24.08.2013 Views

Final ESR - Part 2 - Eskom

Final ESR - Part 2 - Eskom

Final ESR - Part 2 - Eskom

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

REVISED FINAL ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED COMBINED CYCLE GAS<br />

TURBINE (CCGT) POWER PLANT IN THE AMERSFOORT AREA, MPUMALANGA PROVINCE<br />

Photograph 8.1 Panoramic views of the rural landscape in the Majuba area<br />

8.4.2 Methodology<br />

This project has been undertaken as a desktop study involving the following:<br />

• Data Processing - processing of data in the existing GIS project;<br />

• Data Analysis- viewshed analysis of all three sites;<br />

• Map Production- create maps of Scoping sites and create maps of viewshed analysis;<br />

• Photographs - create panoramic views of existing photographs; and<br />

• Interpretation - interpretation of GIS data, maps and photographs.<br />

8.4.3 Potential Visual Impacts<br />

Due to the large footprint and vertical dimensions of the proposed CCGT power plant, and the<br />

predominantly flat topography of the region, it becomes apparent that the facility would be<br />

well exposed. The issues relating to visual impact are the following:<br />

• Visibility<br />

• Proximity<br />

• Exposure<br />

POTENTIAL IMPACTS ON THE SOCIAL<br />

ENVIRONMENTAL<br />

106<br />

11/08/2008

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!