Work Area<br />
USAID Jordan Fiscal Reform II Project<br />
Planed<br />
delivery date<br />
Comments<br />
Other analytical training - intermittent 16-Oct-11 In Progress<br />
Implementation of Assessment Recommendations<br />
for the Public Debt Directorate (PDD) - Phase 2<br />
31-Oct-11<br />
DMFAS 6.0 software upgrade 31-Oct-11<br />
Clarify FRPII's role in upgrade plan 30-Dec-10 In Progress<br />
Agreement between USAID and MOF on terms of<br />
upgrade plan<br />
Implementation of DMFAS upgrade, once approved 31-Oct-11<br />
Technical support for software upgrade, as needed 31-Oct-11<br />
Training for staff, as needed 31-Oct-11<br />
Support work on developing Medium Term Debt<br />
Strategy<br />
Working Group (WG) assigned to include PDD<br />
counterparts and FRPII members<br />
31-Jan-11 In Progress<br />
4-Apr-11<br />
4-Nov-10 Completed<br />
Develop action plan and initiate work on Strategy 28-Feb-11 Completed<br />
Intermittent technical support, if needed by working group 27-Feb-11 Completed<br />
First draft of Strategy completed and submitted for<br />
feedback/ approval<br />
1-Mar-11 Completed<br />
Finalize Strategy based on feedback 3-Apr-11 Completed<br />
Submit final Document 4-Apr-11 In Progress<br />
Capacity building and re-organization 31-Oct-11<br />
Approval from counterparts on re-organization plan 4-Nov-10 Completed<br />
Support re-organization and strengthening of middle<br />
office<br />
31-Oct-11 In Progress<br />
Identify training needs 14-Jul-11 In Progress<br />
Design and preparatory work 10-Mar-11 Completed<br />
Training at MOF Training Center 17-Mar-11 In Progress<br />
Out-of-Country Training 14-Jul-11 Completed<br />
International Borrowing and Debt Management Training 15-May-11 Completed<br />
Other training as needed 14-Jul-11 In Progress<br />
Advancing the Training Center capacities, utilization<br />
and reputation<br />
31-Oct-11<br />