 Underground Excavation<br />
2.1 Surge shaft excavation M 3<br />
2.2 Surge shaft excavation with raise climber M 3<br />
3 Support System<br />
6750 300 20.25<br />
4000 1200 48.00<br />
3000 1500 45.00<br />
3.1 Rockbolts RM 1800 400 7.20<br />
3.3 Shotcreting M 3<br />
400 4000 16.00<br />
4 Concrete<br />
4.1 M-20 M 3<br />
5 Steel Works<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - SURGE SHAFT<br />
Item <strong>of</strong> Work Unit Qty<br />
J-<strong>Power</strong> Plant Civil Works-5<br />
Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
800 4000 32.00<br />
5.1 Deformed Reinforcement MT 50 2700 1.35<br />
169.80<br />
6 Miscellaneous and Ancillary Works<br />
6.1 Various miscellaneious works like site clearance,<br />
drilling & grouting, wire mesh reinforcement,<br />
Airvent pipes, lift arrangement, other steel works etc. 2% 3.40<br />
6.2 Instrumentation 1% 1.70<br />
6.3 Dewatering 1% 1.70<br />
6.4 Add 5% on account <strong>of</strong> contingencies and<br />
workcharged establishment except on L.S. items 5% 8.49<br />
Total 185.08<br />
Say 185.00
Sl.No<br />
.<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - Q - SPECIAL T&P<br />
Item <strong>of</strong> Work<br />
Unit Qty Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
1 Inspection and Transport Vehicles<br />
Staff Car no 4 3.75 15.00<br />
Gypsy / Jeep no 12 3.75 45.00<br />
Amulance no 2 8 16.00<br />
School / Staff Bus no 2 6.5 13.00<br />
Mini Truck no 4 5 20.00<br />
Truck 10 ton no 5 8 40.00<br />
2 Miscellaneous Equipments<br />
Crane 50 ton no 1 155 310.00<br />
Carane 18 ton no 1 75 75.00<br />
Carane 10 ton no 2 45 90.00<br />
DG sets 500 KVA no 4 25 100.00<br />
Welding set no 4 2.25 9.00<br />
Tractor Trailor no 2 18 36.00<br />
Weight Bridge-20 ton no 2 8 16.00<br />
Explosive Van 10 ton no 2 6 12.00<br />
Pump 5 HP no 20 0.2 4.00<br />
Pump 10 HP no 10 0.3 3.00<br />
Pump 50 HP no 10 1 10.00<br />
3 Workshop Equipments<br />
Lathe machine no 2 4 8.00<br />
Shaper machine no 2 1 2.00<br />
Bench Drilling machine no 2 0.7 1.40<br />
Grinder no 4 0.15 0.60<br />
Drill Steel Grinder no 2 0.75 1.50<br />
<strong>Power</strong> hacksw no 6 0.25 1.50<br />
Hydrulic jack no 2 0.5 10.00<br />
Engine repair shop no 2 0.15 8.00<br />
Auto-electrical repair shop no 2 1.25 1.00<br />
Battery charger no 2 1.00<br />
Compressor for tyre inflation no 2 0.30<br />
Gas cutting set no 6 7.50<br />
Unforeseen item no 15.00<br />
Total cost <strong>of</strong> special tools and plants 871.80<br />
Say 872.00<br />
NOTE : The project has been planned for construction through private agencies. The contractor shall arrange<br />
heavy equipments for works for which no provision has been kept under Q - Special T&P.
