01.01.2014 Views

The Project Risk Maturity Model

The Project Risk Maturity Model

The Project Risk Maturity Model

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

12 T h e P r o j e c t R i s k M a t u r i t y M o d e l<br />

100%<br />

Level 4<br />

75%<br />

Level 3<br />

50%<br />

Level 2<br />

25%<br />

Level 1<br />

Stakeholders <strong>Risk</strong> <strong>Risk</strong> <strong>Risk</strong> <strong>Project</strong> Culture<br />

Identification Analysis Responses Management<br />

Figure 1.5<br />

<strong>Project</strong> RMM assessment results for <strong>Project</strong> A<br />

An early pass of this analysis suggested a probable schedule slip of 5–15 days. Lessons<br />

learned from this analysis were then used to introduce planning improvements and<br />

additional risk mitigation. Two further passes of this analysis were undertaken, after<br />

which the plan was considered to be sufficiently robust. This was an excellent example of<br />

how a schedule risk analysis should be used; the process enabled the team to rehearse the<br />

project delivery and understand how best to respond to events that could arise. During<br />

a post-project lessons learned exercise, risk management was identified as having been a<br />

major factor that enabled the project to meet its objectives.<br />

Given the success of risk management on <strong>Project</strong> A, one could ask whether or not<br />

the <strong>Project</strong> RMM assessment should have been Level 4 rather than Level 3. <strong>The</strong> answer<br />

is that this is an example of the fact that, sometimes, a Level 3 project risk management<br />

capability is sufficient to achieve an organisation’s objectives. Although <strong>Project</strong> A was<br />

large (approximately £50M), it was not particularly complex. As an internal project, it also<br />

had simple relationships with its stakeholders. Moreover, a project of this type was not<br />

new to the company concerned; it owned similar production plants and the same plant<br />

had been renewed 13 years previously. Finally, there were no incentives for members of<br />

the project team to make biased risk estimates. <strong>The</strong> sponsor had made a shrewd estimate<br />

of where to set objectives that were challenging, yet realistic and the project team knew<br />

that they would be judged by results, not forecasts.<br />

<strong>The</strong> main reason for the risk management process falling short of Level 4 capability<br />

is that it had only a limited effect on the project strategy. For example, the schedule and<br />

cost objectives were set prior to the introduction of risk management. <strong>The</strong>re was also<br />

no risk-based evidence that the project could live within its budget. For the company<br />

that sponsored <strong>Project</strong> A, these were minor issues. On more complex projects or when<br />

estimating bias or when conflicts of interest are potential causes of difficulty, a project<br />

RMM less than Level 4 would be more of a concern.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!