01.01.2014 Views

The Project Risk Maturity Model

The Project Risk Maturity Model

The Project Risk Maturity Model

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

14 T h e P r o j e c t R i s k M a t u r i t y M o d e l<br />

to be so pessimistic that the modelling must be wrong. All the report’s recommendations<br />

were then quietly forgotten. As it would turn out, actual schedule performance proved to<br />

be much worse.<br />

As the condition of the project grew progressively worse, efforts were made to use the<br />

risk register to identify and manage actions for risk mitigation. Unfortunately these efforts<br />

lacked true support from the project manager. <strong>Risk</strong> reviews were invariably cancelled in<br />

favour of new emergencies. Support for the process was similarly lacking from the other<br />

organisations involved, including the customer and the major subcontractor. <strong>The</strong>re was<br />

general reluctance on the part of the project leaders to tackle risks at source. To do so it<br />

would have been necessary to admit to past mistakes. Survival in project management<br />

jobs required a style that combined energetic fire fighting with the type of cunning that<br />

enables people to forecast success and then avoid blame for failure. <strong>The</strong> development<br />

phase of this project eventually slipped by more than three years: doubling the original<br />

plan.<br />

<strong>The</strong> case of <strong>Project</strong> B illustrates a number of symptoms that may be associated with<br />

Level 1 risk management capability. Forecasts from a cost risk analysis designed to fulfil<br />

a director’s expectations can be worse than useless. If the calculations are unnecessarily<br />

high, the project manager is liable to either spend unnecessarily or claim disproportionate<br />

credit for their performance. More commonly a director’s expectations will be optimistic.<br />

If the risk calculations are optimistically biased in response, the owning organisation will<br />

have late notice of financial issues. In the case of <strong>Project</strong> B, the company’s accountants<br />

were later forced to back trade the project’s contribution to profits. But, perhaps the<br />

most important lesson to be learned from <strong>Project</strong> B is that an effective risk management<br />

process requires continuous and constructive support from managers at all levels. <strong>The</strong><br />

project had the knowledge and resources to manage risk much more effectively, but the<br />

benefits of this were never realised.<br />

Correlation between <strong>Project</strong> Performance and RMM<br />

Assessments<br />

Comparing examples such as <strong>Project</strong> A and B is not untypical of experience to date when<br />

making RMM assessments. <strong>Project</strong>s with higher RMM assessments do seem to be more<br />

capable of achieving their objectives. <strong>The</strong>y also tend to have relatively good reputations<br />

for being good projects to work in. Further evidence for there being a correlation between<br />

project performance and RMM assessments is discussed in Chapter 4: the UK Defence<br />

Procurement case study.<br />

Assessing the Process as it is Applied in Practice<br />

It is one thing to design an effective risk management process. It is another thing to carry<br />

through the process in practice. Even the best-designed process can be rendered ineffective<br />

if it is not implemented as intended. <strong>The</strong> contrast between the example projects A and B<br />

illustrates this point. By working to the process as designed, <strong>Project</strong> A was able to achieve<br />

a higher level of capability than <strong>Project</strong> B. This was despite the fact that <strong>Project</strong> B had the<br />

means to do as well, if not better.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!