must be cleaned before the end of each workday. Street sweeping provides<br />
a mechanism for removal of loose soil materials, but may not be sufficient to<br />
remove materials compacted onto the roadway surfaces. Removal of such<br />
compacted materials during each workday and when required by the<br />
Administrator is also required. Removal of adhered soil materials will be done<br />
in a manner that does not damage the roadway or other right-of-way<br />
appurtenances.<br />
§ T300(n) Temporary Stream Crossings<br />
Temporary stream crossings (bridges, fords, and culvert crossings) should be<br />
designed for short-term use periods not to exceed 1 year. Temporary stream<br />
crossings are to be used only where there is no practicable alternative for<br />
moving heavy equipment from one side of a stream channel to another or<br />
where light duty equipment must cross a stream frequently for a very short<br />
period (