PROJECT TITLE:<br />
<strong>ANNEX</strong> 1<br />
<strong>TERMS</strong> <strong>OF</strong> <strong>REFERENCE</strong><br />
Barangay Electrification of Autonomous Region of Muslim Mindanao and Region IX under<br />
Winrock/Amore Project.<br />
PROJECT TYPE:<br />
Electrification of 56 Barangays using Solar Home Systems<br />
Project Objectives:<br />
This project is designed to provide support for community electrification projects in Muslim<br />
Mindanao, focusing on assistance by the private sector in community or social preparation. This<br />
objective supports the government of the Philippines’ Department of Energy (DOE) Expanded Rural<br />
Electrification Program of relying in part on Independent Power Producers (IPP) and other private<br />
firms to co-finance and implement rural electrification projects.<br />
Scope of Work:<br />
The AMORE through MIRANT Foundation Philippines Inc., intends to procure for the supply,<br />
delivery, installation and the provision of warranty for 1,680 solar home systems for 56 barangays (30<br />
solar home systems/brgys) as specified in Mirant’s Program Plan of Action (PPOA).<br />
Functions and Responsibilities/Deliverables:<br />
A. WINROCK International- AMORE<br />
1. WI-AMORE shall provide the overall management and supervision of the Project<br />
Implementation;<br />
2. WI- AMORE shall facilitate bidding process and awarding of Contract;<br />
3. WI-AMORE shall provide technical assistance to the CONTRACTOR to implement the<br />
project.<br />
4. WI-AMORE shall provide the over-all system design and approve installation and security<br />
plans of the CONTRACTOR; and,<br />
5. WI-AMORE shall commission all installed PV systems.
Role of the CONTRACTOR:<br />
1. Supply, delivery and installation of 20 Wp Solar Home Systems<br />
Solar PV systems are to be installed at identified barangays and households. Each<br />
installation shall be undertaken according to the technical specifications provided and the<br />
provision of documentation (e.g., PV Solar Home System Manuals, etc)<br />
System description: A typical PV system diagram and its details is attached hereto as<br />
Technical Specifications (see Attachment A);<br />
2. CONTRACTOR shall provide the necessary manpower and logistical support to<br />
undertake its tasks;<br />
3. CONTRACTOR shall supervise all works being done;<br />
4. CONTRACTOR shall provide manuals for operations & maintenance and warranty<br />
coverage of equipment. (see Attachment A);<br />
5. CONTRACTOR shall provide Insurance and Performance Bond;<br />
6. CONTRACTORs shall provide a total of 56 sets of Technician’s tools and measuring<br />
instruments necessary in the operation and maintenance of the project (1 set per barangay)<br />
(see Attachment B);<br />
7. CONTRACTOR shall provide for the warehousing, securities of delivered materials/PV<br />
systems and delivery at project site (see Attachment C);<br />
8. CONTRACTOR shall allow authorized representatives of Mirant Foundation Philippines,<br />
USAID and/or WI – AMORE to inspect the said PV systems before delivery at site and<br />
target area; and provide necessary replacement of PV components should inspection<br />
results warrants it;<br />
9. CONTRACTOR shall provide all documentation requirement (e.g., Completion Report,<br />
local licenses and fees, transporation of hazardous materials, etc) that are deemed<br />
necessary by Mirant Foundation Philippines and or other Environmental Offices; and<br />
subsequently shoulder the expenses for this activity;<br />
10. CONTRACTOR shall provide health, safety, environment and security plan in the PV<br />
system installation;<br />
11. CONTRACTOR shall coordinate with Winrock International – AMORE Manila office or<br />
AREA Offices prior installation of PV systems;<br />
12. CONTRACTOR shall perform quarterly monitoring and repair of all installed PV solar<br />
home systems after the commissioning of the PV systems for a period of one (1) year; and,
13. CONTRACTOR shall coordinate with AMORE Area Offices prior conducting monitoring<br />
activities<br />
B. Number and location of systems<br />
The PV Solar Home Systems are to be installed individually in identified households per<br />
barangays. The identification of beneficiaries shall be coordinated with AMORE Area<br />
Offices prior to installation.<br />
A total of 1,680 PV Solar Home Systems are to be delivered and installed in 56 Barangays.<br />
The identified barangays are shown in Attachment C.<br />
C. Documentation<br />
Documentation, as set out in the Technical Specifications (Attachment A) should be provided<br />
in each system installed.<br />
D. Delivery Schedule and Inspection<br />
The CONTRACTOR will perform the scope of work and other related activities within 30<br />
days upon signing of contract. (Batch 1)<br />
Inspection and testing of PV SHS and its components will be conducted (MANILA) by<br />
authorized representative of WI-AMORE and/or MIRANT Foundation Philippines and/or<br />
USAID. There will also be another inspection at designated warehouse (ARMM Site) prior to<br />
delivery at site (barangays).<br />
E. After Sales Services<br />
After commissioning, the CONTRACTOR shall perform after-sales service for a period of<br />
one year. The following after sales services shall be provided:<br />
• Warranty<br />
• Routine maintenance (quarterly)<br />
• Break-down repair service<br />
F. System Warranty<br />
Performance warranty: The supplier must provide a performance warranty for the SHS installed<br />
in the Project’s beneficiary’s premises. The warranty period is one (1) year for the complete SHS<br />
unit from the day the Customer accepts the system (date of signing the Acceptance/Commissioning<br />
Document), with the exception that there is no warranty for light bulbs/tubes and fuses.<br />
Warranty service: During the warranty period the supplier will replace or repair any defective<br />
component that is under warranty at no cost to the Project due to failures caused by defects in<br />
manufacturing, faulty parts or improper installation. In particular,
a. Photovoltaic module: The photovoltaic module if defective will be replaced at no cost to the<br />
Project. The module is considered defective if its output under standard test conditions drops by<br />
more than ten percent (10%) of its rated value during the 10-year warranty period.<br />
b. Controller: The controller will be replaced if it fails during the warranty period.<br />
c. Battery: The battery will be replaced if its amp-hour capacity drops below 80 percent of the<br />
rated amp-hour capacity during the warranty period provided it has been used in accordance with<br />
the User’s Manual.<br />
d. Light fixtures: Light fixtures which fail during the warranty period will be replaced.<br />
e. Switches: Switches which fail during the warranty period will be replaced.<br />
f. Socket outlet: The socket outlet will be replaced if it fails during the warranty period.<br />
G. Voiding the warranty<br />
The warranty will become void if the SHS is not operated and maintained properly as described in<br />
the User’s Manual, or if the system or its components have been tampered with or modified. The<br />
latter include attempting to modify any component or function, bypassing the controller and<br />
connecting loads directly to the battery, short circuiting the battery terminals, disabling the fuses,<br />
using the SHS to operate heavy-duty appliances such as electric irons, adding anything other than<br />
distilled water to the battery and breaking the glass cover on the module.
ATTACHMENT A<br />
TECHNICAL SPECIFICATION
ATTACHMENT B<br />
LIST <strong>OF</strong> TECHNICIAN’S TOOLS
Technician’s tools:<br />
Particulars Unit<br />
1. Digital Multimeter – 20A current rating , 100VDC, 500 VAC<br />
1 unit<br />
2. Hydrometer<br />
3. Plier<br />
2 units<br />
a. Electrical plier 1 unit<br />
b. Side cutter 1 unit<br />
c. Long nose 1 unit<br />
4. Set of screwdriver<br />
a. Flat<br />
b. Phillips<br />
1 set<br />
5. Adjustable wrench (for battery interconnection) 1 unit<br />
6. Steel brush 1 unit