E C OE N E R G I A<br />
Total <strong>project</strong> <strong>in</strong>vestment budget<br />
ITEM DESCRIPTION VALUE<br />
1 Civil works 53.901.496<br />
2 Mechanical equipments 3.630.000<br />
3 Electrical and comunicational equipment 11.187.500<br />
4 Generation equipment 55.353.150<br />
5 Transmission l<strong>in</strong>e 11.385.000<br />
6 Environmental mitigation 2.018.450<br />
7 Community improvemnt works 300.000<br />
Total Construction Works 137.775.596<br />
8 Studies and designs 2.187.000<br />
9 Permits and licencess 675.000<br />
10 Environmental costs 1.155.000<br />
Pre-<strong>in</strong>vestment costs 4.017.000<br />
11 Eng<strong>in</strong>eer<strong>in</strong>g and adm<strong>in</strong>istration 8.248.525<br />
12 Prog. Qulified local employment access 890.550<br />
13 Cont<strong>in</strong>gency 5.998.229<br />
Cost <strong>of</strong> eng<strong>in</strong>eer<strong>in</strong>g and management<br />
15.137.30<br />
Total cost <strong>of</strong> the <strong>project</strong> 156.929.900