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Command Excavation M 3<br />
1.2 Rock excavation M 3<br />
2 Underground Excavation M 3<br />
3 Support System<br />
500 125 0.63<br />
1000 300 3.00<br />
10500 1000 105.00<br />
3.1 Rockbolts RM 5800 400 23.20<br />
3.2 Shotcreting M 3<br />
1300 4000 52.00<br />
4 Concrete<br />
4.1 Cement concrete lining M-20 M 3<br />
2600 4000 104.00<br />
5 Reinforcing Steel T 100 27000 27.00<br />
6 Miscellaneous<br />
6.1 Various miscellaneious works like wiremesh/steel fibre<br />
reinforcement,drilling & grouting PVC pipes<br />
314.83<br />
for drainage, slope protection works etc. 8% 25.19<br />
6.2 Instrumentation 1% 3.15<br />
6.3 Dewatering 2% 6.30<br />
6.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - DIVERSION TUNNEL<br />
Item <strong>of</strong> Work Unit Qty Rate<br />
(Rs.)<br />
C-Works-1<br />
Amount (Rs.<br />
in Lakh)<br />
workcharged establishment except on L.S. items 5% 15.74<br />
Total 365.20<br />
Say 365.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Common Excavation M 3<br />
2 Concrete<br />
2.1 Plum Concrete M 3<br />
2.2 M-15 M 3<br />
400 125 0.50<br />
3000 2000 60.00<br />
2000 4000 80.00<br />
3 Rock Bolting & Drilling RM 400 400 1.60<br />
4 Miscellaneous<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
142.10<br />
4.1 Various miscellaneious works 0.5% 0.71<br />
4.2 Dewatering 3% 4.26<br />
4.3 Add 5% on account <strong>of</strong> contingencies and 5% 7.11<br />
workcharged establishment except on L.S. items<br />
COST ESTIMATE - COFFER DAM<br />
Item <strong>of</strong> Work Unit Qty Rate<br />
(Rs.)<br />
C-Works-2<br />
Amount (Rs.<br />
in Lakh)<br />
Total 154.18<br />
Say 154.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Rock Excavation M 3<br />
2 Support System<br />
20000 300 60.00<br />
2.1 Rockbolts RM 3700 400 14.80<br />
2.2 Shotcreting M 3<br />
500 4000 20.00<br />
3 Concrete<br />
3.1 M 15 M 3<br />
3.2 M 20 M 3<br />
9200 2930 269.56<br />
23000 3392 780.16<br />
4 Reinforcing Steel MT 3250 27000 877.50<br />
5 Miscellaneous<br />
5.1 Various miscellaneious works like wiremesh/steel fibre<br />
reinforcement,drilling & grouting PVC pipes, other<br />
steel works, slope protection works, elevator, road<br />
2022.02<br />
works, archktectural works for dam etc. 3% 60.66<br />
5.2 Instrumentation 1% 20.22<br />
5.3 Dewatering 2% 40.44<br />
5.4 Add 5% on account <strong>of</strong> contingencies and<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - CONCRETE DAM<br />
Item <strong>of</strong> Work Unit Qty<br />
Rate<br />
(Rs.)<br />
C-Works-3<br />
Amount (Rs.<br />
in Lakh)<br />
workcharged establishment except on L.S. items 5% 101.10<br />
Total 2244.44<br />
Say 2245.00
Sl.No<br />
.<br />
1 Surface Excavation<br />
1.1 Common excavation M 3<br />
1.2 Rock excavation M 3<br />
2 Underground Excavation<br />
2.1 Excavation <strong>of</strong> adits M 3<br />
3 Supports Systems<br />
500 125 0.63<br />
1000 300 3.00<br />
2600 1000 26.00<br />
3.1 Rockbolts RM 1900 400 7.60<br />
3.2 Shotcreting M 3<br />
450 4000 18.00<br />
4 Concrete<br />
4.1 Cement Concrete Lining M-20 M 3<br />
950 4000 38.00<br />
5 Reinforcing Steel 50 27000 13.50<br />
6 Miscellaneous<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
COST ESTIMATE - ADITS<br />
6.1 Various miscellaneous works like drilling & grouting,<br />
wiremesh reinforcement, masonery works, PVC<br />
106.73<br />
pipes for drainage etc. 4% 4.27<br />
Instrumentation 1% 1.07<br />
