USAID Jordan Fiscal Reform II Project<br />
Planed<br />
delivery date<br />
Golden list (GL) 28-Jun-11<br />
Comments<br />
Jordan customs (re-launch of GL conditions and benefits) 5-Apr-11 Delayed<br />
Formation of GL workgroup 23-Nov-10 Completed<br />
Review existing GL requirements and incentives, (in light<br />
of GL survey carried out in Y1)<br />
4-Jan-11 In progress<br />
Draft new requirements and incentives 30-Mar-11 In progress<br />
Conduct study tour for JC and PGA's 5-Apr-11 Planning stage<br />
New Requirements and incentives (<strong>Report</strong>) 30-Mar-11 Delayed<br />
JSMO (introducing GL, study and conditions) 29-May-11<br />
Introduce GL concept to JSMO 29-Dec-10 In progress<br />
Formation of GL workgroup 18-Jan-11 In progress<br />
Assessment of requirement to initiate GL program at<br />
JSMO<br />
Work Plan 29-May-11<br />
FDA (introducing GL, study and conditions) 28-Jun-11<br />
2-Mar-11 In progress<br />
Introduce GL concept to FDA 30-Jan-11 In progress<br />
Formation of GL workgroup 20-Feb-11 In progress<br />
Assessment of requirement to initiate GL program at FDA 3-Apr-11 In progress<br />
Draft a work plan for establishing GL program at FDA 28-Jun-11<br />
Work Plan 28-Jun-11<br />
Single window 31-Oct-11<br />
Single Window Master Plan 8-Mar-11<br />
Form planning work group 12-Jan-11 Completed<br />
Draft and presentation of workplan 8-Mar-11 In progress<br />
Attend WCO data committee in brussels 26-Jan-11 Completed<br />
Final Draft SW WP 24-Feb-11 Delayed<br />
Communications and outreach strategy for JSW 6-Jun-11<br />
<strong>Report</strong> Communications and outreach for JSW 6-Jun-11<br />
Advisory on SW initiatives 31-Oct-11 In progress<br />
USAID Fiscal Reform II Project, <strong>Quarterly</strong> <strong>Report</strong> – <strong>February</strong> – <strong>April</strong> <strong>2011</strong> 51