Case Study: Chongming, China. Mixshield ø15,600 mm.<br />
The biggest TBM in the <strong>World</strong>.<br />
A CHALLENGING TIME SCHEDULE.<br />
Start tunnelling<br />
S-317: November 2006<br />
S-318: January 2007<br />
Page 17 Rodrigo Stange – Sales Manager Latin Ameirca – Traffic Tunneling – <strong>Herrenknecht</strong> AG<br />
In total 75,000 lining segments (16 t<br />
each) for 14,340 m of tunnel.<br />
Completion of tunnelling by late<br />
2008/ early 2009.<br />
Tunnel will be opened for the traffic<br />
in time for the <strong>World</strong> Expo 2010.