6.2 Dewatering 2% 2.13<br />
6.3 Add 5% on account <strong>of</strong> contingencies and 5% 5.34<br />
workcharged establishment except on L.S. items<br />
J - POWER PLANT CIVIL WORKS - 9<br />
Item <strong>of</strong> work Unit Qty Rate<br />
(Rs.)<br />
Amount (Rs.<br />
in Lakh)<br />
Total 119.53<br />
Say 120.00
Annexure 12.1<br />
AMOUNT<br />
S.No. DESCRIPTION (Rs.in Crores)<br />
(June 2003)<br />
A CIVIL WORKS<br />
1 DIRECT CHARGES<br />
I - Works<br />
BHARO GHATI HYDRO ELECTRIC PROJECT<br />
ABSTRACT OF COST OF WORKS<br />
A - Preliminary 2.30<br />
B - Land 1.01<br />
C - Works 27.64<br />
J - <strong>Power</strong> Plant Civil Works 87.32<br />
K - Buildings 4.60<br />
M - Plantation 0.50<br />
O - Miscellaneous 5.75<br />
P - Maintenance 1.15<br />
Q - Special Tools & Plants 8.72<br />
R - Communication 5.75<br />
X - Environment & Ecology 2.87<br />
Y - Losses on Stock (-) 0.31<br />
TOTAL OF I - WORKS 147.30<br />
II - Establishhment @ 8% <strong>of</strong> cost <strong>of</strong> I-works less B-Land 10.77<br />
III - Tools and Plants @ 1% <strong>of</strong> cost <strong>of</strong> I - Works 1.47<br />
IV- suspense 0.00<br />
V - Receipt & Recoveries (-) .013<br />
Total Direct Charges 159.53<br />
2 Indirect charges<br />
a) Capital value <strong>of</strong> Abatement <strong>of</strong> land Revenue, 5% <strong>of</strong> B Land 0.05<br />
b) Audit and Account Charges @ 1% <strong>of</strong> cost <strong>of</strong> I-Works. 1.47<br />
Total indirect Charges 1.52<br />
Total <strong>of</strong> Direct & Indirect Charges. 161.05<br />
Abstract :<br />
A Civil Works 161.05<br />
B Electrical works 107.29<br />
Total cost 268.34<br />
Say 268.00
0.31<br />
0.01308
BHAIRONGHATI HYDEL SCHEME<br />
AREA CAPACITY CURVE<br />
ELEVATION CAPACITY<br />
(M) (MCUM)<br />
MDDL 2630 1.03<br />
2631 1.082<br />
2631.5 1.107<br />
2632 1.133<br />
2632.5 1.159<br />
2633 1.185<br />
2633.5 1.21<br />
2634 1.236<br />
2635 1.288<br />
2635.5 1.313<br />
2636 1.339<br />
2637 1.391<br />
2637.5 1.416<br />
2638 1.442<br />
2639 1.494<br />
2639.5 1.519<br />
2640 1.545<br />
FRL 2642 1.883<br />
ANNEXURE-7.1
S. NO. INST.<br />
CAP.(MW)<br />
ANNUAL<br />
ENERGY<br />
BHAIRONGHATI HYDEL SCHEME<br />
INCREMENTAL ENERGY BENEFITS<br />
( 90% DEPENDABLE YEAR )<br />
ANNUAL L.F<br />
(%)<br />
LEAN<br />
FLOW L.F<br />
ANNEX - 7.3<br />
KWh/ KW d (KWh)/ d<br />
(KW)<br />
GEN (GWh)<br />
(%)<br />
1 30 186.81 71.09 37.09 6227.14 -<br />
2 35 204.20 66.60 31.79 5834.23 3476.78<br />
3 40 221.36 63.17 27.82 5533.95 3432.00<br />
4 45 237.58 60.27 24.73 5279.58 3244.63<br />
5 50 252.22 57.58 22.25 5044.43 2928.00<br />
6 55 266.30 55.27 20.23 4841.83 2815.89<br />
7 60 279.74 53.22 18.54 4662.35 2688.00<br />
8 65 293.18 51.49 17.12 4510.47 2688.00<br />
9 70 306.22 49.94 15.90 4374.56 2607.68<br />
10 75 318.08 48.41 14.84 4241.06 2372.01<br />
11 80 329.12 46.96 13.91 4113.99 2208.00<br />
d (kWh) / d (kW)<br />
4000<br />
3500<br />
3000<br />
2500<br />
2000<br />
1500<br />
1000<br />
500<br />
0<br />
BHAIRONGHATI HYDEL SCHEME<br />
30 35 40 45 50 55 60 65 70 75 80 85 90<br />
INSTALLED CAPACITY (MW)
BHAIRONGHATI HYDEL SCHEME<br />
POWER POTENTIAL WITH DIFFERENT INSTALLED CAPACITY IN A 90% DEPENDABLE YEAR<br />
FRL 2642 m GROSS HEAD 124.00 m GEN. EFF 98 %<br />
MDDL 2630 m WC LOSSES 15.1 m TUR. EFF. 93.5 %<br />
TWL 2514 m NET HEAD 108.90 m<br />
ANNEX - 7.2<br />
MONTH INFLOWS POWER UNRESTRICTEINSTALLED<br />
CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP.<br />
POTENTIALENERGY 30 MW 35 MW 40 MW 45 MW 50 MW 55 MW 60 MW 65 MW 70 MW 75 MW 80 MW<br />
POWER ENERGYPOWER ENERGY POWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGY<br />
(CUMECS) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh)<br />
Jun 75 73.42 17.62 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 73.42 17.62 73.42 17.62<br />
98.7 96.62 23.19 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
126.6 123.93 29.74 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
Jul 106.5 104.25 25.02 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
126.9 124.22 29.81 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
173.5 169.84 44.84 30.00 7.92 35.00 9.24 40.00 10.56 45.00 11.88 50.00 13.20 55.00 14.52 60.00 15.84 65.00 17.16 70.00 18.48 75.00 19.80 80.00 21.12<br />
Aug 139.3 136.36 32.73 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
145.3 142.23 34.14 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
121.8 119.23 31.48 30.00 7.92 35.00 9.24 40.00 10.56 45.00 11.88 50.00 13.20 55.00 14.52 60.00 15.84 65.00 17.16 70.00 18.48 75.00 19.80 80.00 21.12<br />
Sep 88.7 86.83 20.84 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
69.8 68.33 16.40 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 68.33 16.40 68.33 16.40 68.33 16.40<br />
53.8 52.66 12.64 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 52.66 12.64 52.66 12.64 52.66 12.64 52.66 12.64 52.66 12.64 52.66 12.64<br />
Oct 42.5 41.60 9.98 30.00 7.20 35.00 8.40 40.00 9.60 41.60 9.98 41.60 9.98 41.60 9.98 41.60 9.98 41.60 9.98 41.60 9.98 41.60 9.98 41.60 9.98<br />
28.5 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70 27.90 6.70<br />
27.9 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21 27.31 7.21<br />
Nov 24 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64 23.49 5.64<br />
20.9 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91 20.46 4.91<br />
18 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23 17.62 4.23<br />
Dec 12.7 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98 12.43 2.98<br />
12.1 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84 11.84 2.84<br />
10.3 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66 10.08 2.66<br />
Jan 12.9 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03 12.63 3.03<br />
12.3 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89 12.04 2.89<br />
12.5 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23 12.24 3.23<br />
Feb 12.2 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87 11.94 2.87<br />
11 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58 10.77 2.58<br />
10.3 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94 10.08 1.94<br />
Mar 10.4 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44<br />
10 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35 9.79 2.35<br />
10.7 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77 10.47 2.77<br />
Apr 11.9 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80 11.65 2.80<br />
10.4 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44 10.18 2.44<br />
16.9 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97 16.54 3.97<br />
May 26.3 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18 25.74 6.18<br />
31.6 30.93 7.42 30.00 7.20 30.93 7.42 30.93 7.42 30.93 7.42 30.93 7.42 30.93 7.42 30.93 7.42 30.93 7.42 30.93 7.42 30.93 7.42 30.93 7.42<br />
45.5 44.54 11.76 30.00 7.92 35.00 9.24 40.00 10.56 44.54 11.76 44.54 11.76 44.54 11.76 44.54 11.76 44.54 11.76 44.54 11.76 44.54 11.76 44.54 11.76<br />
Total energy (GWh) 424.26 186.81 204.20 221.36 237.58 252.22 266.30 279.74 293.18 306.22 318.08 329.12<br />
Lean Period <strong>Power</strong> (MWc) 11.13 11.13 11.13 11.13 11.13 11.13 11.13 11.13 11.13 11.13 11.13<br />
(Jan. - Mar. )<br />
Incr. Energy(GWh) - 17.38 17.16 16.22 14.64 14.08 13.44 13.44 13.04 11.86 11.04<br />
Incr. Cap.(MW) - 5 5 5 5 5 5 5 5 5 5<br />
Incr. Energy/Incr. <strong>Power</strong> (kWh/kW) - 3476.78 3432.00 3244.63 2928.00 2815.89 2688.00 2688.00 2607.68 2372.01 2208.00
BHAIRONGHATI HYDEL SCHEME<br />
POWER POTENTIAL WITH DIFFERENT INSTALLED CAPACITY IN A 50% DEPENDABLE YEAR<br />
FRL 2642 m GROSS HEAD 124.00 m GEN. EF 98 %<br />
MDDL 2630 m WC LOSSES 15.1 m TUR. EFF 93.5 %<br />
TWL 2514 m NET HEAD 108.90 m<br />
MONTH INFLOWS POWER UNRESTRICTEINSTALLED<br />
CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP. INSTALLED CAP.<br />
POTENTIALENERGY 30 MW 35 MW 40 MW 45 MW 50 MW 55 MW 60 MW 65 MW 70 MW 75 MW 80 MW<br />
POWER ENERGYPOWER ENERGY POWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGYPOWER ENERGY<br />
(CUMECS) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh) (MWc) (GWh)<br />
Jun 138.5 135.58 32.54 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
183.9 180.02 43.20 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
222.3 217.61 52.23 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
Jul 196.3 192.16 46.12 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
241.5 236.40 56.74 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
254.3 248.93 65.72 30.00 7.92 35.00 9.24 40.00 10.56 45.00 11.88 50.00 13.20 55.00 14.52 60.00 15.84 65.00 17.16 70.00 18.48 75.00 19.80 80.00 21.12<br />
Aug 253.3 247.95 59.51 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
237 232.00 55.68 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
198.2 194.02 51.22 30.00 7.92 35.00 9.24 40.00 10.56 45.00 11.88 50.00 13.20 55.00 14.52 60.00 15.84 65.00 17.16 70.00 18.48 75.00 19.80 80.00 21.12<br />
Sep 162.4 158.97 38.15 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
125.5 122.85 29.48 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
87.1 85.26 20.46 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 65.00 15.60 70.00 16.80 75.00 18.00 80.00 19.20<br />
Oct 66 64.61 15.51 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 60.00 14.40 64.61 15.51 64.61 15.51 64.61 15.51 64.61 15.51<br />
47.5 46.50 11.16 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 46.50 11.16 46.50 11.16 46.50 11.16 46.50 11.16 46.50 11.16 46.50 11.16 46.50 11.16<br />
44 43.07 11.37 30.00 7.92 35.00 9.24 40.00 10.56 43.07 11.37 43.07 11.37 43.07 11.37 43.07 11.37 43.07 11.37 43.07 11.37 43.07 11.37 43.07 11.37<br />
Nov 39.9 39.06 9.37 30.00 7.20 35.00 8.40 39.06 9.37 39.06 9.37 39.06 9.37 39.06 9.37 39.06 9.37 39.06 9.37 39.06 9.37 39.06 9.37 39.06 9.37<br />
32.8 32.11 7.71 30.00 7.20 32.11 7.71 32.11 7.71 32.11 7.71 32.11 7.71 32.11 7.71 32.11 7.71 32.11 7.71 32.11 7.71 32.11 7.71 32.11 7.71<br />
27.5 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46 26.92 6.46<br />
Dec 20.4 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79 19.97 4.79<br />
19.5 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58 19.09 4.58<br />
18.8 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86 18.40 4.86<br />
Jan 19.6 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60<br />
19.6 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60 19.19 4.60<br />
19.1 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94 18.70 4.94<br />
Feb 18.5 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35 18.11 4.35<br />
17.9 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21 17.52 4.21<br />
17.4 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27 17.03 3.27<br />
Mar 17.1 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02 16.74 4.02<br />
17.5 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11 17.13 4.11<br />
18.9 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88 18.50 4.88<br />
Apr 20.3 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77 19.87 4.77<br />
25.6 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01 25.06 6.01<br />
33 32.30 7.75 30.00 7.20 32.30 7.75 32.30 7.75 32.30 7.75 32.30 7.75 32.30 7.75 32.30 7.75 32.30 7.75 32.30 7.75 32.30 7.75 32.30 7.75<br />
May 45.2 44.25 10.62 30.00 7.20 35.00 8.40 40.00 9.60 44.25 10.62 44.25 10.62 44.25 10.62 44.25 10.62 44.25 10.62 44.25 10.62 44.25 10.62 44.25 10.62<br />
60.1 58.83 14.12 30.00 7.20 35.00 8.40 40.00 9.60 45.00 10.80 50.00 12.00 55.00 13.20 58.83 14.12 58.83 14.12 58.83 14.12 58.83 14.12 58.83 14.12<br />
79.6 77.92 20.57 30.00 7.92 35.00 9.24 40.00 10.56 45.00 11.88 50.00 13.20 55.00 14.52 60.00 15.84 65.00 17.16 70.00 18.48 75.00 19.80 77.92 20.57<br />
Total energy (GWh) 729.68 224.54 248.88 271.93 293.32 312.04 330.40 348.48 365.54 381.50 397.46 412.87<br />
Lean Period <strong>Power</strong> (MWc) 18.01 18.01 18.01 18.01 18.01 18.01 18.01 18.01 18.01 18.01 18.01<br />
(Jan. - Mar. )<br />
Incr. Energy(GWh) - 24.34 23.05 21.39 18.72 18.36 18.08 17.07 15.96 15.96 15.41<br />
Incr. Cap.(MW) - 5 5 5 5 5 5 5 5 5 5<br />
Incr. Energy/Incr. <strong>Power</strong> (kWh/kW) - 4867.73 4610.77 4277.96 3743.87 3672.00 3615.91 3413.13 3192.00 3192.00 3082.16<br />
ANNEX - 7.4
BHAIRONGHATI HYDEL SCHEME<br />
CAPACITY AND ENERGY BENEFITS IN<br />
90% DEPENDABLE YEAR<br />
ANNEX - 7.5<br />
PERIOD INFLOWS OUTPUT IC = 65 MW DESIGN ENERGY<br />
(Cumecs) MWc GWh MWc GWh<br />
JUN - 1 75.00 65.00 15.60 61.75 14.82<br />
JUN - 2 98.70 65.00 15.60 61.75 14.82<br />
JUN - 3 126.60 65.00 15.60 61.75 14.82<br />
JUL - 1 106.50 65.00 15.60 61.75 14.82<br />
JUL - 2 126.90 65.00 15.60 61.75 14.82<br />
JUL - 3 173.50 65.00 17.16 61.75 14.82<br />
AUG - 1 139.30 65.00 15.60 61.75 14.82<br />
AUG - 2 145.30 65.00 15.60 61.75 14.82<br />
AUG - 3 121.80 65.00 17.16 61.75 14.82<br />
SEP - 1 88.70 65.00 15.60 61.75 14.82<br />
SEP - 2 69.80 65.00 15.60 61.75 14.82<br />
SEP - 3 53.80 52.66 12.64 52.66 12.64<br />
OCT - 1 42.50 41.60 9.98 41.60 9.98<br />
OCT - 2 28.50 27.90 6.70 27.90 6.70<br />
OCT - 3 27.90 27.31 7.21 27.31 6.55<br />
NOV - 1 24.00 23.49 5.64 23.49 5.64<br />
NOV - 2 20.90 20.46 4.91 20.46 4.91<br />
NOV - 3 18.00 17.62 4.23 17.62 4.23<br />
DEC - 1 12.70 12.43 2.98 12.43 2.98<br />
DEC - 2 12.10 11.84 2.84 11.84 2.84<br />
DEC - 3 10.30 10.08 2.66 10.08 2.42<br />
JAN - 1 12.90 12.63 3.03 12.63 3.03<br />
JAN - 2 12.30 12.04 2.89 12.04 2.89<br />
JAN - 3 12.50 12.24 3.23 12.24 2.94<br />
FEB - 1 12.20 11.94 2.87 11.94 2.87<br />
FEB - 2 11.00 10.77 2.58 10.77 2.58<br />
FEB - 3 10.30 10.08 1.94 10.08 2.42<br />
MAR - 1 10.40 10.18 2.44 10.18 2.44<br />
MAR - 2 10.00 9.79 2.35 9.79 2.35<br />
MAR - 3 10.70 10.47 2.77 10.47 2.51<br />
APR - 1 11.90 11.65 2.80 11.65 2.80<br />
APR - 2 10.40 10.18 2.44 10.18 2.44<br />
APR - 3 16.90 16.54 3.97 16.54 3.97<br />
MAY - 1 26.30 25.74 6.18 25.74 6.18<br />
MAY - 2 31.60 30.93 7.42 30.93 7.42<br />
MAY - 3 45.50 44.54 11.76 44.54 10.69<br />
TOTAL 1560.26 293.18 279.45<br />
(Mcum)